Title: Simultaneous Nitrification and Denitrification at Fresno
1Simultaneous Nitrification and Denitrification at
Fresno
- Presented by
- Ronald G. Schuyler, PE, DEE, and Joe R. Tamburini
- Rothberg, Tamburini, and Winsor, Inc.
- and
- Steven Hogg and Kim Toepfer
- City of Fresno
2Thanks to all of the Fresno-Clovis operations
staff for making this approach work!
3Operational Problems
- High organic load (gt40 lb BOD/103 ft3)
- High temperature (80ºF)
- Easy nitrification
- Easy secondary clarifier denitrification
- Blanket on top!
- Poor sludge settleability
- High effluent TSS
4The Fresno Treatment System
Plant 2
B Side
To Percolation Ponds
Headworks
Primary Clarifiers
A Side
5A Side Activated Sludge
6Wastewater Characteristics
7Industrial Contribution
8Design Parameters
- Original A-Side Design
- Q 50 MGD
- Influent BOD/TSS 240 mg/L
- Based on CPE performed in May 2003
- Aeration basin limited
- Primary effluent BOD of 238 mg/L
- Two-year average value
- 33.3 MGD _at_ 238 BOD
9Effluent Limitations
10Historical Control Approaches
- Nitrification/denitrification issues exist even
though nitrification was not required - Normal AS plants nitrify at normal MCRT at high T
- Minimize denitrification in secondary clarifiers
- Minimize nitrification in aeration tank
- Very low MCRT
- 1.5-2.0 Days
- RSF high to minimize solids detention time in the
clarifier - Lower DO approximately 1.0 mg/L
11Historical Results
- Worked well with lower organic loading
- High-rate activated sludge
- Effluent BOD/TSS usually lt 40/40
- Clarifier denitrification during low organic
loading - High SVI, but controllable
- Tanks off-line saved money
- Increased organic loading mid 2001
- Food processing industries come on line
- Zoogloeal slime production from sugars, acids and
alcohols - Higher SVI
12Project Objectives
- Treat higher organic load
- Increase the stability of mixed liquor
- Reduce zoogloeal slime
- Reduce SVI (historically very high)
- Control nitrification/denitrification
- Nitrify some for EC control
- Minimize clarifier denitrification
- Reduce effluent TSS
- Minimize oxygen requirements
13Possible Approaches
- Anoxic section - MLE
- High for barriers and recycle piping/pumps
- Excess design and construction time
- May not mesh with next plant upgrade
- On/Off aeration
- Old, unstable fine-bubble aeration grid that
could fall apart - Square tanks with only air mixing and one
influent point
14Modified Approach
- Increase MCRT to provide more stable MLSS
- Reduce zoogloeal slime production
- Reduce F/M to reasonable value
- Use low DO environment
- Minimize nitrification
- Maximize denitrification in aeration tank
- Minimize denitrification in clarifiers
- Control low-DO filaments
- 0.3-0.4 mg/L possibly too low for low DO filaments
15Results
- Load
- Flow
- Organic
- Air
- DO
- Flow rate
- MCRT
- SVI
- Effluent quality
- BOD
- TSS
- Ammonia
- Nitrate no data but less than 8-10 if limited
clarifier DN
16Operating Realities
- System prone to nitrify even in less than ideal
conditions - Operators shifted flows around the system as
needed depending on the system conditions - DO controlled at the end of the aeration tanks
only - DO probe calibration infrequent
- Problems with instrument calibration accuracy
- Problems convincing operators of requirement to
maintain low DO
17A Side Flow Rate
Flow, MGD
18Organic Load
19Aeration Tank Dissolved Oxygen
Very Low MCRT
20Air Flow Rate and Space Loading
21Oxygen Transfer Efficiency
AOTE SOTE(a)(ßCsw CL)/Cs?(T-20)
As CL get smaller, the transfer rate increases.
(ßCsw CL)/Cs For instance in a situation such
as Fresnos with little initial nitrification, a
transfer efficiency increase of about 10 would
be expected with a drop in DO from the 0.9 mg/L
to 0.2 mg/L with ß 0.95, Csw 8.0 mg/L and Cs
9.17 mg/L. Nitrification would improve that
further by increasing a.
22MCRT
23SVI
24Organic Acids
Consistently high SVI from Thiothrix and type 021N
25Effluent Quality
High MCRT
High Organic Load
26Results
- Allowed significantly higher flow rate 22
- Allowed 12 increase in BOD mass loading
- Reduced effluent parameter concentrations
- BOD - 7.5
- TSS - 14
- NH3 - 28
- Air requirements per MGD reduced 22
- Reduced zoogloeal slime
27Results
- Provided acceptable effluent quality under
significantly overloaded conditions - Clarifier denitrification controlled
- DO lt 0.35 mg/L
- Low numbers of low-DO filaments
- DO lt 0.4 mg/L
- There are always process instabilities that make
it difficult to identify a specific causative
agent
28Lessons Learned
- Quality DO meter capable of controlling at
ultra-low level - Accurate and frequent DO meter calibration
required - Low-DO filament population would tell us proper
DO level - Relying on hard and fast DO target a mistake
29More Lessons Learned
- Nose and eyes tell when DO was too low
- Biology of the system told us the correct MCRT
now 5-6 days typically - Low DO, simultaneous N/DN proven successful
- Stable process
- Operational reliability
- Trial and error testing required
- Approach saves energy (and chemicals)
30Questions
Ron Schuyler BugDr_at_rtweng.com