Title: Building a Brigade Combat Team
1Ft Bliss Expansion Program
- Building a Brigade Combat Team
- 2007 Texoma-Missouri River
- Regional Education and Training Conference
- 10 October 2007
2Ft Bliss Expansion Program
- Objective of todays presentation
- Discuss the current state of the execution plan
developed 2 ½ years ago to delivery 2 Bil of
mission critical and community facilities to Ft
Bliss
3Ft Bliss Execution Plan
- Required Criteria
- Meet MILCON Transformation Objectives
- Meet Small Business Goals
- Utilize Other Corps Districts in the Region
- Be Flexible
- Desirable Features
- Incorporated Elements of the COS concept
- Engaged all Supporting District at Program
Start-up
4MT Objectives
- Army sets facility requirements and standards
- Standardization facilities processes
- Continuous building program
- Manufactured building solutions - Types I-V
construction - Longer term customer and industry (IDIQs)
relationships
- Army standards were used
- User requested change process in effect
- Model RFP used on All Facilities
- Centralized Bidder Inquiry System
- Major Project started every six months
- Maximum effort to provide a level funding flow
across the program
- Barracks, COFs
- Headquarters in CAB as a prime contract
- IDIQ Contract durations set-up to meet three
years projection
Quality facilities delivered in less time at
lower cost
5Execution Timeline
Apr 05 Execution Planning Started Jun 05 Land
Development / Product-line Concept Approved Aug
05 Product Delivery Team Formed Sep 05 Interim
LDE Hired Nov 05 BRAC 05 Enacted Jan 06 PL
Solicitation Issued Mar 06 Projects
Authorized May 06 LDE Task Order Issued Aug
06 First PL and Infrastructure Task Orders
Issued Sep 06 Turned Dirt Feb 07 PL Foundation
Work Started Mar 08 First Buildings
Completed Sep 08 1st Brigade Combat Team Fully
Occupied
6Brigade Combat Team
BCT Configurations Heavy Light Stryker
Future Combat Systems Other Unit Types
Combat Aviation Brigade Fires Brigade
Sustainment Brigade
7Brigade Combat Team Footprint
390M 1.4M SF 40 Buildings 230K SY
Parking
Approx. 300 Acre Site
8Biggs AAF and East Biggs
The Challenge
- 50 Projects
- 250 Buildings
- 2,500 Acres
- 20,000 Soldiers
- 8,000,000 SF
- 2,300,000,000
BCT 3
BCT 4
Town Center
BCT 2
BCT 1
CAB
9Land Development Approach
- Acquire services of an experienced land
development engineering firm - Significant part of the program delivery team
- Responsible for all aspects of site development,
site design and site integration of all
utilities and facilities - Provide manpower to assist with the project
management and construction oversight duties - Site and infrastructure construction work will be
accomplished by Infrastructure Multiple Award
Task Order Contracts (MATOCs).
- 5 Year with capacity of 75 Mil
- 45 Tasks Orders valued at 40 Mil
10Brigade Combat Team Facilities
11Urban Design Concept
12- East Biggs - BCT
- Area Development Guide
13Biggs Army Airfield- CAB Area Development Guide
14East Biggs Town Center Area Development Guide
15Land Development Approach
- Acquire services of an experienced land
development engineering firm - Significant player on the program delivery team
- Responsible for all aspects of site development,
site design and site integration of all
utilities and facilities - Provide manpower to assist with the project
management and construction oversight duties - Site and infrastructure construction work
accomplished by Multiple Award Task Order
Contracts (MATOCs).
- 5 Year with capacity of 75 Mil
- 45 Tasks Orders valued at 40 Mil
- Grading, Roadways, Utility Distribution,
Substation, Landscaping
- Master Schedule, Construction Phasing, Document
Control
- 50 full time personnel augmenting field and
District staffs
- 5 large business and 8 Set-aside with capacity
of 600 Mil - Awarded 15 task orders valued at 250 Mil
16Infrastructure Contracts
17InfrastructureFt Worth District
18Walkways, Parking, LandscapingGalveston District
19Product Line Approach
- Facilities are provided through Design-Build
IDIQ Contracts set up for each type of facility
(Product-Lines). - Standards Criteria for each product-line is
provided by USACE Centers of Standardization
(CoS) - Support Districts are assigned to each product
line and provide Cradle to Grave support for
task orders issued against their product-line
contracts. - On-site Resident Offices will administer all
site and product-line task orders execution
20Product-line Contracts
21BarracksFt Worth District
22Company Operation FacilitiesAlbuquerque District
23Tactical Equipment Maint FacTulsa District
24BDE/BN Headquarters BldgSacramento District
25Dining FacilityLittle Rock District
26Deployment StorageSacramento District
27BCT1, BCT2, Training Campus 12 Feb 2007
2nd BCT
1st BCT
Training Campus
28BCT1, BCT2, Training Campus10 May 2007
2nd BCT
1st BCT
Training Campus
29BCT1, BCT2, Training Campus13 August 2007
BCT2
UEPH
BCT1
HQ
COF
TEMF
Training Campus
30East Biggs Aerial PhotoSeptember 2007
31Its a Great Day to Be a Soldier!!