Title: Integrated Management Systems Industry View 2
1Integrated Management SystemsIndustry View 2
- Michael Thompson BSc (Eng), FFICE, MCIWEM
- Roe Thompson Limited
A Member of the Team Focus Group
2What is Integrated Management?
- The intents of Integrated Management are
- to improve delivery of the specified product to
the customer - to improve communication to the man at the sharp
end - to remove duplication of paperwork arising from
operating separate management systems which
actually have a lot in common. - We cannot ignore the close affiliation of these
intents with those of the Partnering approach.
3What is Integrated Management?
- These intents can be achieved in a Project
through the Partnering or Team approach by
setting up, to all intents and purposes, a Single
Organisation which can draw from the several
organisations involved - Better control of the Project and the finished
product can be attained - Some of the annual performance targets,
suggested by Sir John Egan in Rethinking
Construction (July 1998), can be approached - We will get ever closer to the concepts of Best
Practice
4Rethinking Construction
ANNUAL PERFORMANCE TARGETS
5What is Best Practice?
- There is no single definition for Best Practice.
- One definition
- It is the achievement of all the goals laid down
by a Project Team (including the Client) for the
final product, by consideration of the best
techniques of procurement, contract strategy,
quality assurance and good supply management.
6Can we do things better?
- When we look back, could we have done better with
our projects? - Even with the Partnering / Team approach could we
have done better? - Should we not strive for 100 in Excellent?
- Would not then Best Practice be achieved?
7Case History Pennington WwTW
- Four organisations, working together without
walls between them - Client- Southern Water
- Project Manager- Montgomery Watson
- Designer- McDowells
- Contractor- Birse Construction
8The Challenge
- Build a brand new sewage treatment works from
outline design on a green field site within 21
months and within budget - Undertake the earthworks during the worst period
of the year!.
9A Quick Start
- The Project started on 24 July 1995
- The Team Building Workshop took place on 31 July
1995 and a Charter agreed and signed - The Value Management Workshop commenced on 2
August 1995 - A firm outline design was in place within 10 days.
10The Charter
- Mission Statement
- Our project objectives are to deliver the scheme
to the desired quality and levels of service at
the lowest life-cycle cost and highest value, on
time and with no surprises to the satisfaction of
all Partnering Team Organisations
Alliance Charter
11The Pennington Organisation
Independent of the Pennington Team was a firm of
Quantity Surveyors auditing expenditure, using
the Contractors cost files.
12Value Management
- The Team underwent an intensive VM workshop phase
within the first three weeks of scheme
commencement - This developed an optimum outline design
- The Clients Operations personnel signed up to
the Teams outline design on completion of the VM
workshop
13V M Cost Comparisons
Preferred option - Scenario 5
14The Programme Advantage
- Typical comparison
- Partnering (Integrated Management) - 21 months
- DC - 26 months
- Conventional - 30 months
- Savings in time ? Savings in cost
Partnering
Design and Construct
Conventional
15The Pennington Contol Plan
- The foundation of the Integrated Management
System, the Control Plan (Project Management
Plan) addressed all aspects of the Scheme - It linked to the Plans of all four parties in the
Partnership
16Principal Issues Addressed
- The Partnership and its Arrangement
- Contracts
- Quality Systems and Procedures
- Safety (incl. CDM)
- Environment
- Programme
- Variation orders
- Reporting
- Design
- Procurement
- Manufacture
- Construction
- Installation
- Commissioning
- Performance Testing
- HS File (inc. OM)
- Successes Lessons Learnt
17The Filing System
- A Single Filing System for all to use.
- No letters between partners, but confirmation
memos - Other files between Contractor and
Sub-contractors also accessible - Everything auditable.
18Some Pennington Successes
- Rapid establishment of the design with confidence
through Value Management processes - Effective Risk Management relating to Planning
Permission and Discharge Consent - Design and construction taking place concurrently
- Rapid appointment of sub-contractors
- Self supervision of construction works (TQM
approach) - Joint planning with Operations the testing and
commissioning of the Plant - Fast resolution of earthworks problems
19Pennington - Conclusion
- Completed and commissioned 2 weeks early
- Completed 700,000 within budget
- Self-supervised - quality excellent!
- Good Health Safety record
- Environmental constraints observed
- But in retrospect, we are sure that we could have
done better!
20Where to next?
- Hundreds of Project Teams are being formed
annually, adopting the Partnering Approach with
Integrated Management - Many of these are producing successful projects
- But remarkably the approach is still very new for
a good many in the construction industry - More and more need to understand the benefits
that can be achieved through the approach,
particularly at a senior level.