Title: SUBMISSION ON
1 SUBMISSION ON ESKOMS PROPOSED INTERIM PRICE
INCREASE APPLICATION TO NERSA Mthobeli
Kolisa Executive Director Infrastructure Services
2Local government and ESKOM
- Municipalities constitute some 40 of Eskoms
customer base by sales and are therefore one of
Eskoms key stakeholders. - Undermining the financial viability of ESKOM is
not in the interest of local government. - Compromising the financial viability of 187
electricity distributing municipalities is not in
the interest of ESKOM.
3Overall comment on timing
- In terms of the MFMA Eskom is required to provide
Salga with a motivation for its proposed tariff
adjustment at least 40 days before making its
final application to Nersa. - Section 42(2) of MFMA provides that any price
adjustment not tabled in parliament before 15
March of that year may not take effect for
municipalities in the year in question. - On the 16th April 2009 SALGA received an
invitation from ESKOM to submit comments. - ESKOM proceeded to submit the same motivation to
Nersa on 5 May 2009
4Overall comment on timing
- Whilst recognising that Eskom has struggled to
reach finality with national government on its
funding model, Salga cannot understand why Eskom
was not able to submit an interim tariff
application to Nersa at an earlier stage, rather
than delaying the application to a point where
statutory timeframes are ignored and meaningful
consultation becomes impossible. - The challenge of funding the investments
necessary to ensure long-term security of supply
has been recognised for some time. - It is therefore inexplicable that Government and
Eskom have not finalised a sustainable pricing
and funding plan to secure the required
investment by now.
5Overall comment on timing
- This chaotic and incoherent approach appears to
have become the norm for the electricity sector. - SALGA is deeply concerned about the state of
affairs within the energy sector - Appeal to Nersa consider legislative compliance
regulation to be as important as price
regulation.
6Impact of noncompliance with LG legislation w.r.t
timing
- The late submission of the interim tariff
increase, and the anticipated further MYPD tariff
increase application creates substantial
practical and legal problems for municipalities. - Section 24(1) of the MFMA requires that a
municipalitys annual budget be approved 30 days
before the commencement of the financial year
(before end of May). - Municipalities find it difficult to justify draft
budgets that reflect tariff increases that are
based on bulk electricity tariffs that have not
been set in terms of the law. - If NERSAs ruling differs from the increase
anticipated in municipal budgets then there will
be problems related to budget adjustments. - NT recommends one budget adjustment per annum and
in terms of Section 28 of the MFMA such an
adjustment does not include adjustment of tariffs
themselves this will compromise the financial
viability of municipalities if the increase is
more than what is budget for by municipalities.
7Impact of noncompliance with LG legislation w.r.t
risk
- Section 42(2) of MFMA provides that any price
adjustment not tabled in parliament before 15
March of that year may not take effect for
municipalities in the year in question. - Likely to lead to steep increase(s) in the
following year(s) and resultant decline in levels
of payment by consumers! - In 2008 the Minister of Finance issued notices
that purported to exempt municipalities from
complying with the budget process requirements of
the MFMA - This practice poses substantial adverse
implications for municipalities. - NMBM obtained a legal opinion which indicated
that the Ministers notice could have been
unlawful. - This put municipalities at considerable risk of
having their tariff approval and budget processes
set aside by an aggrieved consumer on the basis
that the notices are unlawful.
8Scale of the requested interim tariff increase
- Concerned about the impact of a 34 tariff
increase on consumers, and in particular on the
poor, many of whom are already struggling to pay
municipal services. - Also sensitive for the need for Eskoms tariffs
to cover operating costs and to enable the
financing of the utilitys large capital
expenditure programme. - Notes that the 34 increase excludes a range of
cost items, including the - pending 2c/kWh environmental levy,
- cost of road construction and maintenance,
- cost of non-Eskom generators,
- cost of DSM,
- cost of climate change mitigation, and
- additional cost of liquid fuels.
9Scale of the requested interim tariff increase
- Salgas understanding is that Eskom has not
requested Nersa to make an adjustment to the
proposed tariff increase to factor in these cost
items. - The application itself does not include details
of how Eskom arrived at 34 - Cognisant of the fact that, based on information
available at the time, an indication was given to
Eskom by Nersa in 2008 that Nersa may grant a 25
price increase (in real terms) and that
municipalities were advised by National Treasury
to budget for 34 bulk electricity price
increase.
10CONCLUSIONS AND RECOMMENDATIONS
- Will accept a Nersa decision that
- takes into account the parameters envisaged in
the NT circular - an increase above these
parameters will jeopardise the financial
viability of municipalities. - minimizes the possibility of steep increases in
the future - minimizes the risk to municipalities of having
their tariff approval and budget processes set
aside by an aggrieved consumer on the basis that
the process was unlawful. - The amount of national fiscus FBE subsidy for the
poor must take into account the costs that
municipalities will have to incur to provide FBE
to the poor. - Wish to state categorically that any further
tariff increase during the 09/10 municipal
financial year will be unacceptable - The next tariff adjustment will have to coincide
with the FY10/11 municipal budgeting process, as
mentioned above.
11CONCLUSIONS AND RECOMMENDATIONS
- Wish to propose to Nersa that the following cost
items that are not included in the Eskom interim
price application should be considered in the
context of the MYPD2 and not in this interim
increase application - 2c/kWh environmental levy
- the cost of road construction and maintenance
- the cost of non-Eskom generators
- the cost of DSM,
- the cost of climate change mitigation
- the additional cost of liquid fuels
- Moving forward, it is proposed that bulk
electricity price increases should be approved
for implementation with effect from 1 July for
all customers.