Calculating Emission Increases for Purposes of NSR Applicability - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Calculating Emission Increases for Purposes of NSR Applicability

Description:

Increase utilization that follows increases in reliability, lower operating ... EAB found that increased utilization and the resulting increased emissions were ... – PowerPoint PPT presentation

Number of Views:109
Avg rating:3.0/5.0
Slides: 22
Provided by: JNord
Category:

less

Transcript and Presenter's Notes

Title: Calculating Emission Increases for Purposes of NSR Applicability


1
Calculating Emission Increases for Purposes of
NSR Applicability
2
Calculating Emission Increases
  • Sources Must Use Annual Emission
  • The calculation includes emissions increases
    related to projects to recapture lost utilization
    even if the maximum hourly rate is not increased.
  • A Pre-Construction Requirement
  • The projection of emissions must be made prior to
    any construction activities.
  • Cinergy To allow otherwise would eviscerate
    the pre-construction nature of NSR.
  • Actual emissions after are irrelevant where the
    pre-projection indicates a significant net
    emissions increase.

3
Calculating Emissions Increases
  • Regardless of any such preconstruction
    projections, a major modification results if the
    project causes a significant emissions increase
    and a significant net emissions increase.
  • See e.g., 40 CFR 52.21(a)(iv)(b).

4
PSD Applicability Tests
  • PSD applies when the post-change emissions exceed
    the pre-change emissions by a significant amount.
  • Pre- 2002 NSR Reform Emission Increase Test
  • Non-EGUs Actual Emissions-to-PTE
  • EGUs Actual Emissions-to-Representative Future
    Actual Emissions (re 1992 WEPCO rule)
  • NOTE For changes made before the NSR I Reform
    rules.
  • Post- 2002 NSR Reform Two Alternate Tests for
    all
  • Baseline Actual Emissions-to-PTE
  • Baseline Actual Emissions-to-Projected Actual
    Emissions
  • NOTE Source can choose for existing units but
    new units must use Baseline-to-PTE test to
    calculate increases.

5
PSD Baseline Emissions
  • Baseline Emissions
  • One half of the applicability equation (i.e.,
    post-change emissions baseline emission
    increase or decrease).
  • Baseline Emissions for Changes Prior to 2002 NSR
    Reform
  • Actual Emissions determines the pre-change
    emissions.
  • Baseline Emissions for Changes After 2002 NSR
    Reform
  • Baseline Actual Emissions determines the
    pre-change emissions.
  • Baseline Actual Emissions are different
    depending on whether the source is an EGU or not.

6
Baseline Emissions
  • EGUs Baseline Actual Emissions
  • Equal to the emissions from any 24 consecutive
    months within the 5 previous years
  • Must be based on adequate emissions data
  • Must be adjusted for non-compliant emissions
  • Include quantifiable fugitive emissions and
  • Include start-up, shutdown and malfunction
    emissions to the extent legally allowed.

7
Baseline Emissions
  • Non- EGUs Baseline Actual Emissions
  • Equal to the emissions from any 24 consecutive
    months within the 10 previous years
  • Must be based on adequate emissions data
  • Must be adjusted for non-compliant emissions
  • Must be adjusted for currently applicable
    regulations
  • Include quantifiable fugitive emissions and
  • Include start-up, shutdown and malfunction
    emissions to extent legally allowed.

8
Baseline Emissions
  • Key Principles for Baseline Actual Emissions
  • Good emission data is needed to establish the
    baseline or pre-change emissions.
  • Baseline emissions should be corrected for
    non-compliance (e.g., startups exceeding emission
    limits).
  • For Non- EGUs, baseline emissions must be
    adjusted downward for currently applicable
    requirements (e.g., CD requirements)

9
Post Change Emissions
  • Post-Change Emissions
  • Other half of the applicability equation (i.e.,
    post-change emissions baseline emissions
    increase or decrease).
  • Post-Change Emissions Prior to 2002 Reform
  • Non-EGUs- PTE determines the post-change
    emissions- generally.
  • EGUs- Representative Future Actual Emissions
    determines the post-change emissions.
  • Post- Change Emissions After 2002 Reform
  • PTE or
  • Projected Actual Emissions

10
Post Change Emissions
  • Projected Actual Emissions
  • Maximum annual rate, in tons per year
  • Projected for any one of
  • The 5 years following the date the project
    resumes operation after the project OR
  • The 10 years following the date the project
    resumes operation if
  • The project increases the units design capacity
    or its potential to emit and
  • Full utilization would result in a significant
    emissions increase.

11
Post Change Emissions
  • Projected Actual Emissions (contd)
  • Includes fugitive emissions only if the source is
    a CAA 302(j) listed source- see e.g.,
    52.21(b)(1)(iii).
  • Portland cement plants
  • Kraft pulp mills
  • HF, H2SO4 plants
  • Refinieries
  • Start-up, shutdown and malfunction emissions
    included.

12
Post Change Emissions
  • Projected Actual Emissions are calculated as the
    product of
  • The hourly emission rate based on the units
    operational capabilities following the change
    taking into account any legally enforceable
    restriction that could affect the hourly emission
    rate following the change AND
  • The projected level of utilization (historical
    annual utilization).
  • 67 Fed. Reg. 80,186, 80,196.

13
Post Change Emissions The Demand Growth
Exclusion
  • The owner/operator may exclude from its Projected
    Actual Emissions those emissions
  • that an existing unit could have accommodated
    during the consecutive 24-month period used to
    establish the baseline actual emissions AND
  • that are also unrelated to the particular
    project, including any increased utilization due
    to product demand growth.
  • 40 CFR 52.21(b)(41)(ii)(c).

14
Post Change Emissions The Demand Growth Exclusion
  • Thus, even if the operation of an emissions
    unit to meet a particular level of demand could
    have been accomplished during the baseline
    period, but the increase is related to the
    changes made at the unit, then the emissions
    increases resulting from the increased operation
    must be attributed to the project, and cannot be
    subtracted from the projection of the projected
    actual emissions.
  • 67 Fed. Reg. at 80,203

15
Post Change Emissions The Demand Growth Exclusion
  • Principles of the Demand Growth Exclusion from
    WEPCO
  • Source must be legally and physically able to
    meet the utilization in the baseline without the
    change.
  • Any change that significantly alters the
    efficiency of a facility must be included in the
    projected emissions.
  • If efficiency improvements are the predominate
    cause of the emissions increase, then DGE doesnt
    apply.
  • Must be consistent with the current assumptions
    regarding the sources emissions used in the SIP.
  • 57 Fed. Reg. at 32,328

16
Post Change Emissions The Demand Growth Exclusion
  • Principles of the Demand Growth Exclusion from
    2002 NSR Reform Premable
  • Increase utilization that follows increases in
    reliability, lower operating costs or improving
    other operational characteristics should be
    attributable to the change.
  • In discussion of the provisions, EPA made it
    clear that the source bears the burden of
    demonstrating that the DGE applies.
  • A source may subtract emission increases from the
    projected actual emissions if the source can
    show that the unit could have achieved the
    necessary utilization and the increase in
    emissions is not related.
  • It is important that the source retain a record
    of all information available to support its
    initial claim.

17
Post Change Emissions The Demand Growth Exclusion
  • While EPA projected that it would be difficult
    to separate demand growth increases from a
    project, there are situations where the
    distinction can be clearly made.
  • Skyrocketing demand because the product becomes a
    fad
  • Mishaps at a factory , causing production
    increases at remaining supplier sources
  • Opening of new markets and
  • Decrease in raw material prices.
  • Reconsideration TSD, pp. 18-19.

18
Post Change Emissions The Demand Growth
Exclusion
  • New York I
  • NSR requires a causal link between the proposed
    change and any post change increase in
    emissions.
  • Not a per se exclusion for demand growth-
    emissions must be unrelated to the change to be
    excluded

19
Post Change Emissions The Demand Growth
Exclusion
  • In re Tennessee Valley Authority (2000)
  • EAB found that increased utilization and the
    resulting increased emissions were related to the
    change.
  • EAB focused on whether TVA had a pre-project
    intention to operate more after the change.
  • EPA used TVA pre-project pronouncements to show
    intent to operate more only after the change.

20
Post Change Emissions The Demand Growth
Exclusion
  • Cinergy (S.D. Ind. 2005)
  • Projects at issue increased the hours that the
    units were available to operate.
  • DGE is another way of emphasizing, and
    clarifying, the causation element.
  • Affirmed EPAs position that any excluded
    emissions must be completely unrelated to the
    physical change and caused entirely by
    independent factors.
  • Rejected industrys claim that an increase is
    considered only if it could not have occurred
    but for the physical change.

21
Post Change Emissions
  • Key Principles
  • Inclusion of startup, shutdown and malfunction
    emissions should be scrutinized.
  • Projection in the post change emissions occurs in
    the level of utilization, not the hourly
    emission rate.
  • Emissions must be completely unrelated to the
    change to be excluded from the post-change
    emissions.
Write a Comment
User Comments (0)
About PowerShow.com