Fiber Milestones: WLS Fiber for Tracking Proto. - PowerPoint PPT Presentation

About This Presentation
Title:

Fiber Milestones: WLS Fiber for Tracking Proto.

Description:

40% shipment ready to ship about 1 month after shutdown finishes ... wear on mold ejection parts. Remediation. new procedure removes need for ejector ... – PowerPoint PPT presentation

Number of Views:80
Avg rating:3.0/5.0
Slides: 16
Provided by: kevin499
Category:

less

Transcript and Presenter's Notes

Title: Fiber Milestones: WLS Fiber for Tracking Proto.


1
Fiber MilestonesWLS Fiber for Tracking Proto.
  • Quick summary
  • All Tracking prototype WLS fiber arrived in 2
    shipments
  • 60 shipment 40 shipment
  • 2 shipments due to availability of funds
  • 60 shipment shipped in July
  • The 40 shipment is about ½ finished at the
    shutdown
  • 40 shipment ready to ship about 1 month after
    shutdown finishes
  • Shutdown finishes Oct 12, but PPD will try to get
    crew back earlier
  • very large loss of schedule contingency
  • Not expected to impact WBS 3and downstream
    schedules
  • Have two functioning QC tests
  • both show little variation
  • n.b., these two techniques dont
    definereflectivity in the same way, butboth are
    sensitive to mirror variations

2
WLS Production
  • We expect to start WLS production mirroring in
    mid January 2008

3
Upgrades since Dir Rev
  • We have added 2 new technicians
  • One went from part time to full time in July
  • One starting ½ time in Aug Sep (shared with CMS
    ) and full time in Oct
  • Both of these technicians are being trained for
    ODU production
  • We have doubled the number of gluing stations
    from 60 to 120
  • We have more than doubled our table space for
    production
  • We have identified the table space for boot
    production

4
Fiber MilestonesODU for Tracking Proto.
  • Quick summary
  • ODUs approximately 60 complete
  • some Q/C issues identified and addressed
  • ODU quantities required were updated by
    downstream factories

5
ODUs
  • For tracking prototype we are supposed to ship
    543 ODUs
  • 335 ODUs have been shipped
  • Pass optical QC fit test
  • Another 120 ODUs have passed the optical QC
  • We are modifying the fit test and are waiting for
    test hardware from Lab 7
  • Another 200 are in various stages of production
  • Optical QC test
  • Optical QC requires each fiber in a ODU must have
    its value gt 90 of the transmission mean for that
    channel
  • 5.7 failed the optical QC
  • In addition
  • Another 2.0 of ODUs failed because we purposely
    pushed the diamond to its limit before
    relapping/replacing to test its lifetime
  • 7.5 failed to clip into box because of epoxy on
    back end of ferrule.
  • We noticed this problem after producing 300 ODUs
  • In the last 100 ODUs the problem did not occur
  • In the future we think lt 1 of the ODUs will fail
    this test.
  • The failure rate is slightly higher than before
    as we bring on these new people

6
Tracking Prototype ODUs
  • Estimate of failures for future production
  • 5 optical 1 epoxy failure, if no other
    problems

7
Fiber Milestones Cable Production
  • In a slide
  • Work on cable mold significantly delayed
  • conscious choice because of large float
  • Cable production problems identified
  • change in ferrule length impliesneeded mold
    modifications
  • problems with pouring process andESH impact of
    the material(polyurethane with Al(OH)3 fire
    retardant)
  • material flow into andwear on mold ejection
    parts
  • Remediation
  • new procedure removes need for ejector
  • in the process of completing new hardware
  • estimated startup in 4-6 weeks

8
Optical Cable RD
  • New Mold
  • Use sliding clamp to press connector against mold
    to prevent mold material from flowing to front of
    connector
  • The Alumilite polyurethane did not flow into
    around the connector to the polished fibers as it
    was doing with the old mold
  • No extraction pins which got gummed up in
    previous mold
  • Use straps put in the boot
  • Mold cheaper by more than a factor of 2
  • We have successfully made boots with new mold and
    our original molding material, Alumilite
    polyurethane
  • Problem with mold, connectors fit too tight in
    the mold right now
  • material will have to be removed in the mold
  • about 1 week of work.

9
Mold Material
  • But the Alumilite is not ideal
  • It is fluid than we want
  • Will require a chemical hood, restricts how we do
    production
  • We have identified 2 epoxies which look very
    promising to replace the Alumilite, but we have
    not finished the RD
  • Both epoxies packaged for 2 component mixing guns
  • Both have about the right viscosity
  • Heigl MP5405bk 1st choice
  • Hardens in 15 minutes, no chemical hood needed
  • Successfully easily put boots on 5 cables with
    original mold
  • Problem, Its black material transmits red light
  • Heigl will work with us to fix this problem.

10
Mold Material
  • Resinlab EP1046fg
  • Can pull boot out after 1.5 hours, not ideal, but
    good enough to finish project
  • Epoxy is fine, other than the setting time
  • None of these 3 products are fire retardant
  • ESH suggestion is to paint with fire retardant
    paint
  • Sent initial set of Heigl painted sample to for
    fire test
  • Had problems at sharp corners, but successful
    otherwise
  • Made new samples to fire test which fixed
    problems with sharp corners
  • Made samples of all 3 materials
  • They have been given to Jim Priest

11
Cable Production
  • We expect to start tracking prototype cable
    production on Nov 1 2007
  • Full Cable production starts on May 1 2008

12
Clear Fiber QC
  • We measured the attenuation length for the ODU
    fiber
  • Measured attenuation length of ODU fiber
  • 5 m pieces
  • Cut back test
  • Use 1 m WLS jumper
  • Get a 50 cm longer number as opposed to a 50 cm
    clear jumper
  • CMS and some early MINERvA tests we used 50 cm
    clear jumper

13
Clear Cable QC
  • Get l 815 cm
  • Equivalent to 770 cm in measuring it in the way
    that CMS did and we got about 800 cm for the
    attenuation length in CMS for 0.94 mm S-35 fibers
  • So CMS and MINERvA clear fibers are fairly close
    in attenuation length

14
ESH/QA Changes
  • ESH/QA
  • WBS 1
  • Removed weekly cosmic ray light yield check with
    extruded strips
  • always tracked more precise source tests which
    are performed daily
  • WBS 2
  • QC procedure uses razor blades for cutting fiber
    at 45
  • recent concern raised by PPD ESH. no directive
    yet, but in communication
  • WBS 4
  • QC improvements already discussed
  • We are working with ESH on the new mold material
    both for personal safety and fire safety
  • Heigl epoxy does not require a chemical hood

15
Identified Risks at CD-3aWBS 4 (Fiber Cables)
  • Final tests of light-tight mold essentially
    failed to hold up in a production situation
  • Solution is seen in either redesigning the mold
    or getting a new mold material and we did both
  • RD should be finished in September 2007
  • Fiber costs carry significant contingency to
    reflect past changes in pricing from Kuraray
    (less of a problem with clear fiber than WLS)
Write a Comment
User Comments (0)
About PowerShow.com