FULL DEPTH RECLAMATION - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

FULL DEPTH RECLAMATION

Description:

The contractor blended the roadway at an ... finished the contractor had 10 calendar days to place the initial pavement surface ... Maximum- 400 PSI _at_ 28 days ... – PowerPoint PPT presentation

Number of Views:342
Avg rating:3.0/5.0
Slides: 31
Provided by: tlut
Category:

less

Transcript and Presenter's Notes

Title: FULL DEPTH RECLAMATION


1
FULL DEPTH RECLAMATION
  • Highway 25
  • Center-Hannover
  • SS-1-025(009)028

2
FDR Process
  • Blend Roadway
  • The contractor blended the roadway at an average
    depth of 9 inches (5 inches asphalt, 4 inches
    base) then returned to grade
  • The cement was not added in this pass because
    material needed to be moved to the center of the
    road for slope correction
  • The contractor used an offset stake to maintain
    centerline
  • Cement Application
  • The cement was distributed evenly across one lane
    of the roadway
  • Once the cement was applied to the roadway it was
    blended in with the existing material.
  • The roadway was compacted with a sheepsfoot
    roller following the cement application

3
  • Grading
  • Once initial compaction was completed the roadway
    was finish graded
  • The contractor was given 2 hours from the time of
    cement application to return the roadway to grade
  • A rubber tire roller then finish-rolled the
    roadway
  • After a portion of the FDR base had been
    compacted and finished the contractor had 10
    calendar days to place the initial pavement
    surface
  • Sealing
  • Prime was applied to the roadway to seal the road
    until it was paved. The roadway was then sanded
    but traffic could not return onto the completed
    section for 4 hours after initial mixing to allow
    time for the base to set up.
  • Paving
  • One 2.5 lift of Superpave FAA 40 was placed
  • The pavement was not bonding well with the base
    so tack was applied to correct this problem.

4
Advantages
  • Provides new pavement structure
  • Fast construction cycle
  • No detours
  • Traffic returns quickly
  • Minimal change in elevation
  • Conserves resources by recycling existing
    material
  • Crown and slope corrections
  • Eliminates existing reflective cracking and
    rutting

5
Disadvantages
  • May require additional effort to correct subgrade
    problems
  • Some shrinkage cracks may reflect through
    bituminous surface
  • Cement-treated materials will shrink naturally
    while curing
  • Depth limitations
  • Equipment can mill in excess of 18 but it is
    difficult to compact anything over 12
  • NDDOT requires 50 asphalt 50 aggregate
  • Cost

6
Project Cost
  • Project Length- 5.935 Miles
  • Total Cost of FDR- 1,404,448.00
  • Cost/Mile- 236,638.00
  • Average cost/mile of thin lift overlay-
  • 98,000.00

7
Base Strengths
  • Maximum- 400 PSI _at_ 28 days
  • If strength was higher than 400 PSI the base
    would crack, causing pavement cracks
  • Minimum- 200 PSI _at_ 28 days
  • 300 PSI _at_ 28 days was the goal of Materials and
    Research

8
(No Transcript)
9
(No Transcript)
10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
Existing Roadway
15
Blending Machine
16
Blending Operation
17
Loading Cement
18
Cement Distributor
19
Cement Application
20
Dust
21
Blending
22
Material Sampling
23
(No Transcript)
24
2nd Pass
25
Initial Compaction
26
Finish Blade
27
Grading Operation
28
Final Compaction
29
Finished Base Surface
30
Questions?
Write a Comment
User Comments (0)
About PowerShow.com