SUBMISSION ON - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

SUBMISSION ON

Description:

... tariff adjustment at least 40 days before making its final application ... budget be approved 30 days before the commencement of the financial year (before ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 12
Provided by: kaz81
Category:
Tags: submission

less

Transcript and Presenter's Notes

Title: SUBMISSION ON


1
SUBMISSION ON ESKOMS PROPOSED INTERIM PRICE
INCREASE APPLICATION TO NERSA Mthobeli
Kolisa Executive Director Infrastructure Services
2
Local government and ESKOM
  • Municipalities constitute some 40 of Eskoms
    customer base by sales and are therefore one of
    Eskoms key stakeholders.
  • Undermining the financial viability of ESKOM is
    not in the interest of local government.
  • Compromising the financial viability of 187
    electricity distributing municipalities is not in
    the interest of ESKOM.

3
Overall comment on timing
  • In terms of the MFMA Eskom is required to provide
    Salga with a motivation for its proposed tariff
    adjustment at least 40 days before making its
    final application to Nersa.
  • Section 42(2) of MFMA provides that any price
    adjustment not tabled in parliament before 15
    March of that year may not take effect for
    municipalities in the year in question.
  • On the 16th April 2009 SALGA received an
    invitation from ESKOM to submit comments.
  • ESKOM proceeded to submit the same motivation to
    Nersa on 5 May 2009

4
Overall comment on timing
  • Whilst recognising that Eskom has struggled to
    reach finality with national government on its
    funding model, Salga cannot understand why Eskom
    was not able to submit an interim tariff
    application to Nersa at an earlier stage, rather
    than delaying the application to a point where
    statutory timeframes are ignored and meaningful
    consultation becomes impossible.
  • The challenge of funding the investments
    necessary to ensure long-term security of supply
    has been recognised for some time.
  • It is therefore inexplicable that Government and
    Eskom have not finalised a sustainable pricing
    and funding plan to secure the required
    investment by now.

5
Overall comment on timing
  • This chaotic and incoherent approach appears to
    have become the norm for the electricity sector.
  • SALGA is deeply concerned about the state of
    affairs within the energy sector
  • Appeal to Nersa consider legislative compliance
    regulation to be as important as price
    regulation.

6
Impact of noncompliance with LG legislation w.r.t
timing
  • The late submission of the interim tariff
    increase, and the anticipated further MYPD tariff
    increase application creates substantial
    practical and legal problems for municipalities.
  • Section 24(1) of the MFMA requires that a
    municipalitys annual budget be approved 30 days
    before the commencement of the financial year
    (before end of May).
  • Municipalities find it difficult to justify draft
    budgets that reflect tariff increases that are
    based on bulk electricity tariffs that have not
    been set in terms of the law.
  • If NERSAs ruling differs from the increase
    anticipated in municipal budgets then there will
    be problems related to budget adjustments.
  • NT recommends one budget adjustment per annum and
    in terms of Section 28 of the MFMA such an
    adjustment does not include adjustment of tariffs
    themselves this will compromise the financial
    viability of municipalities if the increase is
    more than what is budget for by municipalities.

7
Impact of noncompliance with LG legislation w.r.t
risk
  • Section 42(2) of MFMA provides that any price
    adjustment not tabled in parliament before 15
    March of that year may not take effect for
    municipalities in the year in question.
  • Likely to lead to steep increase(s) in the
    following year(s) and resultant decline in levels
    of payment by consumers!
  • In 2008 the Minister of Finance issued notices
    that purported to exempt municipalities from
    complying with the budget process requirements of
    the MFMA
  • This practice poses substantial adverse
    implications for municipalities.
  • NMBM obtained a legal opinion which indicated
    that the Ministers notice could have been
    unlawful.
  • This put municipalities at considerable risk of
    having their tariff approval and budget processes
    set aside by an aggrieved consumer on the basis
    that the notices are unlawful.

8
Scale of the requested interim tariff increase
  • Concerned about the impact of a 34 tariff
    increase on consumers, and in particular on the
    poor, many of whom are already struggling to pay
    municipal services.
  • Also sensitive for the need for Eskoms tariffs
    to cover operating costs and to enable the
    financing of the utilitys large capital
    expenditure programme.
  • Notes that the 34 increase excludes a range of
    cost items, including the
  • pending 2c/kWh environmental levy,
  • cost of road construction and maintenance,
  • cost of non-Eskom generators,
  • cost of DSM,
  • cost of climate change mitigation, and
  • additional cost of liquid fuels.

9
Scale of the requested interim tariff increase
  • Salgas understanding is that Eskom has not
    requested Nersa to make an adjustment to the
    proposed tariff increase to factor in these cost
    items.
  • The application itself does not include details
    of how Eskom arrived at 34
  • Cognisant of the fact that, based on information
    available at the time, an indication was given to
    Eskom by Nersa in 2008 that Nersa may grant a 25
    price increase (in real terms) and that
    municipalities were advised by National Treasury
    to budget for 34 bulk electricity price
    increase.

10
CONCLUSIONS AND RECOMMENDATIONS
  • Will accept a Nersa decision that
  • takes into account the parameters envisaged in
    the NT circular - an increase above these
    parameters will jeopardise the financial
    viability of municipalities.
  • minimizes the possibility of steep increases in
    the future
  • minimizes the risk to municipalities of having
    their tariff approval and budget processes set
    aside by an aggrieved consumer on the basis that
    the process was unlawful.
  • The amount of national fiscus FBE subsidy for the
    poor must take into account the costs that
    municipalities will have to incur to provide FBE
    to the poor.
  • Wish to state categorically that any further
    tariff increase during the 09/10 municipal
    financial year will be unacceptable
  • The next tariff adjustment will have to coincide
    with the FY10/11 municipal budgeting process, as
    mentioned above.

11
CONCLUSIONS AND RECOMMENDATIONS
  • Wish to propose to Nersa that the following cost
    items that are not included in the Eskom interim
    price application should be considered in the
    context of the MYPD2 and not in this interim
    increase application
  • 2c/kWh environmental levy
  • the cost of road construction and maintenance
  • the cost of non-Eskom generators
  • the cost of DSM,
  • the cost of climate change mitigation
  • the additional cost of liquid fuels
  • Moving forward, it is proposed that bulk
    electricity price increases should be approved
    for implementation with effect from 1 July for
    all customers.
Write a Comment
User Comments (0)
About PowerShow.com