Title: Farmington Field Office Minimizing Impacts in Oil
1Farmington Field OfficeMinimizing Impacts in Oil
Gas Development Through Implementation of BMPs
- Steve Henke
- District Manager
2(No Transcript)
3(No Transcript)
4Federal Units
- Nearly half the basin is covered in Federal Units
- A single operator per unit results in well
planned development of the resource
5Setting Standards(raising the bar)
- Utilizing existing infrastucture
- -Focus on re-completions (commingles), twin
locations, new technology (directional drilling)
and mitigation measures - Roads
- Reseeding
- Pits/fencing
- Drilling location rehabilitation
6Collaborative Groupsto Achieve Consensus
- San Juan Basin Working Group
- -NMOGA sponsored
- Public Roads Committee
- Govt./Grazing and OG Committee
- -Rancher/surface owner participates in siting
decisions
7Conditions of Approval (COAs)
- All well ties in existing roads
- Pad size and production lay-out standardization
- Produced water gathering systems where feasible
- Interim reclamation
8Twinned Locations
9Directional Well Types Used in the San Juan Basin
S Shape
Horizontal
Extends reach beyond current spacing unit
Exposes more reservoir to drainage
10Directional Drilling
Minimize Surface Impact By drilling multiple
wells From a single pad
11Commingled Completion of Producing Intervals
Ojo Alamo
Kirtland Shale
Fruitland Coal
Pictured Cliffs
Both horizons Producing from Same well
Mesaverde
Dakota
12Roads
- Over 5,200 miles of dirt roads on BLM in the
basin - Developed a road maintenance agreement with
industry - 14 Road Maintenance Units
- Funding is pro-rated based on number of wells
- Spent over 2.2 million last year in maintenance
- Have surface owner/ rancher representatives on
each of the 14 units
13Transportation Planning
- Upgrade of collector roads to Gold Book standards
within 10 years - Plan for all 14 units
- - Off-Highway-Vehicle (OHV) designations
- - Road closures and rehabilitation
- - Road retention, maintenance and
- upgrade
14(No Transcript)
15Roads Arkansas Loop (before)
- Extremely muddy and rutted Arkansas Loop
roadway. - Exposed pipeline in roadway being driven over.
16Arkansas Loop (after)
- Road is crowned, elevated pipeline is covered
and a layer of crushed sandstone is added on top
to prevent rutting during wet weather reseeding
of adjacent pipeline corridor and roadside areas.
17Laying Pipe along ROW
- Stringing pipe at trench. Pipeline located
adjacent to existing road to minimize
disturbance. - Pipe laying machine in action.
18Reclaim Unnecessary Roads(500 miles targeted for
future closure)
19Environmental Compliance
- Communicate Expectations
- 100 compliance on all new surface disturbance
for wells, pipelines and roads - Feedback loop to permitting staff from compliance
staff (continual process improvement) - Established standards for interim well site
reclamation
20Post-construction Compliance
- Well site reclamation
- Reseeding pipeline right-of-way
-
21Interim Rehabilitation
- Interim rehabilitation of well pad
- Pipeline rehab.
22Minimize Long-term Disturbance
- Recent well pad with tear-drop shape and crushed
sandstone roadbase - Tear-drop location with interim rehabilitation
23Properly Contoured Well Sites
24Wildlife Seasonal Closures (483,807 acres)
25Preservation of Raptor Habitat
- 37 wintering ACEC units consisting of 4,141 acres
- Largest population of wintering Bald Eagles on
BLM in New Mexico - ACEC Areas closed from November to March to
minimize habitat loss
26Preventive Measures to Protect Wildlife
- Expanded steel mesh required on all open tanks to
protect birds and small mammals. - Coned screens are placed on separator stacks to
prevent entry by bats birds.
27Minimizing Truck Traffic
- Telemetry truck trips to well sites occur only
when problems are evident and servicing is
required - Centralized water disposal facilities with water
gathering systems reduces trips by water haulers
28Good Neighbor Initiative Compressor Noise
- Compressors are used in the oil field to enhance
gas production. - Compressor Noise however can have a negative
impact on quality of life for nearby residents,
recreational users, and wildlife. - As gas field matures, the compression
requirements will increase
29Noise Sensitive Areas(NSAs)
- 12 Boundary Focused Noise Sensitive Areas
- 50 Receptor Focused Noise Sensitive Area
- Apply adaptive management to monitor and adjust
priorities.
30Noise Abatement Structures
Noise suppression features in an ACEC (upper
left) and within the urban interface
31Reseeding
- Agreement to modify seeding stipulations
- Better oversight of contractor work
- Alternative technology (high intensity livestock
use) - Study/Recommendations from New Mexico State
University seeding mix
32Experimental Seeding
- Co-op with industry, BLM, and NMSU Agriculture
Science Station - Testing 16 different seed varieties (both native
and non-native) on various soil types
33Fencing Facilities
- Before Fence down berms eroded (easy access by
wildlife and livestock). - After Fence has top-rail berm armored with
gravel walk-over access installed produced
water pipe for easy access by hauler.
34Off-Site Mitigation
- Voluntary program started in 2002 (all majors are
participating) - 1,000/acre contribution
- 70 to achieve land health standards on grazing
allotments. - Recommendations for fund expenditures are made to
BLM by the San Juan County Farm and Ranch
Improvement Board. - 977,000 contributed to date
- 30 for BLM on monitoring/studies and Special
Management - Areas (wildlife, recreation, cultural, TE,
riparian) projects
35Goals of the Offsite Program
- Mitigate long term surface disturbance
- Mitigate loss of forage for Livestock and
Wildlife - Mitigate Habitat Fragmentation
- Work in Partnership for improving rangeland and
watershed health - Develop and maintain a partnership with industry,
ranchers, and the public that works toward
improving the landscape for future generations.
36Helicopter Supported Reseeding and Aerial
Tebuthiuron Treatments
37Riparian Stabilization
- Youth Conservation Corps constructing Largo
Canyon sediment traps
38Hydromower Treatment to Restore Mosaic Landscape
39 Water Reservoir Water Well
40Interim Reclamation of Well Pads
After drilling and completion of a gas well, all
free standing fluids from the pits will be
hauled off for disposal.
After the fluids have been hauled off the liner
is removed to the mud line and hauled to a
disposal facility.
41After closing the reserve pit and the blow pit
the location is prepared for the seeding process.
Pit Clean-Up
- Re-define diversions
- Re-contour slopes
- Incorporate BMPs
- Define teardrop driving pattern
42Seeding Site
Seeding Process
- Select seed mixtures
- Appropriate seed depth
- Site specific concerns
- Land owner preferences
43Seeding Site
Mulching Process
- Retains moisture
- Control wind erosion
- Control water erosion
44Straw Mulching
The final process is crimping of the mulch.
This ensures that the mulching is anchored, which
prevents wind and water erosion and also
stabilization of soils.
45Reserve pit and blow pit area have been closed
and re-contoured.