(g-2) Timeline and Resources
  • CAD Presentation

B. Lee Roberts Department of Physics Boston
University
roberts_at_bu.edu http//physics.bu.edu/robert
s.html
2
E969
Osaka University
3
(No Transcript)
4
Strategy of the improved experiment
  • More muons E821 was statistics limited
    sstat 0.46 ppm, ssyst 0.3 ppm
  • Backward-decay, higher-transmission beamline
  • New, open-end inflector
  • Upgrade detectors, electronics, DAQ
  • Improve knowledge of magnetic field B
  • Improve calibration, field monitoring and
    measurement
  • Reduce systematic errors on ?a
  • Improve the electronics and detectors
  • New parallel integration method of analysis

5
Schedule (as presented to PAC in 04)
  • FY 2005
  • RD as funding permits
  • FY 2006-2007
  • Construction
  • FY 2008
  • Fall, pulse on demand, debugging
  • Spring, 3 week engineering run
  • FY 2009
  • 2100 hours data collection
  • (26 weeks _at_ 80 hr/wk)

6
New Hardware and Other Tasks
  • Beamline
  • New front-end magnets Quads Dipoles
  • BNL Responsibility (Wuzheng Meng)
  • Beamline simulations
  • BNL Responsibility (Phil Pile?) with help from U.
    Illinois
  • Inflector
  • New inflector with open ends
  • Japanese (Tokin) have agreed to make it, all they
    need is / (Wuzheng Meng and Akira Yamamoto)
  • Storage Ring Magnet
  • Needs to be put back in operating order
  • BNL Responsibility
  • Vacuum System
  • Needs to be put back in operating order
  • BNL Responsibility (Dick Hseuh)

7
New Hardware ctd. -2
  • Quadrupoles
  • Need to be put back into working order
  • BNL Responsibility (Yannis Semertzidis)
  • Kicker
  • Needs modifications to lower inductance and
    increase peak current
  • Kicker 1s failure needs to be understood
  • BNL Responsibilities (Arlene Zhang? D. Warburton,
    J. Mi? BLR)
  • Proper GEANT-based Tracking Program
  • Boston Responsibility

8
New Hardware ctd. -3
  • CBO damping system
  • RF Dipole
  • (or)
  • Pulsed Octupole
  • Needs simulations, engineering design
  • Responsibility to be determined, but BNL at
    present (Oxford???)
  • Precision Magnetic Field
  • New calibration probe
  • Better field monitoring and control
  • Better shimming
  • University Collaborators Responsibility

9
New Hardware ctd. -4
  • Detectors
  • New electron calorimeters
  • University Collaborators Responsibility
  • Front-end Electronics
  • New WFDs
  • University Collaborators Responsibility

10
Collaboration Resources
  • Boston University Scientific Instrument Facility
    (underutilized at present)
  • Resources
  • 7 full-time machinists
  • State of the art CNC machining capabilities
  • High Vacuum Welding Capabilities
  • Collaborative Rate 35/hr
  • We produced 1M of parts for E821 _at_
    30 - 35/hr plus materials
  • We expect to use this resource for E969.
  • We can make pole pieces for new beamline magnets,
    vacuum chamber or kicker parts, etc.

11
Collaboration Resources
  • Boston University Electronics Design Facility
  • Resources
  • 3 full-time engineers
  • State of the art electronics design capabilities
  • University of Illinois Nuclear Physics Laboratory
  • Resources
  • Two mechanical technicians
  • Machine shop facilities comparable to BU

12
Modified Schedule
  • FY 2006
  • P5 Approval
  • RD as funding permits
  • FY 2007-2008
  • Finish RD
  • Construction
  • FY 2009
  • Fall, pulse on demand, debugging
  • Spring, 3 week engineering run
  • FY 2010
  • 2100 hours data collection
  • (26 weeks _at_ 80 hr/wk)

13
Summary
  • We would hope for first beam in 2009
  • Production run in 2010
  • The Collaboration is ready to go full speed ahead
    if we get approval next spring