Process Improvement for Drill Bit Blanks For MN Twist Drill - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Process Improvement for Drill Bit Blanks For MN Twist Drill

Description:

... reduced setup time: $747, ... to determine if setup is happening. Turn off ... Setup Improvements. A standard process for setup would be very beneficial ... – PowerPoint PPT presentation

Number of Views:132
Avg rating:3.0/5.0
Slides: 16
Provided by: UMD9
Category:

less

Transcript and Presenter's Notes

Title: Process Improvement for Drill Bit Blanks For MN Twist Drill


1
Process Improvement for Drill Bit BlanksFor MN
Twist Drill
University of Minnesota Duluth
Department of Mechanical and Industrial
Engineering
  • The Three Orienteers
  • Scott Anderson Project Leader
  • Andy Johnson Mechanical Engineer
  • Tony Niemczyk Industrial Engineer

Report Number UMDMIE-CD-2006WPDK12
2
Problem Statement
  • Blanks are coming off of machine without
    orientation
  • Manually sorted to bins
  • Blanks manually moved approximately 10 feet to
    coning machine
  • Manually loaded into coning machine

3
Problem Statement
4
Scope of Project
  • Orientate drill bit blanks from cut-off machine
  • Directly feed blanks into coning machine
  • Increase throughput
  • Reduce work in progress

5
Functional Requirements
  • Require little maintenance, less then 2,000/year
  • Reduces manual handling labor
  • Simple in design
  • Utilizes gravity as much as possible
  • Maintains or improves throughput
  • Adaptable to varying lengths and diameters
  • Efficient
  • Implemented with little risk due to offline
    testing

6
Constraints Limitations
  • The speed of the cutting and coning machines
    which for the cuttingmachine is 200 parts per
    minute
  • Budget is a 2 year payback on a 20,000 a year
    salary based on the reallocation of labor
  • Material type being cut which includes cobalt and
    various types of steel.
  • Drill bit diameter and length varying from 1/4
    to 1/2 and 2 ½ to 6 respectively

7
Final Design Concept Chute Hopper
  • Blanks orientate on vibratory table and slide
    down channels to coning hopper
  • Coning hopper uses rake mechanism
  • Logic senses when blanks are in hopper waiting to
    be fed into coning machine

8
Final Design Concept Chute Hopper
9
Mechanisms
10
Economics
  • Installed Cost 10,297.55
  • Annual Benefits of
  • System by itself 37,070.00
  • System with reduced setup time 747,070.00
  • Annual Maintenance (10 of installed cost)
    1,029.76
  • Payback Period of
  • System by itself 108 working days
  • System with reduced setup time 5 working days

11
Procedures
  • Programmable Logic Controller Procedure
  • Sensors in the system check the system for out of
    control circumstances
  • Ensure that the hoppers never overflow with
    material
  • Determine the operation of the slider plates

12
PLC Flowchart
13
Setup Improvements
  • A standard process for setup would be very
    beneficial to process flow
  • Identify external operations
  • Identify internal operations

14
Acknowledgments
  • We would like to thank Matt Mattson for
    contacting the University of Minnesota Duluth
    with a senior design project and for
    accommodating all of the needs of the group in a
    respectful and timely manner
  • We would like to thank Scott Allison for giving
    Matt Mattson the capabilities to go to the
    University and finance the project
  • Finally we would like to thank our professors
    Dave Keranen and Bill Pedersen for all of their
    help and advice in the development of the project
    and for guiding us to not only get the project to
    completion, but also in a manner to help us learn
    new skills on our own

15
MN Twist Drill
  • Questions
  • Comments
Write a Comment
User Comments (0)
About PowerShow.com