Title: 51st Fighter Wing Town Hall Meeting


1
51st Fighter WingTown Hall Meeting
10 September 2009
2
Tour Normalization
  • By Phase

3
Phase 1 (FY09-11)
  • FY10 objective 632 CSP met /
  • MFH shortfall will continue to rely on off-base
    capacity
  • Dorm shortfall remains
  • 7 tier 1 dorms scheduled for demo, Dorm 1472
    opens Aug 09
  • Dental expansion (1,000 capacity) ongoing
  • ADA MILCON project adds 270 parking spots in
    highly congested area
  • CDC expansion/renovation adds 28 full-time
    positions (FY11)

4
Phase 2 (FY12-16)
  • 2x MFH towers and 1x parking garage required
    (government or privatized) to avoid over-reliance
    on off-base capacity
  • USFK DoDDs projections call for 2x elementary
    school equivalents
  • Additional Medical/Dental expansion required
    (currently unprogrammed)
  • Force/Community support facility shortfalls
    apparent
  • Base roads/parking congested with no companion
    projects

5
Phase 3 (FY17-20)
  • Base population more than doubles from FY09
    baseline
  • 9x MFH towers and 5x parking garages required
    (government or privatized)
  • USFK DoDDs projections call for 2x elementary,
    1x middle, 1x high school
  • Further Medical/Dental expansion required
  • Force/Community support facility shortfalls
    continue
  • Base roads/parking overwhelmed with no
    companion projects

6
Military Family Housing
7
Projected Osan MFH Occupancy(as of 24 Jul 09)
  • 351 MFH units (2 GOQ, 19 SOQ, 2 CCC 328 MFH
    units)
  • 2 MFH Units Down for Maintenance

99 MFH Occupied in Aug 09
7
8
MFH Maintenance
  • General Maintenance
  • MFH Contractor (Dong Buk) conducts maintenance of
    your quarters 24/7 (including Holidays)
    784-2376
  • Elevators
  • Elevator maintenance contract awarded July
  • 30 of all base elevators require major repair
  • Repairs are being prioritized across entire base
    some dormitories have no working elevator.
  • 52K was obligated for repair the MFH elevators
  • Self Help Bldg 657, 784-5793
  • All self-help work requires approval through MFH
    office, including painting of the interior walls

9
Pets
  • Owners must ensure their pets do not defecate
    and/or urinate in the elevators, in the hallways,
    or on the bushes, flowers, and similar vegetation
  • Two-pet rule Caged animals (i.e. bird) fall
    under the two-pet rule
  • Residents should report animal violations (loose
    animals, stray, nuisance animals, animal bites,
    abuse, cruelty, etc) to Security Forces, BLDG
    1425, OR CALL 784-5515

10
Fire Prevention
  • Report all Fires, Even if Extinguished, on 911
  • Fire Alarm Pull Stations are for Emergency Use
    Only
  • The individual who creating false fire alarms in
    August has been charged with three criminal
    offenses
  • Never Leave Candles or Cooking Unattended
  • Two Fires in PACAF this CY, Osan and Yokota
  • Bathroom fire at Osan in July
  • Do Not Use Propane Patio-Heaters on Balconies
  • Dispose of Smoking Materials Properly

11
Normal Sprinkler Head Cover
Fire Damage MFH (Osan AB, Korea) Bathroom (14
Jul 09)
Damaged Sprinkler Note Cover Melted at 135 deg F

Mirror Cracked Counter Top Melted
Incident Date/Time 14 Jul/1500 Reported
15 Jul/0900 Ignition Source Burning Candle with
Glass Enclosure Story Resident dependent (RD)
had a candle burning in glass near bathroom wall.
Suddenly, RD heard a something popped and
checked the bathroom. RD found the corner of the
bathroom wall was catching a fire and the
flame/heat melted the sprinkler cover. After the
fire melted the cover (1 ea), a sprinkler head
popped out. RD put fire out using a cup of
water. Note Fire extinguisher was not
used. Damage Cost 800 Note Wall appeared
to have been repainted POC 51 CES, 22 Jul 09
12
Property Storage
  • Due to fire safety, no property will be placed or
    stored in stairwell, landings, corridors,
    entrances or sidewalks
  • Residents CANNOT store stuff within 18 inches
    from sprinkler heads
  • Residents CANNOT hang anything on the fire
    suppression system (including water pipes)

Blocked hallway
Uniform on sprinklers
13
Good Neighbors
  • Ensure children play in the playgrounds and not
    in the
  • parking areas or garages for safety reason
  • Bikes, skateboards, etc should be used outdoors
    only
  • Please keep common areas clean/free of vandalism
  • Quiet Hours From 2200 to 0600 on Weekend
  • From 2100 to 0600 on
    Weekdays
  • Residents may contact Security Forces _at_ 784-5515
    to report a violation of the noise ordinance.
    However, if appropriate, floor leader may speak
    with the neighbor first

14
Construction Update
15
Osan Middle School
What
  • Middle school (3 stories, 87.2K SF), Music
    Facility (1 story, 8.6K SF), Parking Structure
    including athletic court on roof (4 stories,
    194.4K SF, 383 Stalls), Announcer's booth,
    Pavilion including toilets/storage,
    Basketball/volleyball court, Sky Bridge

When
  • Project Completed in August
  • Ribbon cutting/open house will be 10 Sept

CE POC Maj Grolemund
16
FSS/DODEA Turf Field
What
  • New Artificial Turf Field
  • Full size soccer field football field
  • Low maintenance
  • Longer wear
  • No rubber pellets!

When
  • Project started 10 Aug 09
  • Projected to finish 12 Sept 09
  • Kickoff for first game 12 Sept 09

CE POC Maj Grolemund
17
Artificial Turf Softball Flds
What
  • New Artificial Turf Softball Field
  • Re-turfs fields behind fitness center
  • Low maintenance
  • Longer wear
  • No rubber pellets!

When
  • Projected Start 2010 (Funds Promised)
  • Projected to finish TBD

CE POC Maj Grolemund
18
Mustang Valley Village
What
  • Working to acquire land since 2003
  • Land will be re-developed for (possible)
  • Future School
  • Future CDC
  • Future Field House Athletic Complex

When
  • HN will Acquire Private land soon
  • Expect transfer to Osan by end of 2009
  • Possible demolition in 2010/2011

CE POC Maj Grolemund
19
Child Development Center
What
  • Adds additional space for CDC services
  • Approx 24 more full-time slots
  • Approx 48 more part-time slots
  • Located at building 345(former community
    center)--3600SF
  • Requires fire suppression and life safety design

When
  • Projected to complete in March 2011
  • Requires AF level certification of design
  • Requires fire suppression system and US-made
    materials

CE POC Maj Grolemund
20
New NCO Club
What
  • Provides 3-story Club for NCOs and SNCOs
  • Replaces Challenger NCO Club
  • Located next to Community Center
  • Serves meals for 500 people

When
  • Project to start in late December 2009
  • Completion date June 2011

CE POC Maj Grolemund
21
Dorm Renovation and Construction
What
  • Renovating Multiple Dorms
  • Under Construction 476, 731, 732, 734, 708, 720,
    709(TLF)
  • Upcoming in 2010 705, 707, 717, 718
  • New construction Amn dorm 1472
  • Future work SNCO Dorm

When
  • Dorm 1472 completed in August
  • Most dorms will come online in 2009/2010
  • 705, 707, 717, 718 will come online in 2011 and
    2012

CE POC Maj Grolemund
22
Vehicles
23
(No Transcript)
24
Parking Information for Osan
  • Currently registered vehicles on Osan 6000
  • Current parking slots on Osan 2700
  • Bottom line 2.2 vehicles registered per
    parking
  • slot

25
Upcoming Events
  • Chusok 2-4 Oct 09 (Family Day on 2 Oct 09)
  • Songtan Friendship Festival 10 Sep 09
    Cancelled
  • 1st Annual American-Korean Music Festival 19
    Sep 09
  • Air Power Day 21 Oct 09
  • IRRE/CERE 2-6 Nov 09
  • Thanksgiving 26 Nov 09

26
Questions Topics Youve Submitted
27
  • 1. If the quality of the water in the tower is
    regularly checked, how do residents know the
    results?
  • 2. Who can we address concerns regarding COLA
    that is, the insufficiency of it?
  • 3. What is being done locally to help an
    increasing number of AD spouses find employment?
  • 4. What is the base commander policy on dogs that
    bite and the bites have been documented? If a
    dog has been reported to the vet clinic and
    housing offices for biting other dogs and/or
    humans, what should happen to that dog? How many
    bites before something will be done?

28
  • 5. When will our elevators be fixed? I have
    lived here for over 1 year and elevator 2 has
    been broken for that amount of time.
  • 6. Will security cameras be installed in the
    towers? If not, there need to be foot patrol of
    some sort especially during the summer months
    when all the vandalism occurs.
  • 7. How do you get a Command Sponsored billet if
    you are already here?

29
QUESTIONS