Scheduling Resources and Costs - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

Scheduling Resources and Costs

Description:

Level of resource used for an activity cannot be changed. ... Assuming a 1/2/08 start and no special holidays, we go from ending on 3/4 to 3/20 ... – PowerPoint PPT presentation

Number of Views:200
Avg rating:3.0/5.0
Slides: 34
Provided by: charli148
Category:

less

Transcript and Presenter's Notes

Title: Scheduling Resources and Costs


1
Scheduling Resources and Costs
  • Chapter 8

2
(No Transcript)
3
The Resource Problem
  • Resources and Priorities
  • Project network times are not a schedule until
    resources have been assigned.
  • The implicit assumption is that resources will be
    available in the required amounts when needed.
  • Adding new projects requires making realistic
    judgments of resource availability and project
    durations.
  • Resource-Constrained Scheduling
  • Resource leveling (or smoothing) involves
    attempting to even out demands on resources by
    using slack (delaying noncritical activities) to
    manage resource utilization.

4
Types of Project Constraints
  • Technical or Logic Constraints
  • Constraints related to the networked sequence in
    which project activities must occur
  • Resource Constraints
  • The absence, shortage, or unique
    interrelationship and interaction characteristics
    of resources that require a particular sequencing
    of project activities

5
Constraint Examples
FIGURE 8.1
6
Kinds of Resource Constraints
  • People
  • Materials
  • Equipment
  • Working Capital

7
Classification of a Scheduling Problem
  • Classification of Problem
  • Using a priority matrix will help determine if
    the project is time or resource constrained
  • Time-Constrained Project A project that must be
    completed by an imposed date
  • Time is fixed, resources are flexible if
    additional resources are required to ensure
    project meets schedule, they may be obtainable
  • Or a
  • Resource-Constrained Project A project in which
    the level of resources available cannot be
    exceeded
  • Resources are fixed, time is flexible inadequate
    resources will simply delay the project.

8
Resource Allocation Methods
  • Limiting Assumptions
  • Splitting activities is not allowedonce an
    activity is start, it is carried to completion.
  • Level of resource used for an activity cannot be
    changed.
  • Activities with the most slack pose the least
    risk.
  • Reduction of flexibility does not increase risk.
  • The nature of an activity (easy, complex) doesnt
    increase risk.
  • (Aside) From practical observation, the way many
    PMs handle resource allocation is to assign
    people to activities after the network has been
    MSProject-ized, and then filter for person and
    put in additional links.
  • While easy to do, this is not theoretically
    correct and leads to over-restrictive scheduling
    or inability to react to personnel changes.

9
Time-Constrained Projects
  • Are projects that must be completed by an
    imposed date
  • Require the use of leveling techniques that focus
    on balancing or smoothing resource demands by
    using (positive) slack (i.e. delaying noncritical
    activities) to manage resource utilization over
    the duration of the project
  • Peak resource demands are reduced.
  • Resources over the life of the project are
    reduced.
  • Fluctuation in resource demand is minimized.

10
Botanical Garden Example
  • Given the following project network, we would
    like to
  • minimize total resources (rented backhoes) used
  • smooth capacity requirements (avoid large
    fluctuations)

FIGURE 8.2
11
Pre and Post Smoothing
FIGURE 8.2 (contd)
12
Resource Allocation Methods
  • Resource Demand Leveling Techniques for
    Time-Constrained Projects
  • Advantages
  • Peak resource demands are reduced.
  • Resources over the life of the project are
    reduced.
  • Fluctuation in resource demand is minimized.
  • Disadvantages
  • Loss of flexibility that occurs from reducing
    slack
  • Increases in the criticality of all activities

13
Resource-Constrained Projects
  • Are projects that involve resources that are
    limited in quantity or by their availability
  • Scheduling of activities through use of
    heuristics (rules-of-thumb), according to the
    following priorities.
  • Note- Heuristics do not guarantee optimal
    solutions, but they help in finding a decent
    solution quickly
  • Start from beginning of project time and, when
    resources used exceed the resources available,
    retain activities first by
  • Minimum slack
  • Smallest (least) duration
  • Lowest activity identification number
  • and push the others out further in time
  • An unarticulated rule in later periods, do not
    move activities that have already started
  • Additional caveat when considering activities
    not to delay, consider the resources each
    activity uses.

14
Example Resource Constrained Project
  • Assume we only have 3 people available to do the
    following project, and we cannot afford to hire
    more.

15
Example of Resource-Constrained Scheduling
a2
a5
a1
a7
a3
a6
a4
Suggestion for improving notation- prefix
activity IDs with a to keep s from overwhelming
FIGURE 8.3
16
Prior to Resource Balancing
ES resource load chart (with slack in gray)
Revisions from book, to make process clearer
FIGURE 8.3 (contd)
17
View Resources in MS Project
  • In Resource Graph can see the overage
  • Set resource availability via view resource
    sheet
  • Defaults to increments of 50 but you can
    manually type in different amounts

18
Start Shifting Activities Later to Satisfy
Resource Availability
Resource-constrained schedule through period 56
2 2 2 2 2 2
1 1
1 1 1 1
1 1
FIGURE 8.4
19
We Now Consider the Resources Available
Delay activity 2 by 1 period, making 2-to-3
period resource- feasible (still not feasible for
3-to-4 and beyond.)
2 2 2 2 2 2
1 1
1 1 1 1
1 1
FIGURE 8.3 (contd)
20
Resource Load Now Feasible
  • Final resource-constrained schedule
  • Still need to re-compute slack, given new project
    end date

FIGURE 8.4 (contd)
21
Example in MS-Project
  • Go to tools level resources
  • For resource-constrained leveling, use the
    default settings
  • For time-constrained, pick Level within Slack
    and ignore the working messages that may be
    produced
  • Will produce a schedule with less fluctuation,
    but may still exceed level limits

22
(Another) Computer Demonstration
ofResource-Constrained Scheduling
  • EMR Project
  • The development of a handheld electronic medical
    reference guide to be used by emergency medical
    technicians and paramedics
  • Problem
  • There are only eight design engineers who can be
    assigned to the project due to a shortage of
    design engineers and commitments to other
    projects.

23
EMRProject NetworkView of Schedule before
Resources Leveled
This is the illustration from the book, which
has 2 grievous errors- Can anyone spot them?
FIGURE 8.5
24
EMR Project Prior to Leveling Resources
FIGURE 8.6
25
Time Constrained Leveling Within Slack
  • We reduce the need for some overtime
  • but still have a large peak at the end, so this
    is probably not acceptable

26
Leveling by Allowing the Project Duration to
Expand
  • If we take MS Projects leveling defaults
  • Project duration will now be 57 working days
    instead of 45 working days.
  • Assuming a 1/2/08 start and no special holidays,
    we go from ending on 3/4 to 3/20
  • Resource usage between 5 to 8 engineers
  • Can insert leveling delay column in schedule
    view to see the shifts
  • Even manually make them without relying on MS
    algorithms.

27
The Impacts of Resource-Constrained Scheduling
  • Reduces delay but reduces flexibility
  • Increases sensitivity of the network
  • Increases scheduling complexity
  • Can break the sequence of events
  • May cause parallel activities to become
    sequential and change the critical path

28
Splitting/Multi-tasking
  • A scheduling technique use to get a better
    project schedule and/or increase resource
    utilization
  • Involves interrupting work on an activity to
    employ the resource on another activity, then
    returning the resource to finish the interrupted
    work
  • Is feasible when startup and shutdown costs are
    low (must include them)
  • Although easy to put in with project software,
    both prof and book would argue this is not a good
    approach.

29
Assigning Project Work
  • Factors to Consider
  • Dont always pick the same people for the
    toughest assignments.
  • Choose people with an eye to fostering their
    development through participation on the project.
  • Pick people with compatible work habits and
    personalities but who are not identical- can
    complement each other.
  • Mix team-up veterans with new hires to share
    experience and socialize newcomers into the
    organization.
  • Select people who may need to learn work together
    on later stages of the project or other projects.

30
Multiproject Resource Schedules
  • Multiproject Scheduling Problems
  • Overall project slippage
  • Delay on one project creates delays for other
    projects.
  • Inefficient resource application
  • The peaks and valleys of resource demands create
    scheduling problems and delays for projects.
  • Resource bottlenecks
  • Shortages of critical resources required for
    multiple projects cause delays and schedule
    extensions.

31
Multiproject Resource Schedules
  • Managing Multiproject Scheduling
  • Create project offices or departments to oversee
    the scheduling of resources across projects.
  • Use a project priority queuing system first
    come, first served for resources.
  • Prioritize based on perceived need- Internal
    projects more likely to get slipped than
    client-facing ones.
  • Centralize project management treat all projects
    as a part of a mega-project.
  • Outsource projects to reduce the number of
    projects handled internally.

32
Group Exercise
  • Old Test Question
  • Given the following
  • table and the fact
  • that we have 4
  • coders on staff
  • Before smoothing/rebalancing resources construct
    a Gantt chart and show weekly resource usage.
  • Revise the Gantt chart and weekly resource usage
    assuming that we are time-constrained and can
    hire coders at 3K/week. Summarize your
    recommendation to your boss.
  • If we are resource-constrained, redo the Gantt
    chart and resource usage to produce a feasible
    schedule. Summarize appropriately.

33
Some Final Thoughts on Resources
  • We may not have a pure time-constrained or
    resource constrained problem. A hybrid approach
    may be most appropriate.
  • It may make sense to show management both
    extremes in order to triangulate to the best
    solution
  • We have not explored revisiting activity
    dependencies, outsourcing tasks, doubling effort
    to do a task twice as fast (or halving effort to
    do twice as slow)
  • In the next chapter we will look at one such
    possibility
Write a Comment
User Comments (0)
About PowerShow.com