Title: A Portfolio Approach to IT Projects
1A Portfolio Approach to IT Projects
- MIS 6413 Management Information Systems
- Fall 2005 Dr. Richard S. Segall
- Chapter 10 Lecture Notes
2Introduction
- Today we will examine
- IT portfolio management
3INTRODUCTION
1
- Source of Implementation Risk
- Project Categories and Degrees of Risk
- Project Management A contingency approach
- Concluding Thoughts
4Objectives
- At the conclusion of this lesson, the student
should be able to - Explain what IT Portfolio Management is
- Describe three steps used to implement IT
Portfolio Management - Discuss risks associated with IT projects and
risk mitigation
5What is Portfolio Management?
- A methodology for ensuring every product in an IT
organizations portfolio is analyzed for risk and
return - If the risk is too great or the reward too
little, the project doesnt get funded.
Doug Hubbard Hubbard Decision
Research Glen Ellyn
6Sources of Implementation Risk p.580-581
- Project Size
- Experience with Technology
- Project Structure
7Three Steps
- Step 1 List every IT project in the enterprise,
including resource requirements stated
objectives - Step 2 Evaluate each project for risk return
- Step 3 Ongoing risk assessment
- Continually reassess risks as project progresses
8Risk Matrix
High
Project Risk
Low
High
Investment Return
9(No Transcript)
10(No Transcript)
11Project Categories and Degrees Of Risk p.581-585
- Assessing Risk for Individual Projects
- Large Project vs. Small Project
- Low Structure vs. High Structure
- Low Company-relative technology
- High Company-relative technology
- Risk Assessment Questionnaire Figure 10.3 on page
583.
12(No Transcript)
13(No Transcript)
14(No Transcript)
15Step 1 List Projects
- Determine what projects are in progress
- Create a database containing all pertinent data
on each project - Determine what tools and resources are in use on
these projects - Hopefully will reveal duplication of effort and
poor use of resources
16Tools Resources
- Complete knowledge of resources available
requires strong asset management program - Knowing what IT resources are already on hand
should facilitate intelligent reuse and eliminate
purchase of items already held - Allows better grasp of technology resources the
company has already invested in for planning and
resource management
17Tools Resources
- Knowledge of what tools resources are in use in
each project should eliminate redundancy - One bank, using IT portfolio management,
discovered four divisions doing four CRM
projects, one with a different application then
the other three, and huge duplication of effort - Resource capacity should also be considered
- One project may require only half the capacity of
a server purchased for the project, freeing the
rest for use by another project
18Dont Stop at Step One!
- Many enterprises are so pleased with the results
of the first step they never take IT Portfolio
Management any further - Evaluation of projects for risk and return will
save far more than merely coordinating asset use
and eliminating duplicate efforts
19Risk
- The chance of injury, damage, or loss Webster's
New World Dictionary of the American Language
(1979, Simon Schuster, New York, NY) - The National Academy of Sciences defines risk as
a combination of the probability of an
eventusually an adverse eventand the nature and
severity of the event.
20Inherent Risk Factors p.579-580
- Project size
- The bigger they are, the harder they fall!
- Experience with technology
- Project structure
- High- or low-structure project
21Components of Risk p.581-586
- (1.) Portfolio Organizational risk p.585
- e.g. Risk that organization will not manage
change necessary to maximize projects value - (2.) Technological risk Fig 10.3 page 584
- e.g. Tech tools developed or purchased for the
project will fail in some fashion - (3.) Project management risk p.585
- e.g. Risk that project manager(s) will not have
sufficient knowledge or experience
22Top Three Risks
- As identified by IT managers
- Lack of top management commitment to the program
- Failure to gain user commitment
- Misunderstanding the requirements
23Risk Assessment
- A scientific process of evaluating the potential
adverse effects caused by risks - Characterized by uncertainty
- Uncertainty inherent in risk assessment because
risk assessors cannot precisely describe most
risks due to this, they should state the range
of probabilities for harm for the risks that they
have identified
24Step 2 Risk Assessment
- Using questionnaires and matrices, evaluate risk
of project - The higher the risk assessment score, the more
urgent that top management has a say in decision
to implement the project - Three questions
25Three Questions on Risk p.585
- 1. Are the benefits great enough to offset the
risk? - 2. Can affected parts of the organization survive
if the project fails? - 3. Have planners considered appropriate
alternatives?
26Risk Factors
- The project sponsor and/or the project manager
does not recognize that every project is a risk
exercise. - This project is very different from the last one.
- There is a feeling of uneasiness.
- When the project is in its earliest phase,
project risk and uncertainty are highest. - The project scope, objectives and deliverables
are not clearly defined or understood.
Norton, Joe Mitigating Risk in Technology
Investments through IT Portfolio Management,
www.teradata.com/executive/b_tech_portfolio_series
.asp
27Risk Factors
- A large number of alternatives are perceived as
possible. - Some or all technical data is lacking.
- The technical process and design are not mature.
- Standards for performance are unrealistic or are
absent. - Costs, schedules and performance are not
expressed in ranges.
28Risk Factors
- The future timing of activities and events are
vague. - Design lacks production engineering input.
- Prototype of a key element is missing.
- There is a higher than usual RD component.
- Some or all environmental permits are lacking.
- Other similar projects have been delayed or
cancelled.
29Risk Factors
- Wide variations in bids are received.
- Some key subsystems and/or materials are sole
source. - No appropriate contingency plans have been
developed. - The project team relies entirely on the
contingency allowance. - Someone starts hedging their bets!
30Quadrant Risk Mapping
High
Probability of Risk Event
Low
High
Severity of Consequences
Jeffery, Mark Mitigating Risk in Technology
Investments through IT Portfolio Management,
www.teradata.com/executive/b_tech_portfolio_series
.asp
31Assignment of Risk Value
- Identify which quadrant each risk belongs in
- Give greatest attention to resolution of risks in
upper right quadrant - If risks cannot be mitigated, abandon project
32Return
- Should be predicated on long term benefit
- Can get bogged down in ROI
- Especially short-term
- Big IT projects are infrastructure and unlikely
to have impact on quarterly profit - Benefits not all ROI, but some experts believe
all returns can be measured
33Portfolio Risk p.585-586
- What percentage of projects in the portfolio are
high risk? - What proportion of high risk projects are
acceptable to the organization? - Percentage will vary widely based on type of
organization - High percentages may be acceptable in IT firms
but percentages should be low for, as an example,
banks
34Step 3 Ongoing Risk Assessment
- Reassess risk throughout duration of project
- Examine not only risk of project failure but
impact on overall project portfolio as well - Key concern is value to organization
- On time, under budget does little good if the
intended value to the business is not delivered
35Levels of IT Portfolio Management
- IT asset project inventory
- Identify needs in the organization
- Align IT Portfolio with organizational strategy
- Match strategy with concrete IT objectives
- Automate the ITPM process
Jeffery, Mark Unlocking the Value from Your IT
Investments with Technology Portfolio Management,
www.teradata.com/executive/b_tech_portfolio_series
.asp
36Project Management A Contingency Approach
- Management Tools
- External Integration Tools
- Internal Integration Devices
- Formal Planning Tools (Project manager, COCOMO,
CPM) - Formal Results Control Mechanisms
37(No Transcript)
38Project Management A Contingency Approach (Cont.)
- Influences on Tool selection
- High Structure/Low technology projects
- High Structure/High Technology projects
- Low Structure/Low Technology projects
- Low Structure/High Technology projects
- Relative Contribution of management Tools
- Emergence of Adaptive Project Management Methods
39(No Transcript)
40Systems Development
- SDLC System Development Life Cycle
- Rapid Systems Development
- Prototyping
- Adaptive Methodologies
- Adaptive Methods and Change Management
- Software Configuration Management
41Business Strategy ? IT Strategy
- Properly applied, IT portfolio management is a
key component in aligning IT strategy with
business strategy - Alignment of IT strategy will allow ongoing
reassessment of IT portfolio, allowing dumping of
non-performing on unused assets
42Bottom Line IT is a Business
- Process consistency and agility in Project
management - A Minimalist Approach to process Formalization
- Flow
- Completeness
- Visibility
43The End
44A Portfolio Approach to IT Projects
- MIS 6413 Management Information Systems
- Fall 2005 Dr. Richard S. Segall
- Chapter 10 Lecture Notes