Browns Ferry: Accident - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Browns Ferry: Accident

Description:

The inspector first tried to use a flashlight to stop the fire, then rags stuffed into the hole ... had no paper from 4:30 PM until 2:00 PM the following day ... – PowerPoint PPT presentation

Number of Views:612
Avg rating:3.0/5.0
Slides: 25
Provided by: nelson87
Category:
Tags: accident | browns | ferry

less

Transcript and Presenter's Notes

Title: Browns Ferry: Accident


1
Browns FerryAccident Implications
  • Matthew Denman
  • Nelson Royall

2
Background
  • Located in Athens, AL
  • Owned by Tennessee Valley Authority
  • Three units, two currently operating
  • Unit 1 began operation Aug. 1, 1974
  • Shut down since 1985
  • Plans to begin operation again in 2007

An external view of the Browns Ferry nuclear
power plant began construction in 1967 and
currently operates two of three units.
3
Background
  • All three units are 1065 MWe General Electric
    BWRs

4
(No Transcript)
5
Accident Sequence
  • March 22nd, 1975 at 12PM Units 1 2 operating at
    full power
  • An electrical inspector and an electrician were
    sealing air leaks in cable spreading room using
    2 thick, resilient polyurethane foam
  • Used a candle to determine if there was a leak, a
    change in the flame indicated a leak
  • A 2 x 4 hole in a penetration window carrying
    four wires significantly sucked in the flame
  • The electrical engineer filled the hole with two
    strips of the foam and rechecked the hole for a
    leak

Resilient polyurethane foam such as this was used
to fill holes in the Browns Ferry power plant,
it is highly flammable.
6
Accident Sequence
  • The electrical inspector put the candle too close
    to the hole and the flame was sucked into the
    hole igniting the foam
  • The inspector first tried to use a flashlight to
    stop the fire, then rags stuffed into the hole
  • Finally, the inspector used a CO2 extinguisher
    which blew the fire behind the hole to the other
    side and ignited the reactor building side of the
    hole
  • A blowtorch effect from the fire began following
    the second application of the extinguisher due to
    the airflow through the hole

The CO2 fire extinguisher used by the electrical
inspector trying to put out the flame ignited the
other side of the hole leading to a more serious
situation.
7
Accident Response
  • At 1215 PM the electrical inspector informed a
    guard in the turbine room of the fire
  • The code to sound the alarm via telephone was not
    called immediately, instead the guard alerted the
    shift engineer who then called the reactor
    operator to sound the alarm
  • Had the shift engineer been in a construction
    department he would not have been able to sound
    the alarm
  • Only plant phones can dial plant numbers and only
    construction phones can dial construction
    numbers, therefore preventing construction
    personnel from sounding a fire alarm
  • This violated BFNP Standard Practice BFS3, which
    stated that all personnel must be able to sound
    an alarm in case of fire

8
Operator Response
  • At 1240 PM, five minutes after the alarm began,
    the operators continued to run the Unit 1 reactor
  • All the ECCS pumps and many other pumps were on
    while alarms were also sounding
  • Indicating lights were turning bright, dimming
    and turning off in the control room
  • Also, smoke was emitted from beneath the 9-3
    control board
  • After ten minutes of these events, the power
    began to drop in the reactor prompting the
    operator to decrease the pump flow
  • At 1251 PM, the pumps failed causing the
    operator to insert the control rods to shut down
    the reactor

9
Accident Complications
  • At 1255 PM, power to control, reactor shutdown
    equipment and the ECCS was lost in Unit 1
  • At 115 PM, the operator lost all nuclear
    instrumentation and other equipment except for
    four pressure relief valves
  • At 130 PM, the operator opened the relief valves
    to drop the pressure so that low-pressure pumps
    would increase water flow to the core
  • However, all low-pressure pumps had failed so a
    condensate booster pump was used to increase
    water flow
  • The water level dropped from 200 inches to only
    45 inches, but allowed the operator to regain
    control temporarily

10
Unit 2 Effects
  • At 100 PM, Unit 2 began undergoing the same
    problems that had occurred in Unit 1 prior to
    shutdown, prompting the operator to begin Unit 2
    shutdown
  • At 120 PM, Unit 2 lost control to the reactor
    relief valves and at 145 PM the high-pressure
    ECCS system and other shutdown equipment failed
  • Finally, at 215 PM, Unit 2 regained control of
    the reactor relief valves and depressurized the
    reactor to initiate the low-pressure pumps
  • The A and C subsystems of the low-pressure ECCS
    and the spray systems had failed earlier, leaving
    only the B subsystem which failed sporadically
    from 135 PM 435 PM
  • Using the same technique as the Unit 1 operator,
    the condensate booster pump was used to increase
    core flow

11
Extinguishing the Fire
  • After the electrician and the electrical
    inspector left the cable spreader room, the shift
    engineer turned on the Cardox system (Fills the
    room with CO2)
  • Because the control room was directly above, the
    Cardox system pushed the smoke into the control
    room through small gaps
  • The Cardox system had only slowed the spread of
    the fire
  • Many of the breathing masks were not functioning
    and others were partially functional, preventing
    firefighting efforts
  • BFNP personnel managed firefighting efforts with
    the assistance of the local fire department for 6
    hours
  • The fire chiefs recommendation to use water at
    130 PM was finally attempted at 600 PM and
    ended the fire within 20 minutes

12
Post-Fire Concerns
  • Aircraft warning lights on the 600 ft. cooling
    tower failed at nightfall, no call to the FAA was
    made
  • Time and sequence recording devices for the
    control circuits had no paper from 430 PM until
    200 PM the following day
  • Phone conversations were recorded as of 340 PM,
    however the phone recorders malfunctioned leaving
    partial records of the calls
  • After 600 PM the workers returned to the control
    room and control was lost to the final four
    relief valves in Unit 1
  • The pressure increase prevented the condensate
    booster pump to flow water to the core
  • Unaware that the Unit 2 control rod drive pump
    could be diverted, the operators tried to bring
    back the relief valves since the Unit 1 spare
    control rod drive pump had failed
  • At 900 PM control of the relief valves was
    regained and core melt due to boiloff was
    prevented

13
Radiation Response
  • No radiation leaks occurred according to the NRC
    and TVA
  • Unit 1 lost all radiation monitors almost
    immediately
  • Unit 2 lost radiation monitors from 200 PM until
    900 PM
  • Air sampling occurred at 445 PM at
  • Athens, AL (10 mi NE of BFNP)
  • Hillsboro, AL (10 mi SW of BFNP)
  • Rogersville, AL (35 mi NW of BFNP)
  • Wind direction was from NW to SE at time of
    accident
  • Air sampling from Decatur, AL (20 mi SE of BFNP)
    did not begin until 900 PM

14
Regulations and Reports
  • NUREG-0050
  • BTP APCSB 9.5-1
  • 10 CFR 50.48 and Appendix R
  • NUREG/CR 2258
  • IAEA Safety Guidelines No. 98

The Browns Ferry accident on March 22, 1975
prompted the NRC to enact strong fire safety
regulations previously almost entirely ignored.
15
NUREG-0050
  • Recommendations Related to Browns Ferry Fire
    (Feb. 1976)
  • Seal that caught on fire was not the seal
    designed and tested in the plant design
  • Flexible polyurethane foam was used instead of
    spray polyurethane foam, increasing the risk of
    fire
  • Seal did not have the fire retardant coating that
    was specified in the plant design

16
BTP APCSB 9.5-1
  • NRC issued in May 1976
  • Applied only to licensees filing for construction
    permits after July 1, 1976
  • Incorporated recommendations from Browns Ferry
    fire special review team and NUREG-0500
  • Added Defense in Depth methodology to current
    fire safety procedures.
  • Divided plants into multiple distinct and
    independent fire containment areas
  • Equipment redundancy must be demonstrated between
    each fire area to maintain shutdown margin and
    ensure safety
  • Vital equipment must be adequately protected from
    fire

17
10 CFR 50.48 Fire Protection
  • Applies to all nuclear plants licensed after
    January 1, 1979
  • Requires
  • Automatic and manually operated fire detection
    and suppression systems in fire-sensitive areas
  • Limit fire damage to structures, systems and
    components important to shutdown margin and
    safety
  • All cables covered in flame retardant coverings

18
10 CFR 50 Appendix R
  • Fire protection for nuclear facilities operating
    before January 1, 1979
  • Hot Shutdown Criteria
  • One train of equipment necessary to achieve hot
    shutdown from either the control room or
    emergency control station(s) must be maintained
    free of fire damage by a single fire, including
    an exposure fire.

10 CFR 50 Appendix R requires that a single fire
not prevent the shutdown of the reactor from
either the control room or emergency control
stations as a result of the near meltdown at
Browns Ferry.
19
10 CFR 50 Appendix R (Cont.)
  • Each nuclear power plant must establish a fire
    protection program to create and implement a fire
    protection policy
  • Must conduct Fire Hazards Analysis (FHA)
  • Considers both in situ and transient fire hazards
  • Transient fire analysis must be conducted for
  • Normal operation
  • Maintenance
  • Repair
  • Modification
  • Requires compliance with BTP APCSB 9.5-1

20
NUREG/CR 2258
  • Provides conditional probabilities, used in most
    PRAs, for hot shorts caused by fire damage
  • Empirical data taken from Browns Ferry fire was
    used to determine the probability and duration of
    a hot short during a fire
  • Hot shorts are conductor to conductor shorts that
    induce spurious actuation
  • Browns Ferry is one of the only majors fires
    whose report focused on the details of cable
    failures and resulting circuit faults

21
IAEA Safety Guidelines No. 98
  • On-Site Habitability in the Event of an Accident
    at a Nuclear Facility
  • Recommendations from Browns Ferry Fire
  • Open penetrations between cable spreading room
    and control room should be avoided and if found
    should not be filled with flammable foam
  • Firefighting equipment (CO2, Halides) should be
    considered a potential hazard for personal

The IAEA recommended changes be made in safety
and risk analysis including considering
firefighting equipment failures.
22
Defense in Depth
  • Objectives
  • Prevent fires from starting
  • Promptly detect control and extinguish fires that
    occur
  • Protect structures, systems, and components
    important to safety so that a fire that is not
    promptly extinguished will not prevent the safe
    shutdown of the plant

23
Seal Inspections
  • BFNP Units 2 and 3 underwent 100 penetration
    seal inspection in 1975 and 1977 respectively
    following the accident
  • Penetration seals are one element of fire
    protection defense in depth
  • Confines the fire to the area of origin
  • Protects plant systems and components within an
    area from fire outside the area
  • NRC does not consider penetration seal
    deficiencies to be a lack of adequate fire
    protection

24
Fire Protection Programs
  • Consider Potential Fire Hazards (PFH)
  • Determine the effects of fires in the plant on
    the ability to safely shutdown the reactor or on
    the ability to minimize and control the release
    of radioactivity to the environment
  • Specified measures for
  • Fire prevention
  • Fire detection
  • Fire containment
  • Automatic and manual fire suppression
  • Post-fire safe-shutdown capability
Write a Comment
User Comments (0)
About PowerShow.com