Genova Site - Report
  • C.Gemme, G. Darbo, V.Kostyukhin INFN / Genova
  • Copy of the talk
  • http//www.ge.infn.it/ATLAS/SQTF/Minutes/Minutes_0
    5-03-10_aux/

2
Status of Loaded Staves
Spreadsheet complete
LOAD/therm.cycles/ STAVE Test
Survey
Load date
Stave ID
X / X / X
X
X
18/08/2004
S4004
X / X / X
X
X
27/10/2004
S4028
X / X / X
To be filled with el. test
X (to be remade, CTE mismatch not taken into
account)
22/11/2004
S4024
To be filled with el. test
X / X / X
X
19/12/2004
S4048
To be filled with el. test
X / X / on going
X
26/01/2005
S4038
04/03/2005
S4016
3
Mini milestones
  • We foresee to finish the current stave next
    Friday. The next 3 staves will be loaded in the
    next 4 weeks completion date 8/4.
  • We are able to load 1 per week and we keep 1 week
    more for safety and Easter slow down.
  • Survey takes 1/2 day
  • LOAD test Thermal cycles STAVE test takes lt 1
    week.
  • 4 SURFs have been put to work and source is moved
    automatically.
  • We are waiting from Joern a multi module analysis
    version of his program to automatically fill
    spreadsheets and PDB. We have a backlog of 3
    staves.
  • We foresee to finish the 3 staves by 15/4.

4
Status of Loaded Sectors/Staves
Dates correspond to start loading Ref.
http//www.ge.infn.it/ATLAS/SQTF/home_frames/home_
QP_Tables.html