Title: 51st Fighter Wing Town Hall Meeting
151st Fighter WingTown Hall Meeting
10 September 2009
2Tour Normalization
3Phase 1 (FY09-11)
- FY10 objective 632 CSP met /
- MFH shortfall will continue to rely on off-base
capacity - Dorm shortfall remains
- 7 tier 1 dorms scheduled for demo, Dorm 1472
opens Aug 09 - Dental expansion (1,000 capacity) ongoing
- ADA MILCON project adds 270 parking spots in
highly congested area - CDC expansion/renovation adds 28 full-time
positions (FY11)
4Phase 2 (FY12-16)
- 2x MFH towers and 1x parking garage required
(government or privatized) to avoid over-reliance
on off-base capacity - USFK DoDDs projections call for 2x elementary
school equivalents - Additional Medical/Dental expansion required
(currently unprogrammed) - Force/Community support facility shortfalls
apparent - Base roads/parking congested with no companion
projects
5Phase 3 (FY17-20)
- Base population more than doubles from FY09
baseline - 9x MFH towers and 5x parking garages required
(government or privatized) - USFK DoDDs projections call for 2x elementary,
1x middle, 1x high school - Further Medical/Dental expansion required
- Force/Community support facility shortfalls
continue - Base roads/parking overwhelmed with no
companion projects
6Military Family Housing
7Projected Osan MFH Occupancy(as of 24 Jul 09)
- 351 MFH units (2 GOQ, 19 SOQ, 2 CCC 328 MFH
units) - 2 MFH Units Down for Maintenance
99 MFH Occupied in Aug 09
7
8MFH Maintenance
- General Maintenance
- MFH Contractor (Dong Buk) conducts maintenance of
your quarters 24/7 (including Holidays)
784-2376 - Elevators
- Elevator maintenance contract awarded July
- 30 of all base elevators require major repair
- Repairs are being prioritized across entire base
some dormitories have no working elevator. - 52K was obligated for repair the MFH elevators
- Self Help Bldg 657, 784-5793
- All self-help work requires approval through MFH
office, including painting of the interior walls
9Pets
- Owners must ensure their pets do not defecate
and/or urinate in the elevators, in the hallways,
or on the bushes, flowers, and similar vegetation
- Two-pet rule Caged animals (i.e. bird) fall
under the two-pet rule - Residents should report animal violations (loose
animals, stray, nuisance animals, animal bites,
abuse, cruelty, etc) to Security Forces, BLDG
1425, OR CALL 784-5515
10Fire Prevention
- Report all Fires, Even if Extinguished, on 911
- Fire Alarm Pull Stations are for Emergency Use
Only - The individual who creating false fire alarms in
August has been charged with three criminal
offenses - Never Leave Candles or Cooking Unattended
- Two Fires in PACAF this CY, Osan and Yokota
- Bathroom fire at Osan in July
- Do Not Use Propane Patio-Heaters on Balconies
- Dispose of Smoking Materials Properly
11Normal Sprinkler Head Cover
Fire Damage MFH (Osan AB, Korea) Bathroom (14
Jul 09)
Damaged Sprinkler Note Cover Melted at 135 deg F
Mirror Cracked Counter Top Melted
Incident Date/Time 14 Jul/1500 Reported
15 Jul/0900 Ignition Source Burning Candle with
Glass Enclosure Story Resident dependent (RD)
had a candle burning in glass near bathroom wall.
Suddenly, RD heard a something popped and
checked the bathroom. RD found the corner of the
bathroom wall was catching a fire and the
flame/heat melted the sprinkler cover. After the
fire melted the cover (1 ea), a sprinkler head
popped out. RD put fire out using a cup of
water. Note Fire extinguisher was not
used. Damage Cost 800 Note Wall appeared
to have been repainted POC 51 CES, 22 Jul 09
12Property Storage
- Due to fire safety, no property will be placed or
stored in stairwell, landings, corridors,
entrances or sidewalks - Residents CANNOT store stuff within 18 inches
from sprinkler heads - Residents CANNOT hang anything on the fire
suppression system (including water pipes)
Blocked hallway
Uniform on sprinklers
13Good Neighbors
- Ensure children play in the playgrounds and not
in the - parking areas or garages for safety reason
- Bikes, skateboards, etc should be used outdoors
only - Please keep common areas clean/free of vandalism
- Quiet Hours From 2200 to 0600 on Weekend
- From 2100 to 0600 on
Weekdays - Residents may contact Security Forces _at_ 784-5515
to report a violation of the noise ordinance.
However, if appropriate, floor leader may speak
with the neighbor first
14Construction Update
15Osan Middle School
What
- Middle school (3 stories, 87.2K SF), Music
Facility (1 story, 8.6K SF), Parking Structure
including athletic court on roof (4 stories,
194.4K SF, 383 Stalls), Announcer's booth,
Pavilion including toilets/storage,
Basketball/volleyball court, Sky Bridge
When
- Project Completed in August
- Ribbon cutting/open house will be 10 Sept
CE POC Maj Grolemund
16FSS/DODEA Turf Field
What
- New Artificial Turf Field
- Full size soccer field football field
- Low maintenance
- Longer wear
- No rubber pellets!
When
- Project started 10 Aug 09
- Projected to finish 12 Sept 09
- Kickoff for first game 12 Sept 09
CE POC Maj Grolemund
17Artificial Turf Softball Flds
What
- New Artificial Turf Softball Field
- Re-turfs fields behind fitness center
- Low maintenance
- Longer wear
- No rubber pellets!
When
- Projected Start 2010 (Funds Promised)
- Projected to finish TBD
CE POC Maj Grolemund
18Mustang Valley Village
What
- Working to acquire land since 2003
- Land will be re-developed for (possible)
- Future School
- Future CDC
- Future Field House Athletic Complex
When
- HN will Acquire Private land soon
- Expect transfer to Osan by end of 2009
- Possible demolition in 2010/2011
CE POC Maj Grolemund
19Child Development Center
What
- Adds additional space for CDC services
- Approx 24 more full-time slots
- Approx 48 more part-time slots
- Located at building 345(former community
center)--3600SF - Requires fire suppression and life safety design
When
- Projected to complete in March 2011
- Requires AF level certification of design
- Requires fire suppression system and US-made
materials
CE POC Maj Grolemund
20New NCO Club
What
- Provides 3-story Club for NCOs and SNCOs
- Replaces Challenger NCO Club
- Located next to Community Center
- Serves meals for 500 people
When
- Project to start in late December 2009
- Completion date June 2011
CE POC Maj Grolemund
21Dorm Renovation and Construction
What
- Renovating Multiple Dorms
- Under Construction 476, 731, 732, 734, 708, 720,
709(TLF) - Upcoming in 2010 705, 707, 717, 718
- New construction Amn dorm 1472
- Future work SNCO Dorm
When
- Dorm 1472 completed in August
- Most dorms will come online in 2009/2010
- 705, 707, 717, 718 will come online in 2011 and
2012
CE POC Maj Grolemund
22Vehicles
23(No Transcript)
24Parking Information for Osan
- Currently registered vehicles on Osan 6000
- Current parking slots on Osan 2700
- Bottom line 2.2 vehicles registered per
parking - slot
-
25Upcoming Events
- Chusok 2-4 Oct 09 (Family Day on 2 Oct 09)
- Songtan Friendship Festival 10 Sep 09
Cancelled - 1st Annual American-Korean Music Festival 19
Sep 09 - Air Power Day 21 Oct 09
- IRRE/CERE 2-6 Nov 09
- Thanksgiving 26 Nov 09
26 Questions Topics Youve Submitted
27- 1. If the quality of the water in the tower is
regularly checked, how do residents know the
results? - 2. Who can we address concerns regarding COLA
that is, the insufficiency of it? - 3. What is being done locally to help an
increasing number of AD spouses find employment? - 4. What is the base commander policy on dogs that
bite and the bites have been documented? If a
dog has been reported to the vet clinic and
housing offices for biting other dogs and/or
humans, what should happen to that dog? How many
bites before something will be done?
28- 5. When will our elevators be fixed? I have
lived here for over 1 year and elevator 2 has
been broken for that amount of time. - 6. Will security cameras be installed in the
towers? If not, there need to be foot patrol of
some sort especially during the summer months
when all the vandalism occurs. - 7. How do you get a Command Sponsored billet if
you are already here?
29 QUESTIONS