Integrated Management Systems Industry View 2 - PowerPoint PPT Presentation

About This Presentation
Title:

Integrated Management Systems Industry View 2

Description:

... design was in place within 10 days. 10. RTL. Alliance Charter. The Charter ... intensive VM workshop phase within the first three weeks of scheme commencement ... – PowerPoint PPT presentation

Number of Views:52
Avg rating:3.0/5.0
Slides: 21
Provided by: MichaelT67
Learn more at: http://www.teamfocus.org
Category:

less

Transcript and Presenter's Notes

Title: Integrated Management Systems Industry View 2


1
Integrated Management SystemsIndustry View 2
  • Michael Thompson BSc (Eng), FFICE, MCIWEM
  • Roe Thompson Limited

A Member of the Team Focus Group
2
What is Integrated Management?
  • The intents of Integrated Management are
  • to improve delivery of the specified product to
    the customer
  • to improve communication to the man at the sharp
    end
  • to remove duplication of paperwork arising from
    operating separate management systems which
    actually have a lot in common.
  • We cannot ignore the close affiliation of these
    intents with those of the Partnering approach.

3
What is Integrated Management?
  • These intents can be achieved in a Project
    through the Partnering or Team approach by
    setting up, to all intents and purposes, a Single
    Organisation which can draw from the several
    organisations involved
  • Better control of the Project and the finished
    product can be attained
  • Some of the annual performance targets,
    suggested by Sir John Egan in Rethinking
    Construction (July 1998), can be approached
  • We will get ever closer to the concepts of Best
    Practice

4
Rethinking Construction
ANNUAL PERFORMANCE TARGETS
5
What is Best Practice?
  • There is no single definition for Best Practice.
  • One definition
  • It is the achievement of all the goals laid down
    by a Project Team (including the Client) for the
    final product, by consideration of the best
    techniques of procurement, contract strategy,
    quality assurance and good supply management.

6
Can we do things better?
  • When we look back, could we have done better with
    our projects?
  • Even with the Partnering / Team approach could we
    have done better?
  • Should we not strive for 100 in Excellent?
  • Would not then Best Practice be achieved?

7
Case History Pennington WwTW
  • Four organisations, working together without
    walls between them
  • Client- Southern Water
  • Project Manager- Montgomery Watson
  • Designer- McDowells
  • Contractor- Birse Construction

8
The Challenge
  • Build a brand new sewage treatment works from
    outline design on a green field site within 21
    months and within budget
  • Undertake the earthworks during the worst period
    of the year!.

9
A Quick Start
  • The Project started on 24 July 1995
  • The Team Building Workshop took place on 31 July
    1995 and a Charter agreed and signed
  • The Value Management Workshop commenced on 2
    August 1995
  • A firm outline design was in place within 10 days.

10
The Charter
  • Mission Statement
  • Our project objectives are to deliver the scheme
    to the desired quality and levels of service at
    the lowest life-cycle cost and highest value, on
    time and with no surprises to the satisfaction of
    all Partnering Team Organisations

Alliance Charter
11
The Pennington Organisation
Independent of the Pennington Team was a firm of
Quantity Surveyors auditing expenditure, using
the Contractors cost files.
12
Value Management
  • The Team underwent an intensive VM workshop phase
    within the first three weeks of scheme
    commencement
  • This developed an optimum outline design
  • The Clients Operations personnel signed up to
    the Teams outline design on completion of the VM
    workshop

13
V M Cost Comparisons
Preferred option - Scenario 5
14
The Programme Advantage
  • Typical comparison
  • Partnering (Integrated Management) - 21 months
  • DC - 26 months
  • Conventional - 30 months
  • Savings in time ? Savings in cost

Partnering
Design and Construct
Conventional
15
The Pennington Contol Plan
  • The foundation of the Integrated Management
    System, the Control Plan (Project Management
    Plan) addressed all aspects of the Scheme
  • It linked to the Plans of all four parties in the
    Partnership

16
Principal Issues Addressed
  • The Partnership and its Arrangement
  • Contracts
  • Quality Systems and Procedures
  • Safety (incl. CDM)
  • Environment
  • Programme
  • Variation orders
  • Reporting
  • Design
  • Procurement
  • Manufacture
  • Construction
  • Installation
  • Commissioning
  • Performance Testing
  • HS File (inc. OM)
  • Successes Lessons Learnt

17
The Filing System
  • A Single Filing System for all to use.
  • No letters between partners, but confirmation
    memos
  • Other files between Contractor and
    Sub-contractors also accessible
  • Everything auditable.

18
Some Pennington Successes
  • Rapid establishment of the design with confidence
    through Value Management processes
  • Effective Risk Management relating to Planning
    Permission and Discharge Consent
  • Design and construction taking place concurrently
  • Rapid appointment of sub-contractors
  • Self supervision of construction works (TQM
    approach)
  • Joint planning with Operations the testing and
    commissioning of the Plant
  • Fast resolution of earthworks problems

19
Pennington - Conclusion
  • Completed and commissioned 2 weeks early
  • Completed 700,000 within budget
  • Self-supervised - quality excellent!
  • Good Health Safety record
  • Environmental constraints observed
  • But in retrospect, we are sure that we could have
    done better!

20
Where to next?
  • Hundreds of Project Teams are being formed
    annually, adopting the Partnering Approach with
    Integrated Management
  • Many of these are producing successful projects
  • But remarkably the approach is still very new for
    a good many in the construction industry
  • More and more need to understand the benefits
    that can be achieved through the approach,
    particularly at a senior level.
Write a Comment
User Comments (0)
About PowerShow.com