Britannia Village Flood Control System - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

Britannia Village Flood Control System

Description:

30 day public review period. Project Plan Amendment (if necessary) 'Notice of ... Field Layout and Site Meetings with Landowners early April to mid-May ... – PowerPoint PPT presentation

Number of Views:302
Avg rating:3.0/5.0
Slides: 31
Provided by: bruce120
Category:

less

Transcript and Presenter's Notes

Title: Britannia Village Flood Control System


1
Britannia Village Flood Control System
  • Information Meeting for Directly Affected
    Landowners
  • February 5, 2009

2
Agenda
  • Introductions
  • (D.Downey)
  • The Projects History to date
  • (B.Reid)
  • The Planning and Design Process
  • (D.Yaeger)
  • The Project Schedule
  • (D.Yaeger)
  • About Easement Agreements
  • (B. Reid)
  • The Special Service Charge Process
  • (G.Gill)

3
Introductions
  • Moderator Diane Downey (RVCA Communications)
  • Speakers
  • Dave Yaeger Delcan Corporation
  • Gina Gill Ottawa, Infrastructure Services
  • Bruce Reid RVCA
  • Waterfront Landowners

4
(No Transcript)
5
The Island
The Flood Plain
6
Project History to Date
  • May, 1979 max. water level 60.26m
  • 1980 Construction of some sea walls and berms to
    60.3m
  • 1984 1100 year flood 60.77m
  • 1992 flood damage reduction study
  • 1996 to 2007 community discussions
  • Sept 2007 Council approval to proceed with a
    remedial flood control project

7
Design Criteria Considerations
  • Protection against 1100 year flood level under
    calm winds, with 30 cm freeboard 61.1 m
  • Berms and seawalls
  • Land-side drainage
  • Permits and easements
  • Ministry of Natural Resources
  • Fisheries and Oceans Canada
  • Private landowners

8
Planning and Design Process
  • Engineering Phase 1
  • review background
  • update cost estimate
  • Completed Aug. 2008
  • Novatechs 2005 preliminary design can
  • be used as the starting point for detail
  • Design.
  • Updated Construction Cost 525,000

9
Conceptual Design
10
(No Transcript)
11
Conceptual Design
12
Conceptual Design
13
Conceptual Design
14
Conceptual Design
15
Conceptual Design
16
Conceptual Design
17
Conceptual Design
18
Planning and Design Process
  • Engineering Phase 2
  • Initiated November 2008
  • Environmental impacts analysis
  • Site meetings with Landowners
  • Detailed physical surveys
  • Preliminary design drawings
  • Finalized Drawings

19
Environmental Assessment
  • In accordance with
  • Conservation Ontarios Class
  • Environmental Assessment for
  • Remedial Flood and Erosion Control
  • Projects
  • (approved by Ont. Min. of the Environment, June ,
    2002)

20
Environmental Assessment
  • Notice of Intent
  • Community Liaison Committee
  • Environmental Impacts Analysis
  • Project Plan
  • Notice of Filing
  • 30 day public review period
  • Project Plan Amendment (if necessary)
  • Notice of Project Approval
  • Notice of Project Completion

21
Project Schedule

22
Project Schedule (continued)

Subject to confirmation that pre-tender
construction cost estimate and lowest acceptable
tender amount remain within City Councils
approved budget
23
Permanent Easements
  • convey rights to enter and occupy a specific area
    of the property for a specific purpose
  • registered against title, runs with the deed
  • The Area defined by registered plan
  • Purpose for construction and maintenance of the
    flood control system and its component parts

24
Easement Process
  • Step 1 (April - May) permanent easement
    acquisition agreements
  • sets out RVCAs obligations
  • installations per engineering drawings
  • site restoration, warranty provisions
  • protection of adjacent works
  • reimbursement of legal fees
  • landowner agrees to grant permanent easement

25
re filled crown land
  • MNR approval requires consultation with owners of
    immediately adjacent upland property

26
Easement Process
  • Step 2 construction proceeds in accordance with
    permanent easement acquisition agreements
  • Step 3 (after construction) R-Plan prepared by
    surveyor and deposited at Land Registry Office
  • Step 4 execution and registration of documents
    for transfer of easement

27
Special Service Charges
  • Ontario Regulation 305/02 and Section 326 of the
    Municipal Act 2001 allow the recovery of costs
    related to Special Service works from landowners
    via their tax bill
  • Additional funding request currently scheduled to
    proceed to committee and council in April 2009
  • No change to cap on cost recovery amount from
    property owners

28
Special Service Charges
  • All costs will be recovered over the course of a
    ten-year period, with carrying costs as necessary
  • Yearly charge amount for a property will be based
    on the property's assessed value relative to that
    of the rest of the properties in the Special
    Service area
  • Charge will be an additional levy amount on the
    final tax notice for each property, due and
    payable at the same time as the property taxes
  • Approximately 60 per year, per 100,000 of
    assessed value, for each property assessed in a
    single-family residential tax class

29
Next Steps
  • Field Layout and Site Meetings with Landowners
    early April to mid-May
  • Please sign a consent form for the field layout
  • Please leave your contact info with us

30
Questions?
Write a Comment
User Comments (0)
About PowerShow.com