A Portfolio Approach to IT Projects - PowerPoint PPT Presentation

1 / 44
About This Presentation
Title:

A Portfolio Approach to IT Projects

Description:

... World Dictionary of the American Language (1979, Simon & Schuster, New York, NY) ... tools developed or purchased for the project will fail in some fashion ... – PowerPoint PPT presentation

Number of Views:96
Avg rating:3.0/5.0
Slides: 45
Provided by: raytry
Category:

less

Transcript and Presenter's Notes

Title: A Portfolio Approach to IT Projects


1
A Portfolio Approach to IT Projects
  • MIS 6413 Management Information Systems
  • Fall 2005 Dr. Richard S. Segall
  • Chapter 10 Lecture Notes

2
Introduction
  • Today we will examine
  • IT portfolio management

3
INTRODUCTION
1
  • Source of Implementation Risk
  • Project Categories and Degrees of Risk
  • Project Management A contingency approach
  • Concluding Thoughts

4
Objectives
  • At the conclusion of this lesson, the student
    should be able to
  • Explain what IT Portfolio Management is
  • Describe three steps used to implement IT
    Portfolio Management
  • Discuss risks associated with IT projects and
    risk mitigation

5
What is Portfolio Management?
  • A methodology for ensuring every product in an IT
    organizations portfolio is analyzed for risk and
    return
  • If the risk is too great or the reward too
    little, the project doesnt get funded.
    Doug Hubbard Hubbard Decision
    Research Glen Ellyn

6
Sources of Implementation Risk p.580-581
  • Project Size
  • Experience with Technology
  • Project Structure

7
Three Steps
  • Step 1 List every IT project in the enterprise,
    including resource requirements stated
    objectives
  • Step 2 Evaluate each project for risk return
  • Step 3 Ongoing risk assessment
  • Continually reassess risks as project progresses

8
Risk Matrix
High
Project Risk
Low
High
Investment Return
9
(No Transcript)
10
(No Transcript)
11
Project Categories and Degrees Of Risk p.581-585
  • Assessing Risk for Individual Projects
  • Large Project vs. Small Project
  • Low Structure vs. High Structure
  • Low Company-relative technology
  • High Company-relative technology
  • Risk Assessment Questionnaire Figure 10.3 on page
    583.

12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
Step 1 List Projects
  • Determine what projects are in progress
  • Create a database containing all pertinent data
    on each project
  • Determine what tools and resources are in use on
    these projects
  • Hopefully will reveal duplication of effort and
    poor use of resources

16
Tools Resources
  • Complete knowledge of resources available
    requires strong asset management program
  • Knowing what IT resources are already on hand
    should facilitate intelligent reuse and eliminate
    purchase of items already held
  • Allows better grasp of technology resources the
    company has already invested in for planning and
    resource management

17
Tools Resources
  • Knowledge of what tools resources are in use in
    each project should eliminate redundancy
  • One bank, using IT portfolio management,
    discovered four divisions doing four CRM
    projects, one with a different application then
    the other three, and huge duplication of effort
  • Resource capacity should also be considered
  • One project may require only half the capacity of
    a server purchased for the project, freeing the
    rest for use by another project

18
Dont Stop at Step One!
  • Many enterprises are so pleased with the results
    of the first step they never take IT Portfolio
    Management any further
  • Evaluation of projects for risk and return will
    save far more than merely coordinating asset use
    and eliminating duplicate efforts

19
Risk
  • The chance of injury, damage, or loss Webster's
    New World Dictionary of the American Language
    (1979, Simon Schuster, New York, NY)
  • The National Academy of Sciences defines risk as
    a combination of the probability of an
    eventusually an adverse eventand the nature and
    severity of the event.

20
Inherent Risk Factors p.579-580
  • Project size
  • The bigger they are, the harder they fall!
  • Experience with technology
  • Project structure
  • High- or low-structure project

21
Components of Risk p.581-586
  • (1.) Portfolio Organizational risk p.585
  • e.g. Risk that organization will not manage
    change necessary to maximize projects value
  • (2.) Technological risk Fig 10.3 page 584
  • e.g. Tech tools developed or purchased for the
    project will fail in some fashion
  • (3.) Project management risk p.585
  • e.g. Risk that project manager(s) will not have
    sufficient knowledge or experience

22
Top Three Risks
  • As identified by IT managers
  • Lack of top management commitment to the program
  • Failure to gain user commitment
  • Misunderstanding the requirements

23
Risk Assessment
  • A scientific process of evaluating the potential
    adverse effects caused by risks
  • Characterized by uncertainty
  • Uncertainty inherent in risk assessment because
    risk assessors cannot precisely describe most
    risks due to this, they should state the range
    of probabilities for harm for the risks that they
    have identified

24
Step 2 Risk Assessment
  • Using questionnaires and matrices, evaluate risk
    of project
  • The higher the risk assessment score, the more
    urgent that top management has a say in decision
    to implement the project
  • Three questions

25
Three Questions on Risk p.585
  • 1. Are the benefits great enough to offset the
    risk?
  • 2. Can affected parts of the organization survive
    if the project fails?
  • 3. Have planners considered appropriate
    alternatives?

26
Risk Factors
  • The project sponsor and/or the project manager
    does not recognize that every project is a risk
    exercise.
  • This project is very different from the last one.
  • There is a feeling of uneasiness.
  • When the project is in its earliest phase,
    project risk and uncertainty are highest.
  • The project scope, objectives and deliverables
    are not clearly defined or understood.

Norton, Joe Mitigating Risk in Technology
Investments through IT Portfolio Management,
www.teradata.com/executive/b_tech_portfolio_series
.asp
27
Risk Factors
  • A large number of alternatives are perceived as
    possible.
  • Some or all technical data is lacking.
  • The technical process and design are not mature.
  • Standards for performance are unrealistic or are
    absent.
  • Costs, schedules and performance are not
    expressed in ranges.

28
Risk Factors
  • The future timing of activities and events are
    vague.
  • Design lacks production engineering input.
  • Prototype of a key element is missing.
  • There is a higher than usual RD component.
  • Some or all environmental permits are lacking.
  • Other similar projects have been delayed or
    cancelled.

29
Risk Factors
  • Wide variations in bids are received.
  • Some key subsystems and/or materials are sole
    source.
  • No appropriate contingency plans have been
    developed.
  • The project team relies entirely on the
    contingency allowance.
  • Someone starts hedging their bets!

30
Quadrant Risk Mapping
High
Probability of Risk Event
Low
High
Severity of Consequences
Jeffery, Mark Mitigating Risk in Technology
Investments through IT Portfolio Management,
www.teradata.com/executive/b_tech_portfolio_series
.asp
31
Assignment of Risk Value
  • Identify which quadrant each risk belongs in
  • Give greatest attention to resolution of risks in
    upper right quadrant
  • If risks cannot be mitigated, abandon project

32
Return
  • Should be predicated on long term benefit
  • Can get bogged down in ROI
  • Especially short-term
  • Big IT projects are infrastructure and unlikely
    to have impact on quarterly profit
  • Benefits not all ROI, but some experts believe
    all returns can be measured

33
Portfolio Risk p.585-586
  • What percentage of projects in the portfolio are
    high risk?
  • What proportion of high risk projects are
    acceptable to the organization?
  • Percentage will vary widely based on type of
    organization
  • High percentages may be acceptable in IT firms
    but percentages should be low for, as an example,
    banks

34
Step 3 Ongoing Risk Assessment
  • Reassess risk throughout duration of project
  • Examine not only risk of project failure but
    impact on overall project portfolio as well
  • Key concern is value to organization
  • On time, under budget does little good if the
    intended value to the business is not delivered

35
Levels of IT Portfolio Management
  • IT asset project inventory
  • Identify needs in the organization
  • Align IT Portfolio with organizational strategy
  • Match strategy with concrete IT objectives
  • Automate the ITPM process

Jeffery, Mark Unlocking the Value from Your IT
Investments with Technology Portfolio Management,
www.teradata.com/executive/b_tech_portfolio_series
.asp
36
Project Management A Contingency Approach
  • Management Tools
  • External Integration Tools
  • Internal Integration Devices
  • Formal Planning Tools (Project manager, COCOMO,
    CPM)
  • Formal Results Control Mechanisms

37
(No Transcript)
38
Project Management A Contingency Approach (Cont.)
  • Influences on Tool selection
  • High Structure/Low technology projects
  • High Structure/High Technology projects
  • Low Structure/Low Technology projects
  • Low Structure/High Technology projects
  • Relative Contribution of management Tools
  • Emergence of Adaptive Project Management Methods

39
(No Transcript)
40
Systems Development
  • SDLC System Development Life Cycle
  • Rapid Systems Development
  • Prototyping
  • Adaptive Methodologies
  • Adaptive Methods and Change Management
  • Software Configuration Management

41
Business Strategy ? IT Strategy
  • Properly applied, IT portfolio management is a
    key component in aligning IT strategy with
    business strategy
  • Alignment of IT strategy will allow ongoing
    reassessment of IT portfolio, allowing dumping of
    non-performing on unused assets

42
Bottom Line IT is a Business
  • Process consistency and agility in Project
    management
  • A Minimalist Approach to process Formalization
  • Flow
  • Completeness
  • Visibility

43
The End
  • Questions?
  • Discussion!

44
A Portfolio Approach to IT Projects
  • MIS 6413 Management Information Systems
  • Fall 2005 Dr. Richard S. Segall
  • Chapter 10 Lecture Notes
Write a Comment
User Comments (0)
About PowerShow.com