Title: ZDC Status, 9th December 07


1
ZDC Status, 9th December 07
  • Fitting in the TAN slot
  • Getting in and out of the TAN
  • Schedule
  • Trigger

Yasar Onel (Michael Murray) for ZDC group
2
Several problems fitting in TAN
  • bumps in the ZDC, biggest bumps flattened
    threaded rods were inserted through the empty
    screw holes in the 2 hadronic modules
  • Poor assembly of TAN improved
  • The slope of the LHC, the bottom of the ZDCs has
    been bevelled
  • Limitations of crane Paul and Ianos have come up
    with a much better design that should be much
    cheaper than option proposed by CERN. (See
    ZDC_crane.ppt for full details)

3
Partial Vertical Extraction
  • Twin Lead screws (not shown) located vertically
    between each end of the
  • Lift frame and outer frame pull ZDC from slot..

4
Full Extraction
5
Partial Rotation
  • Clever Bell assembly is rotated slightly upward
    and out toward transport
  • side of tunnel. Motion is again by a pair of lead
    screws which span
  • between each set of fixed and rotating leaves.

6
Clever Bell mated to Shielding Pig
  • Clever Bell assembly mates on alignment pins to
    pig. Alignment blocks
  • on sideof TAN allow accurate pre-placement of pig.

7
ZDC Fully lowered into Pig
  • Human intervention then to disconnect ZDC
    fromcrane. Pig is removed,
  • pig containing copper bars put in place, affixed
    to crane and procedure
  • reversed. Copper bar module must be built to
    duplicate the manner in
  • which ZDC attaches to lift frame.

8
Schedule
  • Right hand ZDC will most likely be installed
    sometime in weeks 7,8 or 9, left sometime between
    Feb 24 and Apr 9
  • Getting crane approved and built by then is a
    great challenge but everyone on ZDC team will
    work on this
  • KU, Iowa will cover these times but we could do
    with help

9
Trigger
  • ZDC has very simple on, off contributions to
    trigger that will be used for beam tuning,
    diffraction and heavy ion.
  • Need to start programming frim-ware for this. One
    student coming to CERN for 3 months, perhaps he
    could learn how to do this.

10
ZDC gt LHCC
  • We have not yet presented ZDC project to LHCC.
    Skuja approved the the report but we are trying
    to improve its look and feel
  • Oleg and David dEnterrira are working on this