Title: Holy Spirit Jr High Improvements Final Report


1
Holy Spirit Jr High Improvements Final Report
  • Science Lab Jr. High Zone
  • Sponsored by HSA / Jr High Committee / PAC

2
Goals
  • Make HS School more Jr High marketable
  • Action to parents concerns/suggestions
  • Projects
  • Improve the Science Class experience
  • Provide an enhanced Jr High like environment
    within the K-8 context

3
Science Lab Project (Stage-1)Accomplishments
  • Flexible layout Lab Lecture to meet Jr High
    Curriculum
  • Specialized design heavy duty lab tables. Solid
    wood with composite tops heath and chemical
    resistant. Includes a disabled compliant unit.
  • Easy access to outlets supporting heavy
    electrical loads.
  • Portable teacher's station. Services include
    electrical, gas and built in sink.
  • New cabinets with composite tops and storage
    space.
  • Cabinet includes
  • Built in teachers desk. Access to LAN and remote
    projector feed. Tablet technology enablement.
  • Three new composite lab grade sinks and fixtures.
  • A new ceiling mounted projector with specially
    designed projecting whiteboard.
  • Additional new services include
  • LAN drops to built in desk and computer area.
  • Video and computer feed to ceiling mounted
    projector

4
Science Lab Requirements
  • Basic Design Requirements Status
  • Enough sitting for largest class section
  • Recommended is 24 Achieved
  • Epoxy work Tables (Area 5 sq-ft/student)
  • Minimum Aisle Space 2-6 Achieved
  • Recommended 35/40 sq-ft per student (Actual
    29x29841/2435 sq-ft) Achieved
  • Laboratory grade sinks fixtures
  • Minimum of 3 (1 per 2 teams) Achieved
  • Teacher Station
  • All services Electrical, Water, Sink, Gas,
    LAN Achieved
  • Fumes extracting station
  • Recommended. Planned for
  • Curriculum

5
Science Lab Cost
  • Plan Actual
  • Equipment Installation
  • Casework/Tables/Teacher Station 22,151.00
    22,151.00
  • Upgrades Locks, Steel Fixtures, Book Drawers
    1,991.00
  • Services Construction
  • Electrical
  • Equipment (no reels used) 4,823.00
    868.27
  • Materials/Labor (reels replacement)
    3,200.00 4,726.43
  • Plumbing 4,660.00 4,100.00
  • Construction Materials/Labor 6,268.00
    6,273.10
  • Technology Enablement
  • LAN (provided by RCS Technology Group)
  • Projector unit, rough-in and mounting hw
    679.00 803.91
  • Gas 1,450.00 1,450.00
  • Fume Extraction N/A
  • Additional Equipment (whiteboard)
    749.19

6
Door Project Accomplishments
  • Placed a door in hallway (SE Door) by the
    Computer Lab to include south locker section
  • Placed a door in hallway (NW Door) by the current
    Science Room
  • Added door to Science Lab to access Jr High Zone
  • Specifications
  • Doors include glass window and glass side panels
    (Safety)
  • Doors match existing door features (frame, wood
    grain and stain color)
  • Doors provide best noise isolation (key goal)

7
Jr High ZoneRequirements
  • Requirements Status
  • Zone must include access to all Jr High
    classrooms Achieved
  • Lockers must be contained within the Zone
    boundaries Achieved
  • Zone must provide noise isolation Achieved
  • Architecturally compliant Achieved
  • Functional and safe Achieved

8
Door ProjectFinal Expense
  • Plan Actual
  • Adding SENW Doors 8,128.00 8,127.44
  • Additional Glass Window Feature 203.00
    507.00
  • Planned 2, added 4.
  • Additional side Glass Feature 470.00
    940.00
  • Planned 2, added 4.
  • Adding Science Room Door 2,504.00
    2,504.00
  • Parts and Installation included
  • Additional Repairs TBD 186.35
  • Total 11,305.00 12,264.79

9
Science and Door ProjectsFinal Expenses
  • Plan Actual
  • Science Lab Equipment 22,151.00 24,142.00
  • All Equipment (w/upgrades)
  • Science Lab Construction 21,080.00 18,970.90
  • All planned services tech enable
  • Doors 11,305.00 12,264.79
  • All 3 new doors features
  • Project Total 54,536.00 55,377.69

10
Committee Members
  • We would like to thank the following individuals
    for their contributions during the planning and
    multiple reviews that lead to the approval of
    these projects.
  • Holy Spirit Staff
  • Ron Gaines (Principal)
  • Mrs. Schlaman (Jr. High Science Teacher)
  • Mrs. Sanderfoot (Jr. High Teacher)
  • Mrs. Smith (Jr. High Teacher)
  • HSA
  • Elaine Pardi (HSA President / Former PAC Member)
  • PAC / Jr High Committee
  • Julie Modjeski (Jr High Steering Committee Chair)
  • Julie Hansen (Former PAC Chair)
  • Josep Cors (Project Coordinator / Former PAC
    Member)
  • RCS
  • Terri Riessen (RCS Director of Technology)
  • Chris Larsen (H.S. School Representative /
    Former PAC Member)
  • Volunteers
  • Barb Greguson (Door Project Steering Committee)
  • Tom Virgin (Science Lab electrical consultant)

11
Future Recommendations
  • Add additional storage capacity
  • Finish current casework. Add wall cabinets peg
    board (dry lab equipment)
  • Replace existing south wall large storage and
    book shelves (current furniture mismatch)
  • Invest in Tablet technology. Interactive teaching
    tool.

12
Science Lab Expansion (Stage-2)
  • Casework Wall Cabinets
  • Flexible rail mounting wall cabinet units
  • Including cabinets/shelving for built teachers
    desk area
  • Peg Board
  • Large Storage Cabinet (replace metal portable
    unit not functional in current space)
  • Additional wall cabinets for books (replace
    existing floor shelving)

13
Science Lab ExpansionEstimates (Stage-2)
  • Current casework wall cabinets/shelving plus
    large fixed storage unit
  • As per plan (see elevation 2) 10,579.00
  • Large fixed storage (see elevation 1)
    1,400.00
  • Replace south wall floor shelves and add
    additional storage
  • As per plan (see elevation 1) 6,517.00
  • Total Stage-2 18,496.00
  • Note () If both options listed are ordered
    there are savings of around 1,000.00 dollars (
    17,496.00)

14
Science Lab Layout
15
Cabinets Elevation 01
16
Cabinets Elevation 02