Title: MSBA Update
1- MSBA Update
- MMA Conference 2008
Treasurer Tim Cahill, Chair Katherine Craven,
Executive Director
2The Massachusetts School Building Authority
- Chapter 208 of the Acts of 2004 created an
independent public Authority, chaired by State
Treasurer Tim Cahill, ending the former School
Building Assistance Program administered by the
Department of Education. - The Authority is charged with
- Succeeding to the powers of the Department of
Education, inheriting approximately 11 Billion
in outstanding payments for 1156 projects
authorized under the former SBA program - Achieving the effective management, planning and
financial sustainability of the school building
assistance program - Revising regulations for a new program of grants
for school renovation and construction projects
subject to the availability of funds and a
statutory cap, beginning in FY08
3Massachusetts Version of the Marshall Plan for
School Construction
- Massachusetts has expended over 20B--15B in
state tax dollars-- on local schoolhouse capital
facilities over the past 20 years - Of the 1,817 schools in the Commonwealth, 1,156,
or 63, are currently or recently reimbursed for
construction or renovation projects undertaken
between 1986 and 2005 with an approximate MSBA
cost of 11 billion - The condition of the 1,817 Massachusetts schools
is generally good - Over 76 rated in generally good condition
- Only 3, or 62 schools, rated in need of
substantial work - There was little correlation between the relative
wealth of a school district and the general
condition of the school buildings within that
district - Almost one-half of the current school facility
square footage is new or recently renovatedare
these projects being maintained? - Massachusetts schools have been built 32 to 39
larger, on average, than the maximum gross square
footage space requirements per student in the
Department of Education regulations
4(No Transcript)
5First 3 Years Significant Progress Made
- MSBAs accomplishments to date
- Made over 5.1 Billion in payments to cities,
towns, and regional school districts - Under the former program, the state would have
taken decades to make most of these payments - Of the 428 projects on the Waiting List
- 369 projects have received a payment or have been
completely paid off - 30 audits are in process, 20 projects have still
not started, 9 projects were removed under the
Grant Conversion Program - Substantially completed over 700 audits of the
800 audit backlog inherited from the former
program. The completed audits have - Saved the taxpayers of Massachusetts over 570
Million - Generated 2.1 Billion in avoided local interest
costs - Completed first ever capital survey of 1,817
schools in the Commonwealth - Completed most comprehensive revision of program
regulations in 60 years - Developed and implemented a pay-as-you-build
Progress Payment System for projects. The new
Progress Payment System - Provides municipalities with much needed cash
flow as projects are built - Reduces the amount of debt a city, town or
regional school district needs to issue
6Waiting List Projects DOE Original Estimates vs.
Maximum Allowable Costs
In every year since 1999 the maximum cost allowed
by DOE for any given project far exceeded what
DOE originally estimated to be the cost of a
project on average costs exceeded original
estimates by almost 26
7Sales Tax Dedicated to the MSBAs School
Renovation and Construction Program
- The Commonwealth has dedicated 1 cent of the
statewide 5 cent sales tax to the MSBA for the
school renovation and construction grant program - The 1 cent is phased-in through fiscal year 2011
with a guaranteed minimum amount through fiscal
year 2009 - During a period when many other programs have
been cut or level funded, the Commonwealth has
dedicated, on average, an additional 76 Million
per year for the school renovation and
construction program.
Guaranteed
8The Authoritys Finance Plan
- Fund Waiting List
- 5.5 billion between fiscal years 2006 and 2011
( in millions)
- Fund Prior Grants
- 5.1 billion from 2005 to 2023
Completion of a final audit is necessary to
complete payments on Waiting List projects and to
determine actual annual payment amounts on Prior
Grants.
- Fund New Grants beginning in fiscal year 2008
- Capped by law at the lesser of (i) 500 million
per year growing at rate of growth of the MSBAs
portion of the sales tax up to 4.5 annually or
(ii) the availability of funds - This allows for a 2.5B New Program, Five Year
Capital Pipeline
9New SBA program has finite budget
All of the Authoritys revenue is being committed
to the following types of payments Prior Grant
projects, debt service, operations of the
authority and eventually the new program.
10The New Process
- The MSBAs enabling statute places tremendous
emphasis on planning, due diligence and
prioritization of scarce Authority resources.
The statute and MSBA regulations also require
collaboration between local districts and the
MSBA during all phases of the process. -
- The New Process
- 1. Identify the Problem
- Local community identifies deficiencies in school
facilities through the Statement of Interest
process - 2. Validate the Problem
- MSBA and local community work together to
validate deficiencies identified - Requires the MSBA and the city, town or regional
school district to agree on the problem - 3. Evaluation of potential solutions
- MSBA and local community work in collaboration to
identify potential solutions - Solution must fit within the MSBAs available
funding, long-term capital plan and will be
prioritized based on the priorities established
in G.L. c.70B s.8 - 4. Confirm the solution
- MSBA and local community agree on solution and
appropriate course of action - 5. Implement the agreed upon solution
- MSBA and local community continue collaboration
through design and construction
11Summary of SOI Submissions
- 423 Statements of Interest (SOI) submitted
- 162 different districts represented
- 91 of the SOIs are related to buildings that
were rated 1 or 2 in MSBA Needs Survey (pretty
good shape to brand new schools) - Over half the SOI relate to Elementary Schools
- Many requests are for roofs, boiler renovations,
and other moderate repairs - Include everything from overcrowding to
educational obsolescence
12Statement of Interest Submissions by Month
13SOI Diagnostic Process Overview
- Based on lessons learned from the Waiting List
projects, each district was required to choose
one priority on which the MSBA would focus the
diagnostic process - Diagnostic analysis by the MSBA includes
- Review of the SOI
- Meeting with local officials
- Site visits to assess overcrowding
- Facility assessments
- Senior studies
- Review of historical enrollment trends and
forecasts - Review of educational programs
14Senior Study - Overview
- Efficient, cost effective diagnostic tool used to
evaluate SOI - Each study team composed of an MSBA staff member
and two senior architects with extensive
knowledge of building systems and educational
programs - Studies examine both facility condition and
programmatic issues - Identify goals and concerns of the school
district - Evaluate physical condition of the facility,
including major building systems (building
envelope, HVAC, electrical distribution, interior
finishes) - Assess overcrowding or capacity issues
- Determine ability of the facility to support the
required educational program - Assess design factors such as availability of
natural light which make a schools environment
conducive to learning - Examine site considerations
- Evaluate school districts routine and capital
maintenance programs - Results summarized in concise report format
permitting review and comparison of numerous SOI
15Assessment Criteria
- Building Condition
- Building exhibits signs of moderate to severe
deficiencies in multiple building systems such
as roofing system, façade, windows and doors,
heating and ventilation systems, and electrical
distribution system. - These deficiencies adversely impact the school
facilitys ability to support the delivery of the
educational program. - Building Capacity
- Building exhibits signs of moderate to severe
overcrowding including excessive class sizes,
inadequate number of classrooms, high number of
cafeteria seatings, and conversion of
non-educational space to educational uses. - These conditions adversely impact the school
facilitys ability to support the delivery of the
educational program. - Educational Program
- The ability to support the required educational
program is adversely impacted by building
condition and/or capacity, including use of
inadequate spaces for the delivery of educational
programs. - Structural Deficiency
- Building has clearly documented structural
deficiencies that pose an immediate risk to
health and safety of building occupants.
16Senior Study Summary of Results
- Since July, Senior Studies have been conducted on
132 schools - Provide MSBA with a comparative tool for
classifying priority SOI - Created a practical knowledge base
- Many schools are functional but tired
- Worn interior finishes
- Aging mechanical systems
- Lack technology
- Some schools are overcrowded or cannot support
the required educational program - SPED instruction conducted in converted storage
closets - Classes held on auditorium stage
- Modulars used for 10 years to capacity
- Cafeterias with 5 or 6 lunch seatings
- PE conducted in corridors
- Wide disparity in level of locally supported
capital improvements (roofs, windows and
mechanical systems)
17MSBA Categorization/ Desired Outcomes
- MSBA separates all potential projects into the
following categories - Feasibility Invitation Some medium-larger scope
project will be agreed upon by MSBA and community
to solve agreed upon facility problem with
educational impact - Repair Assessment Smaller, targeted projects
over 250K that will extend useful life of a
facility (roofs, windows, HVAC) - Project Scope Invitation (2007 only) Projects
that otherwise meet the need and urgency criteria
established by C70B that commenced between
2003-2007 - Planning MSBA working with Districts whose
facility or educational needs and enrollments
require clarification or solutions are not
readily apparent. Includes MSBA sharing costs for
technical services agreed to be necessary. - Regionalization Assessment Certain districts may
lend themselves to mergers with neighbors given
small and decreasing enrollments and budget
challenges for capital and operational costs - Regional Vocational/Technical HS Non-repair,
major potential projects which each have unique
needs and local concerns - Hold Community continues to work with MSBA to
clarify Statements of Interest issues and resolve
local issues about master planning
18MSBA Board Actions November 2007
- Based on the MSBA diagnostic analysis and input
from the Facilities Assessment Subcommittee, the
Board took the following actions in November
2007 - Feasibility Invitation 49
- Repair Assessment 27
- Project Scope Invitation 7
- Planning 13
- Regionalization Assessment 12
- Regional Vocational/Technical HS 9
- Hold 45
- Total 162
19Next Steps Nota Bene
- Invitation to Collaborate on a Feasibility Study,
Repair Assessment or Invitation to Collaborate on
a Project Scope and Budget Conference is not
approval of a project. - The Moratorium ended June 30, 2007. Any city,
town or regional school district that
unilaterally proceeds with the design or
construction of a school facility without the
MSBA will be ineligible for funding. - Moving forward in the process requires
collaboration with MSBA. To qualify for funding,
districts must follow MSBA statute and
regulations which require MSBA collaboration and
approval at each step of the process. - Generally, SOIs placed in the hold category
require further information or explanation from
the district to clarify issues identified in the
SOI.
20Invitation to Collaborate on a Feasibility Study
- What this means
- This is not approval of a project. Districts
must Proceed with Caution - The city, town or regional school district will
begin to collaborate with MSBA to explore
potential solutions for identified problems - Solutions to be explored may include
non-construction options such as re-districting,
regionalization, or re-programming of existing
spaces - Next Steps
- The MSBA will schedule a meeting to begin the
process of exploring solutions for the problems
identified with your school facility - For SOIs invited to this phase, the following
will need to occur - Approval by the MSBA of an Owners Project
Manager (OPM) which will include a review by the
MSBA OPM Review Panel - Selection of Feasibility Designer through the
MSBAs Designer Selection Panel (DSP) - Submission by the district of the Initial
Compliance Certification (ICC) - Execution of a Feasibility Study Agreement with
the MSBA - Agreement will detail scope, schedule and
milestones of the Feasibility Study - MSBA will pay its share of eligible Feasibility
Study costs based on its calculation of the
district's grant reimbursement rate - If the district has already completed a
Feasibility Study it is likely that it will need
to be enhanced - MSBA will require much more robust Feasibility
Study than most studies done in the past
21Repair Assessment
- What this means
- Initial review of SOI and evaluation of facility
indicate scope of a potential project is limited
to replacement or repair of one or a limited
number of building systems - Repair would materially extend the useful life of
the school and preserve an asset that otherwise
is capable of supporting the required educational
program - Next Steps
- If studies or assessments have been recently
completed, the MSBA and the city, town or
regional school district will review the studies,
assessments and other data to confirm scope is
limited to one or a limited number of building
systems - MSBA may require new assessment, study or design
work to be completed - MSBA may require selection of designer and/or OPM
to complete feasibility study for scope of work - MSBA may conduct further site visits to verify
scope is limited and useful life of the school
would be materially extended
22Invitation to Collaborate on Project Scopeand
Budget Conference
- What this means
- Applies to the 7 Statements of Interest where the
community has made significant progress during
the moratorium (i.e. new facilities were
constructed, are under construction, or detailed
design is complete and ready for bid) - Initial review by MSBA confirms that some action
was required to correct significant deficiencies
in the existing facility - Next Steps
- MSBA will conduct a detailed scope review to
assess whether the scope and cost of the project
are appropriate and consistent with MSBA
statutes, regulations and guidelines - The scope review process may take several
meetings - The district will be required to provide design
documents, educational specifications,
educational program goals, and other information
required by the MSBA
23Planning
- What this means
- Statement of Interest submitted by school
district identified issues that may warrant
further action by MSBA, but were not clearly
stated in the SOI or evident upon MSBA diagnostic
investigations - Additional information from the district and/or
further investigations by the MSBA may required
to establish the extent of the problem and
identify the potential solution path, if needed - Next Steps
- The MSBA and the city, town or regional school
district will meet to begin the process of
understanding the issues within the school
facilities and what the best plan of action is
moving forward - The MSBA remains committed to working in
partnership with districts that were placed in
the Planning category to better understand the
issues they perceive with their school facilities
and how they impact the districts educational
program
24Regionalization Assessments
- What this means
- In reviewing certain Statements of Interest, the
MSBA identified potential opportunities to
address issues raised by the school district
through the exploration of solutions combining
regional resources - May result in capital projects which address the
educational needs of multiple school districts in
a cost effective manner - Next Steps
- The MSBA and the cities, towns or other
neighboring regional school districts will meet
to - Review any previous exploratory discussions that
may have occurred between the districts involved - Begin the process of understanding the facility
issues throughout the several districts and begin
exploring ideas on combining resources with a
goal of finding the best plan of action moving
forward - The MSBA remains committed to working in
partnership with districts that were placed in
the Regionalization Assessment category to better
understand the issues they perceive with their
school facilities and how they impact the
districts educational program.
25Regional Vocational Technical High Schools
- What this means
- Regional vocational technical high schools are
complex, high cost institutions that require
special consideration - They typically serve geographically large
regional districts which are overlaid on existing
school districts containing academic high schools
that may have other priorities which must be
coordinated - Next Steps
- The MSBA plans on performing a separate
evaluation of regional vocational technical high
schools - The evaluation process will be aided by a review
panel of key stakeholders to be formed by the MSBA
26Hold
- What this means
- Issues identified in SOI may require long range
planning - Statement of Interest did not clearly identify
issues warranting MSBA action - In some instances the issues identified in the
SOI were not verified during MSBA diagnostic
investigations - Issues identified in the SOI were clearly stated
and confirmed by diagnostic investigations but
were not of sufficient severity or urgency to
require further MSBA action at this time - Next Steps
- The MSBA will schedule a meeting with the city,
town or regional school district to begin the
process of understanding the issues within the
school facilities and what the best plan of
action is moving forward - The MSBA remains committed to working in
partnership with districts that were placed in
the Hold category to better understand the issues
they perceive with their school facilities and
how they impact the districts educational
program.
27What does this all mean?
- The categorization the 423 SOIs is the
culmination of months of due diligence and
analysis by the MSBA to determine which school
facilities across the Commonwealth are in most
need of capital investment. - The MSBA is implementing a rolling capital
pipeline for project approvals, which means that
the determinations of project progress made by
the MSBA Board of Directors on November 28, 2007
will not necessarily be the final time that any
SOIs move forward to a different phase during
this year. - In general, the category status of any SOI is
subject to change to reflect progress at any time
during the year depending upon the MSBAs
understanding of how a school facilitys need and
urgency fit within the statewide spectrum of
need. - Once a district has submitted a complete SOI, it
will not have to resubmit an SOI unless expressly
directed to do so by the MSBA or unless facility
conditions or enrollment have changed
significantly. - The MSBA is committed to spending our limited
budget as equitably as possible where we agree
that the need and urgency for projects exists.
28Your SOI was placed in the Hold, Regional
Assessment, Planning, or Voc Tech Category
- It is not the end of the process, but the
beginning of a dialogue with the MSBA about your
school facilities - MSBA will schedule a meeting to discuss your SOI
and better understand deficiencies that your
district perceives with their school facilities - The MSBA may require your district to prepare or
provide further information - The MSBA may perform further diagnostic
evaluation - If through further dialogue and diagnostic
evaluations, the MSBA determines that your SOI
meets the statutory priorities and the need and
urgency fit within the statewide spectrum of
need, your districts SOI may be moved from
current category to another appropriate category
29Your SOI was placed in the Feasibility Study,
Project Scope or Repair Assessment Category
- This is not approval of project
- The MSBA will schedule a meeting to begin
evaluating potential solutions or reviewing scope
of work - There still will be a lot of work to be done to
determine the MSBAs participation in a school
project, if any - Timing of the process depends on
- the district, the extent and urgency of the
problems, - the number of potential solutions that may need
to be explored, - the ability of the MSBA and the local district to
agree upon an educationally and financially sound
solution, - the ability of the local district to fund their
portion of the agreed upon solution, and - the many other factors that all could impact
timing.
30Designer Selection Panel
- The Designer Selection Panel (DSP) was created to
ensure an impartial and objective designer
selection process. - Any city, town or regional school district
selected to move forward to the Feasibility Study
phase of the process with a school renovation or
construction project estimated to be in excess of
5 Million, will be required to select a designer
through the MSBAs Designer Selection Panel. - City, town or regional school district prepares a
Request for Services based on scope of work from
the Feasibility Study Agreement with MSBA. - City, town or regional school district advertises
the agreed upon scope of the study, receives
submissions, check references of firms
submitting, and forwards all information gathered
to the DSP. - DSP meets to review submissions and typically
selects 3 firms that the DSP believes are most
qualified based on qualifications, past
performance, content of submissions, reference
checks and other evaluation information on file
with DCAMM, the MSBA or other agencies. - DSP typically interviews the 3 selected firms and
ranks them. It is expected that the city, town or
regional school district will negotiate and enter
a contract with the top ranked firm. - Members of the DSP include 12 permanent members
recruited from MSBA professional staff and
independent professional groups and 3 revolving
members recommended by the school district on a
project-by-project basis.
31Owners Project Manager Review Panel
- Any project over 1.5 Million is required to have
an Owners Project Manager (OPM). The MSBA must
approve OPMs for approved school projects that
exceed the 1.5 Million threshold and may require
an OPM on certain projects under the threshold. - MSBA will require a very comprehensive role for
the OPM to serve the needs of both the district
and the MSBA. Scope of services will include - Monitoring and reporting on total project budget,
schedule, cash flow - Monitoring and reporting on performance of
designer and general contractor - Facilitation in the resolution of issues between
the designer and the contractor to prevent
schedule slippage and cost overruns - Providing effective management in field
supervision of the contractor - Conducting a review for constructability, long
term maintenance and life cycle cost savings - Providing representation at project and
construction meetings - Cost estimating and control, schedule analysis,
quality control, safety - Notifying the MSBA and city, town or regional
school district of defective work - Cities, towns and regional school districts must
conduct a qualifications based selection process
for selecting an OPM and submit to the MSBA a
summary of the qualification process, the basis
of its selection and recommendation to the MSBA
for approval. - The MSBA intends, with the assistance of its OPM
Review Panel, to focus its review and approval
on - Prior relevant experience of firm, Project
Director and Project Representative in the
supervision of projects similar in type, size,
dollar value and complexity to project being
considered. - Documentable evidence of past performance -
number of projects managed, project dollar value,
number and percentage completed on time, dollar
value of change orders, safety record and number
of legal actions - Management approach
- Key Personnel
32MSBA Capital Pipeline Flow Chart
33MSBA Capital Pipeline
34Local Votes
- The MSBA will require a very specific form and
language for local votes going forward. The
format of votes must be approved by the MSBA
prior to adoption. - One project One Vote
- Vote must be a separate, stand alone vote
- Vote cannot be lumped in with any other school
facility projects or municipal projects - Vote must be project specific and must include
descriptions of - Project Site street location, parcel,
orientation on parcel where possible - Project Scope New, Renovation, Addition,
Repair, square footage, project components - Total Project Costs Local Share, MSBA grant
- Vote must include language acknowledging that
- the MSBA grant program is a non-entitlement
program - the MSBA grant program is a discretionary program
based on need, as determined by the MSBA - the school facility that is the site of the
project will remain in use as an educational
facility for the instruction of school children - any project costs in excess of the MSBA grant are
the sole responsibility of the city, town or
regional school district - The MSBAs standards for votes apply to any local
votes that may be required - Appropriations Vote
- Debt Authorization Vote
- Override Vote (if any)
- Debt Exclusion Vote (if any)
3540 Broad Street, 5th Floor Boston , MA
02109 Phone 617-720-4466Fax 617-720-5260
http//www.massschoolbuildings.org
Questions? Brian McLaughlin brian.mclaughlin_at_mass
schoolbuildings.org