PSDH Update - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

PSDH Update

Description:

Additional runway capacity provided stringent environmental limits can be met ' ... With a third runway the airport could eventually support up to 720,000 movements ... – PowerPoint PPT presentation

Number of Views:83
Avg rating:3.0/5.0
Slides: 29
Provided by: LHRFair
Category:
Tags: psdh | update

less

Transcript and Presenter's Notes

Title: PSDH Update


1
PSDH Update
  • Markus Kaps, Senior Strategy Manager
  • Simon Baugh, Head of Government Affairs

2
Presentation objectives
  • This is what we have learned
  • This is what is going on
  • This is what we need from you
  • Contents
  • ATWP progress report
  • Programme and next steps
  • Environmental Assessment
  • Air Quality
  • Air Noise
  • Surface Access
  • Promotion

3
Aviation Transport White Paper progress report
4
What is the ATWP Progress Report?
  • Reports on progress on the policies and proposals
    set out in the Air Transport White Paper
    (December 2003)

5
What did the 2003 White Paper say?
  • Conclusions
  • Maintain Heathrows status as UKs leading hub
  • Make best use of current infrastructure
  • Additional runway capacity provided stringent
    environmental limits can be met

The further development of Heathrow is
supported, including a further new runway
additional terminal capacity to be delivered as
soon as possible (within the 2015-2020 period)
after the new runway at Stansted, but only if
stringent environmental limits can be met.
6
Progress Report Heathrow policy position
  • The Progress Report reaffirms the Governments
    support for further expansion of Heathrow

The Government continues to support the
development of a third runway at Heathrow, as
soon as it is possible to meet the stringent
environmental limits set in the White Paper,
taking account of the mitigation measures needed
to allow this to happen.
7
What the Progress Report covers
  • The global environmental challenge (climate
    change)
  • The local environmental challenge (noise, air
    quality, airport master plans)
  • Economic benefits of air travel
  • Progress since 2003

8
Progress Report - Third runway
  • Work since 2003 has confirmed that a new runway
    would have to be supported by a new passenger
    terminal, as well as changes to nearby roads
  • With a third runway the airport could eventually
    support up to 720,000 movements (around 128
    million passengers a year)
  • The PSDH environmental assessments will not be
    finalised before spring 2007

9
Progress Report - Mixed Mode
  • The DfTs provisional environmental assessment
    for mixed mode operation suggests that the noise
    contour limit could be met if extra movements
    were phased in gradually as noisier aircraft were
    retired
  • However, it would require ending of the Cranford
    Agreement and some loss of runway alternation
  • The Government is committed to reviewing the
    current practice of 'westerly preference'
  • The impacts of all these factors will be the
    subject of public consultation

10
Progress Report - Mixed Mode
  • Following a policy decision, BAA would need to
    prepare proposals for mixed mode operation within
    current traffic levels, helping to reduce delays
    and improve schedules
  • But a planning application would be necessary to
    increase the current 480,000 limit on annual
    movements as well as provide additional
    facilities for the extra passengers and aircraft

11
Programme and next steps
12
Programme
13
Environmental Assessment
14
Air Quality
  • first outputs from the modelling work
  • what we know
  • large twin engine aircraft have an exponential
    impact
  • engine and aircraft technology improvements
  • aircraft replacement programmes
  • road borne emissions
  • next steps
  • fleet mix and forecast
  • operational and technology
  • non aviation

40µg/m3 NO2
15
Air Noise
  • improvements made to the ANCON model
  • what we know
  • MDA operations favour Air Noise, MAD better for
    Air Quality
  • engine and aircraft technology improvements
  • aircraft replacement programmes
  • next steps
  • understand the inter dependence between Air Noise
    and Air Quality
  • model hybrid solutions

127km² (57dBA)
16
Surface Access
  • primary objectives
  • model future road usage to inform air quality
    modelling
  • establish mitigation options to reduce road borne
    emissions
  • progress
  • modelling work complete with a few weeks
  • mitigation options under discussion with DfT

17
Promotion
18
2003 White Paper conclusions
  • Maintain Heathrows status as UKs leading hub
  • Make best use of current infrastructure
  • Additional runway capacity provided stringent
    environmental limits can be met

The further development of Heathrow is
supported, including a further new runway
additional terminal capacity to be delivered as
soon as possible (within the 2015-2020 period)
after the new runway at Stansted, but only if
stringent environmental limits can be met.
19
Progress Report Heathrow policy position
  • The Progress Report reaffirms the Governments
    support for further expansion of Heathrow

The Government continues to support the
development of a third runway at Heathrow, as
soon as it is possible to meet the stringent
environmental limits set in the White Paper,
taking account of the mitigation measures needed
to allow this to happen.
20
Options for runway capacity growth
21
Steps to planning permission (MM)
22
Decision Makers / Influencers
23
Communications - next 12 months
Pre-consultation
Consultation
Decision
24
Key Messages
  • We are fixing security
  • Heathrow transformation
  • Progress on the environment
  • Regional economic benefits
  • UK competitiveness

25
Evidence We are fixing security
  • We are steadily driving out queues while
    maintaining high standards
  • 500 new security officers
  • 13 new security lanes
  • 25 increase in capacity
  • Mi-sense and ESP body scanners
  • 95 within 5 minutes

26
Evidence Heathrow transformation
  • Terminal 5
  • Heathrow East
  • T3 Futures
  • T4 refurbishment
  • In 2012 most passengers will travel through
    terminals not even open today

27
Evidence progress on the environment
  • Climate Change EU ETS
  • Noise Insulation schemes, noise fines, quieter
    aircraft
  • Air Quality Ground operations, clean vehicles
    programme, FEGP/PCA
  • Surface Access AirTrack, PRT, Heathrow Express
    and Connect

28
Evidence Regional economic benefits
  • 70,000 on-airport jobs, 100,000 indirect
  • 1 in 10 people from some local boroughs work at
    the airport
  • 90 of local businesses rate the airport as
    vital or very important
  • 52 of senior directors say that international
    transport links are an essential factor in
    inward investment

29
Evidence UK competitiveness
  • 85 of all UK long-haul flights, and the UKs
    only direct air links with Shanghai, Beijing,
    Mumbai, Sao Paulo
  • More than half of all UK air freight
  • 2 runways are operating at 98 of permitted
    capacity. Frankfurt has 3 runways, Paris has 4,
    Amsterdam has 5, all at less than 75
  • Number of destinations served has dropped from
    227 in 1990 to 180 today

30
How you can help
  • Future Heathrow
  • Events
  • Use key messages
  • Ideas
Write a Comment
User Comments (0)
About PowerShow.com