Title: Capital Planning and Investment Control CPIC Advance
1Capital Planning and Investment Control (CPIC)
Advance
- ITIM Self-Assessment Outcomes
- January 26, 2005
2Todays Discussion
- Recap
- DOI ITIM Goals
- ITIM Overview
- ITIM Activities To Date
- ITIM Self-Assessment General Findings
- General Recommendations
- Next Steps
- Questions and Answers
3DOI ITIM Goals
- The DOI ITIM goals are reflected on page 56
in the DOI ITIM Strategic Plan FY 2003-2008 - Improve the Department/Bureau IT Management
Process to reach Level 2 along GAOs ITIM
framework by FY 2005 and Level 3 by FY 2008. - As of December 30, 2004, neither the
Department nor any of the Bureaus have been
independently certified as having achieved ITIM
Stage 2.
4GAOs ITIM Framework
- Information Technology Investment Management
(ITIM) A Framework for Assessing and Improving
Process Maturity (GAO-04-394G March 2004
Version 1.1) - GAO developed ITIM as a maturity model, to guide
agencies in improving IT investment processes - ITIM is a tool for standardizing internal and
external assessments of an agencys IT investment
management process - ITIM is a framework for consistently reporting
assessment results to agency executives, the
Congress, and other interested parties
5GAOs ITIM Model Measures CPIC Process Maturity
GAO-04-394G, GAO IT Investment Management, A
Framework for Assessing Improving Process
Maturity, March 2004.
6Critical Processes 5 ITIM Stages of Maturity
End of FY 2008
End of FY 2005
Today
GAO-04-394G, GAO IT Investment Management, A
Framework for Assessing Improving Process
Maturity, March 2004.
7ITIM Activities To Date
- September 2003 GAO assessed DOIs and BLMs ITIM
maturity - Based on exposure draft of the ITIM Framework
- Determined DOI is executing 7 of the 38 key
practices1 - Determined BLM is executing 32 of the 38 key
practices2 - September 2003 DOI set ITIM goals for the
Department and the Bureaus - November 2004 PMD provided ITIM Self-Assessment
Orientation - December 2004 Bureaus completed their ITIM
Self-Assessments - December 2004 Bureaus completed their ITIM
Stage 2 Gap Closure Plans - January 2005 CPIC Advance held
1GAO-03-1028, Department Leadership Crucial to
Success of Investment Reforms at Interior,
September 2003. 2GAO-03-1025, Plan Needed to
Sustain Progress in Establishing IT Investment
Management, September 2003.
8ITIM Self-Assessment General Findings
- BLM and OST Achieve ITIM Stage 2 Progress Varies
at Other Bureaus - ITIM Foundation Largely Established, Resource
Constraints Hinder Progress - General Weakness in the Selecting an Investment
Critical Process - Localized Weakness in the Providing Investment
Oversight Critical Process - Self-Assessment Scores Appear Biased
9General Finding 1 BLM and OST Achieve ITIM
Stage 2 Progress Varies at Other Bureaus
- BLM and OST report they have already achieve ITIM
Stage 2 - MMS and BOR should achieve ITIM Stage 2 easily
- NPS and FWS report low scores and risk not
achieving ITIM Stage 2 by FY 2005 - Remaining Bureaus and the Department scores range
from 17 to 21. Some risk of not achieving ITIM
Stage 2 by FY 2005
10General Finding 1 (Continued)
- Department-wide 146 key practices not fully
executed. 115 (79) are partially executed. This
suggests significant progress is underway. - OSM and USGS each report 17 partially executed
key practices. Indicates a greater ability to
meet the FY 2005 deadline than their executed
scores suggest. - BIA and the Department each report a significant
number of key practices are not executed.
Indicates some risk in meeting the FY 2005
deadline. - NPS and FWS each report a large number of
partially executed practices. Indicates that ITIM
Stage 2 activities are broadly established but
much work remains.
11General Finding 2 ITIM Foundation Largely
Established, Resource Constraints Hinder Progress
- Organizations are Instituting the Investment
Boards and Meeting Business Needs - Laying a governance foundation by establishing
charters, boards, rules - However, lagging in implementing more tangible
and practical CPIC practices - Bureaus share a common prerequisite constraint
that spans multiple critical processes - Inadequate resources (people, funding, and tools)
- Resulting in a low number of executed key
practices
12General Finding 3 General Weakness in the
Selecting an Investment Critical Process
- A significant number of key practices are not
executed, which suggests weaknesses in - Aligning selection criteria with broader
strategic goals - Analyzing projects to determine whether they
should be reselected - Aligning selection criteria with the Enterprise
Architecture or in the understanding,
communicating, or enforcing policies concerning
the target Enterprise Architecture
13General Finding 4 Localized Weakness in the
Providing Investment Oversight Critical Process
- Documenting policies and procedures for IT
project management oversight and in maintaining
approved project management plans. - Understanding and/or implementing of Earned Value
principals. This weakness is also perceptible in
the activities in the Capturing Investment
Information critical process.
14General Finding 5 Self-Assessment Scores Appear
Biased
- Bureaus performed a self-assessment while the
Department was independently assessed - 8 (31 out of the 380) key practices were scored
not executed, 10 of the 31 were from the
Department. - Some evidence cited is not sufficient to justify
the score. - Bureaus noted key practice executed, however
identified gaps. - Does not invalidate self assessment results, but
independent ITIM Assessment might not result in
similar conclusions.
15General Recommendations
- Finalize Plans at Bureaus to Close Gaps
- All Organizations Address Resource Issues
- Monitor Progress Monthly
- Provide Earned Value Training/Briefing to Boards
Members and Project Managers - Amend Departmental CPIC Guide to Require Annual
ITIM Assessments - Prepare for Independent ITIM Certifications
16Next Steps
- Bureaus finalize plans to close ITIM Stage 2 gaps
- Department provide Bureaus with specific findings
and recommendations - Department coordinate with Bureaus to define a
ITIM Stage 2 Certification Package - Department prepare monthly reporting specifics
for the gap closure plan - All organizations execute gap closure plans and
report on progress to the Department monthly
starting in Q3 FY 2005 (April).
17Questions