Title: PSDH Update
1PSDH Update
- Markus Kaps, Senior Strategy Manager
- Simon Baugh, Head of Government Affairs
2Presentation objectives
- This is what we have learned
- This is what is going on
- This is what we need from you
- Contents
- ATWP progress report
- Programme and next steps
- Environmental Assessment
- Air Quality
- Air Noise
- Surface Access
- Promotion
3Aviation Transport White Paper progress report
4What is the ATWP Progress Report?
- Reports on progress on the policies and proposals
set out in the Air Transport White Paper
(December 2003)
5What did the 2003 White Paper say?
- Conclusions
- Maintain Heathrows status as UKs leading hub
- Make best use of current infrastructure
- Additional runway capacity provided stringent
environmental limits can be met
The further development of Heathrow is
supported, including a further new runway
additional terminal capacity to be delivered as
soon as possible (within the 2015-2020 period)
after the new runway at Stansted, but only if
stringent environmental limits can be met.
6Progress Report Heathrow policy position
- The Progress Report reaffirms the Governments
support for further expansion of Heathrow
The Government continues to support the
development of a third runway at Heathrow, as
soon as it is possible to meet the stringent
environmental limits set in the White Paper,
taking account of the mitigation measures needed
to allow this to happen.
7What the Progress Report covers
- The global environmental challenge (climate
change) - The local environmental challenge (noise, air
quality, airport master plans) - Economic benefits of air travel
- Progress since 2003
8Progress Report - Third runway
- Work since 2003 has confirmed that a new runway
would have to be supported by a new passenger
terminal, as well as changes to nearby roads - With a third runway the airport could eventually
support up to 720,000 movements (around 128
million passengers a year) - The PSDH environmental assessments will not be
finalised before spring 2007
9Progress Report - Mixed Mode
- The DfTs provisional environmental assessment
for mixed mode operation suggests that the noise
contour limit could be met if extra movements
were phased in gradually as noisier aircraft were
retired - However, it would require ending of the Cranford
Agreement and some loss of runway alternation - The Government is committed to reviewing the
current practice of 'westerly preference' - The impacts of all these factors will be the
subject of public consultation
10Progress Report - Mixed Mode
- Following a policy decision, BAA would need to
prepare proposals for mixed mode operation within
current traffic levels, helping to reduce delays
and improve schedules - But a planning application would be necessary to
increase the current 480,000 limit on annual
movements as well as provide additional
facilities for the extra passengers and aircraft
11Programme and next steps
12Programme
13Environmental Assessment
14Air Quality
- first outputs from the modelling work
- what we know
- large twin engine aircraft have an exponential
impact - engine and aircraft technology improvements
- aircraft replacement programmes
- road borne emissions
- next steps
- fleet mix and forecast
- operational and technology
- non aviation
40µg/m3 NO2
15Air Noise
- improvements made to the ANCON model
- what we know
- MDA operations favour Air Noise, MAD better for
Air Quality - engine and aircraft technology improvements
- aircraft replacement programmes
- next steps
- understand the inter dependence between Air Noise
and Air Quality - model hybrid solutions
127km² (57dBA)
16Surface Access
- primary objectives
- model future road usage to inform air quality
modelling - establish mitigation options to reduce road borne
emissions - progress
- modelling work complete with a few weeks
- mitigation options under discussion with DfT
17Promotion
182003 White Paper conclusions
- Maintain Heathrows status as UKs leading hub
- Make best use of current infrastructure
- Additional runway capacity provided stringent
environmental limits can be met
The further development of Heathrow is
supported, including a further new runway
additional terminal capacity to be delivered as
soon as possible (within the 2015-2020 period)
after the new runway at Stansted, but only if
stringent environmental limits can be met.
19Progress Report Heathrow policy position
- The Progress Report reaffirms the Governments
support for further expansion of Heathrow
The Government continues to support the
development of a third runway at Heathrow, as
soon as it is possible to meet the stringent
environmental limits set in the White Paper,
taking account of the mitigation measures needed
to allow this to happen.
20Options for runway capacity growth
21Steps to planning permission (MM)
22Decision Makers / Influencers
23Communications - next 12 months
Pre-consultation
Consultation
Decision
24Key Messages
- We are fixing security
- Heathrow transformation
- Progress on the environment
- Regional economic benefits
- UK competitiveness
25Evidence We are fixing security
- We are steadily driving out queues while
maintaining high standards - 500 new security officers
- 13 new security lanes
- 25 increase in capacity
- Mi-sense and ESP body scanners
- 95 within 5 minutes
26Evidence Heathrow transformation
- Terminal 5
- Heathrow East
- T3 Futures
- T4 refurbishment
- In 2012 most passengers will travel through
terminals not even open today
27Evidence progress on the environment
- Climate Change EU ETS
- Noise Insulation schemes, noise fines, quieter
aircraft - Air Quality Ground operations, clean vehicles
programme, FEGP/PCA - Surface Access AirTrack, PRT, Heathrow Express
and Connect
28Evidence Regional economic benefits
- 70,000 on-airport jobs, 100,000 indirect
- 1 in 10 people from some local boroughs work at
the airport - 90 of local businesses rate the airport as
vital or very important - 52 of senior directors say that international
transport links are an essential factor in
inward investment
29Evidence UK competitiveness
- 85 of all UK long-haul flights, and the UKs
only direct air links with Shanghai, Beijing,
Mumbai, Sao Paulo - More than half of all UK air freight
- 2 runways are operating at 98 of permitted
capacity. Frankfurt has 3 runways, Paris has 4,
Amsterdam has 5, all at less than 75 - Number of destinations served has dropped from
227 in 1990 to 180 today
30How you can help
- Future Heathrow
- Events
- Use key messages
- Ideas