Title: Construction Supervisor: Session 8


1
Construction SupervisorSession 8
2
Costs Associated with Project Completion
  • Labor
  • Materials
  • Equipment
  • Safety
  • Quality

3
Conceptual Estimate
4
Detailed EstimateConstruction Systems
  • Site Work
  • Excavation and Foundations
  • Structure
  • Enclosure
  • Roof
  • Interior Construction
  • Equipment and Furnishings
  • Conveying Systems
  • Mechanical Systems
  • Electrical Systems

5
Construction System Details
  • Excavation
  • Dig the hole
  • Stockpile fill
  • Backfill
  • Foundations
  • Footings
  • Walls
  • Columns

6
Standard Units of Measure
  • Cubic yards (CY)used for concrete and soil
    materials calculated by Length X Width X Depth
    divided by 27.
  • Square feet (SF)used for area calculated by
    Length X Width.
  • Contact area (SFCA)concrete form work
    calculated by Length X Height X 2 sides.
  • Lineal feet (LF)measured length of material
    calculated by measured total length of materials
    needed.
  • Ton (ton)rock, spoil material 2,000 lbs per ton
  • Ton (ton)Reinforcing steel 4 .668 lbs per
    LF5 1.043 lbs per LF, 6 1.502 lbs per LF.

7
Subcontractors Estimates
  • Be sure all work is covered
  • Check to see that there are no exclusions
  • Double-check for duplication
  • Last-minute bids
  • Lowest bid vs. best bid
  • Combined bids

8
Problems with Estimates
  • Inaccurate materials
  • Inaccurate production and labor costs
  • Gaps in subcontracts
  • Non-qualified subcontractors

9
Other Labor Cost Items
  • FICA (Social Security)
  • Unemployment Tax (both federal and state)
  • Workers Compensation Insurance premiums
  • Fringe benefits provided to employees health
    insurance, retirement, paid holidays and
    vacation, others
  • Other insurance, such as general liability
  • Miscellaneous payroll taxes that may be levied by
    the state or local government

10
Labor Cost Variances
  • Environmental Conditions
  • Weather
  • Housekeeping
  • Other?
  • Crew Performance
  • Composition of the crew
  • Crew Compatibility
  • Ineffective supervision
  • Other?

11
Causes of Material Variances
  • Late delivery
  • Supplier delay
  • Defective products

12
Also Include
  • General costs
  • Items specifically mentioned in General
    Conditions document
  • Jobsite overhead
  • Office/storage space
  • Utilities
  • Project personnel
  • Main Office Overhead
  • Offices/storage
  • Utilities
  • Office personnel
  • Profit