MidPoint Review Report - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

MidPoint Review Report

Description:

All wires have been sauntered and connected. Both alarms have ... Waiting for quotation from Burkert Fluid Controls for pneumatically actuated cryogenic valve ... – PowerPoint PPT presentation

Number of Views:72
Avg rating:3.0/5.0
Slides: 17
Provided by: Jab9
Learn more at: https://eng.fsu.edu
Category:

less

Transcript and Presenter's Notes

Title: MidPoint Review Report


1
  • Mid-Point Review Report
  • 900 MHz NMR Probe Cryogenic Gas Supply System
  • Team 2
  • Rebecca Altman
  • Jason Kitchen
  • Zachary Stevenson
  • Jessica Vanterpool
  • February 26th, 2009

2
Presentation Outline
  • Subsystem Testing
  • Temperature Variance
  • Mass Flow Controller
  • Pneumatic Actuator vs. Solenoid Valve
  • Future Testing
  • Future Plans

Team with Dr. Brey in front of 900 MHz magnet
3
Project Overview
4
Assembly Progress
  • Refill controller
  • All wires have been sauntered and connected
  • Both alarms have been added
  • Two pin connector for the solenoid valve has been
    added

Senior Design Group 2 900 MHz NMR Probe
Cryogenic Gas Supply System
5
Heat Exchanger Coil Testing
  • Increased the flow rate in increments of 5 scfh
  • 10 Minute Intervals
  • Ideal Flow Rate is 60 scfh
  • Very high pressure readings before 40 scfh
    (debris)
  • Droplets at 65 scfh, temperature at 78.1 K
  • Results
  • Experimentally T 84.7 K (With possible
    debris)
  • Theoretically T 79.3 K (Did not take debris
    into consideration)
  • Within required range, perform experiment again
    for verification

Senior Design Group 2 900 MHz NMR Probe
Cryogenic Gas Supply System
6
Heat Exchanger Coil Testing Cont.
  • Flow Rate and Pressure vs. Temperature

Senior Design Group 2 900 MHz NMR Probe
Cryogenic Gas Supply System
7
Heat Exchanger Coil Testing Cont.
  • Equipment and Schematic Video

Senior Design Group 2 900 MHz NMR Probe
Cryogenic Gas Supply System
8
N2 Gas Flow Regulation Improvement
  • Current valve block in spectrometer has 15 valve
    setting combinations for N2 gas flow from 0 to
    2000 L/hr
  • Problem gas flow fluctuates with supply
    pressure changes, which leads to temperature
    fluctuation
  • Solution purchased a mass flow controller from
    Alicat Scientific, cost 1396.00
  • Features
  • Flow range is 0 to 50 L/min
  • Self adjusts for pressure changes using solenoid
    valve
  • Typical 100 ms response time
  • Accuracy 0.8 of reading
  • Repeatability 0.2
  • 30 pre-defined gases, including N2

9
Testing Progress
  • Nitrogen Dewar
  • Temperature variance test
  • Several refills were carried out at three
    different cryostat pressures (6,10,22 psig)
  • First the FTS system was set at -75 C
  • The N2 gas flow was set to 25 scfh during each
    refill
  • Temperature was also allowed to reach a steady
    state before each refill began
  • Digital thermometer used to record temperature
    reading at transfer line entrance

Liquid valve
Gas Valve
Senior Design Group 2 900 MHz NMR Probe
Cryogenic Gas Supply System
10
Testing Progress Cont.
  • Results
  • Less boil off at 6 psig, however there was a
    significant decrease in the refill rate and twice
    had to open the supply valve further to continue
    the refill
  • Pressure will have to be maintained to ensure a
    good refill rate
  • lower supply cryostat pressures will lower the
    effect of a refill on the output temp to the
    probe
  • Significant decrease in the amount of N2 vapor
    venting out of the HX each time the supply
    pressure was lowered

Senior Design Group 2 900 MHz NMR Probe
Cryogenic Gas Supply System
11
Solution Pneumatically Actuated Cryogenic Valve
  • Solenoid valve moved 15 m from magnet axis,
    outside of magnetic field
  • Solenoid now controls a pilot gas connected to
    pneumatic valve actuator
  • Pneumatic valve can be located inside magnetic
    field
  • Pneumatic actuation opens LN2 fill line to refill
    from supply dewar to HX cryostat

12
Purchase Summary
  • Waiting for quotation from Burkert Fluid Controls
    for pneumatically actuated cryogenic valve
  • Remaining purchases will be plumbing fittings for
    hookup of valves to supply Dewar and HX cryostat

13
Design Problem Refill Solenoid Valve Proximity
to Magnet
  • LN2 supply dewar must be within 3 m of the 900
    MHz magnets axis
  • Refill solenoid located here could eventually
    fail as it becomes permanently magnetized

14
Future Testing
  • March 3rd Refill Controller Test 1
  • Check Wire Diagrams
  • Refill Controller will be connected to the supply
    system where each switch will be test multiple
    times
  • March 5th Hx Coil Test 2
  • Mass Flow Controller instead of Wall Pressure
    Regulator
  • Spring Break Dr. Fus Experiment
  • Dr. Fu will be using our setup minus the
    controller.
  • Will be given data from him after Spring Break

15
Future Plans
  • Nitrogen Dewar
  • Come up with a test that will be able to bypass
    or insulate the HX pre-cooling coils to see what
    effect they have on the refill temp stability
  • Temperature Fluctuation Issues
  • Talk with Dr. Van Sciver
  • Temperature Fluctuation from the Supply Dewar
  • Temperature readings taken at the outlet, better
    place?
  • Things that can be done to prevent further
    temperature flunctuation

Senior Design Group 2 900 MHz NMR Probe
Cryogenic Gas Supply System
16
Questions?
Write a Comment
User Comments (0)
About PowerShow.com