Title: Browns Ferry: Accident
1Browns FerryAccident Implications
- Matthew Denman
- Nelson Royall
2Background
- Located in Athens, AL
- Owned by Tennessee Valley Authority
- Three units, two currently operating
- Unit 1 began operation Aug. 1, 1974
- Shut down since 1985
- Plans to begin operation again in 2007
An external view of the Browns Ferry nuclear
power plant began construction in 1967 and
currently operates two of three units.
3Background
- All three units are 1065 MWe General Electric
BWRs
4(No Transcript)
5Accident Sequence
- March 22nd, 1975 at 12PM Units 1 2 operating at
full power - An electrical inspector and an electrician were
sealing air leaks in cable spreading room using
2 thick, resilient polyurethane foam - Used a candle to determine if there was a leak, a
change in the flame indicated a leak - A 2 x 4 hole in a penetration window carrying
four wires significantly sucked in the flame - The electrical engineer filled the hole with two
strips of the foam and rechecked the hole for a
leak
Resilient polyurethane foam such as this was used
to fill holes in the Browns Ferry power plant,
it is highly flammable.
6Accident Sequence
- The electrical inspector put the candle too close
to the hole and the flame was sucked into the
hole igniting the foam - The inspector first tried to use a flashlight to
stop the fire, then rags stuffed into the hole - Finally, the inspector used a CO2 extinguisher
which blew the fire behind the hole to the other
side and ignited the reactor building side of the
hole - A blowtorch effect from the fire began following
the second application of the extinguisher due to
the airflow through the hole
The CO2 fire extinguisher used by the electrical
inspector trying to put out the flame ignited the
other side of the hole leading to a more serious
situation.
7Accident Response
- At 1215 PM the electrical inspector informed a
guard in the turbine room of the fire - The code to sound the alarm via telephone was not
called immediately, instead the guard alerted the
shift engineer who then called the reactor
operator to sound the alarm - Had the shift engineer been in a construction
department he would not have been able to sound
the alarm - Only plant phones can dial plant numbers and only
construction phones can dial construction
numbers, therefore preventing construction
personnel from sounding a fire alarm - This violated BFNP Standard Practice BFS3, which
stated that all personnel must be able to sound
an alarm in case of fire
8Operator Response
- At 1240 PM, five minutes after the alarm began,
the operators continued to run the Unit 1 reactor - All the ECCS pumps and many other pumps were on
while alarms were also sounding - Indicating lights were turning bright, dimming
and turning off in the control room - Also, smoke was emitted from beneath the 9-3
control board - After ten minutes of these events, the power
began to drop in the reactor prompting the
operator to decrease the pump flow - At 1251 PM, the pumps failed causing the
operator to insert the control rods to shut down
the reactor
9Accident Complications
- At 1255 PM, power to control, reactor shutdown
equipment and the ECCS was lost in Unit 1 - At 115 PM, the operator lost all nuclear
instrumentation and other equipment except for
four pressure relief valves - At 130 PM, the operator opened the relief valves
to drop the pressure so that low-pressure pumps
would increase water flow to the core - However, all low-pressure pumps had failed so a
condensate booster pump was used to increase
water flow - The water level dropped from 200 inches to only
45 inches, but allowed the operator to regain
control temporarily
10Unit 2 Effects
- At 100 PM, Unit 2 began undergoing the same
problems that had occurred in Unit 1 prior to
shutdown, prompting the operator to begin Unit 2
shutdown - At 120 PM, Unit 2 lost control to the reactor
relief valves and at 145 PM the high-pressure
ECCS system and other shutdown equipment failed - Finally, at 215 PM, Unit 2 regained control of
the reactor relief valves and depressurized the
reactor to initiate the low-pressure pumps - The A and C subsystems of the low-pressure ECCS
and the spray systems had failed earlier, leaving
only the B subsystem which failed sporadically
from 135 PM 435 PM - Using the same technique as the Unit 1 operator,
the condensate booster pump was used to increase
core flow
11Extinguishing the Fire
- After the electrician and the electrical
inspector left the cable spreader room, the shift
engineer turned on the Cardox system (Fills the
room with CO2) - Because the control room was directly above, the
Cardox system pushed the smoke into the control
room through small gaps - The Cardox system had only slowed the spread of
the fire - Many of the breathing masks were not functioning
and others were partially functional, preventing
firefighting efforts - BFNP personnel managed firefighting efforts with
the assistance of the local fire department for 6
hours - The fire chiefs recommendation to use water at
130 PM was finally attempted at 600 PM and
ended the fire within 20 minutes
12Post-Fire Concerns
- Aircraft warning lights on the 600 ft. cooling
tower failed at nightfall, no call to the FAA was
made - Time and sequence recording devices for the
control circuits had no paper from 430 PM until
200 PM the following day - Phone conversations were recorded as of 340 PM,
however the phone recorders malfunctioned leaving
partial records of the calls
- After 600 PM the workers returned to the control
room and control was lost to the final four
relief valves in Unit 1 - The pressure increase prevented the condensate
booster pump to flow water to the core - Unaware that the Unit 2 control rod drive pump
could be diverted, the operators tried to bring
back the relief valves since the Unit 1 spare
control rod drive pump had failed - At 900 PM control of the relief valves was
regained and core melt due to boiloff was
prevented
13Radiation Response
- No radiation leaks occurred according to the NRC
and TVA - Unit 1 lost all radiation monitors almost
immediately - Unit 2 lost radiation monitors from 200 PM until
900 PM - Air sampling occurred at 445 PM at
- Athens, AL (10 mi NE of BFNP)
- Hillsboro, AL (10 mi SW of BFNP)
- Rogersville, AL (35 mi NW of BFNP)
- Wind direction was from NW to SE at time of
accident - Air sampling from Decatur, AL (20 mi SE of BFNP)
did not begin until 900 PM
14Regulations and Reports
- NUREG-0050
- BTP APCSB 9.5-1
- 10 CFR 50.48 and Appendix R
- NUREG/CR 2258
- IAEA Safety Guidelines No. 98
The Browns Ferry accident on March 22, 1975
prompted the NRC to enact strong fire safety
regulations previously almost entirely ignored.
15NUREG-0050
- Recommendations Related to Browns Ferry Fire
(Feb. 1976) - Seal that caught on fire was not the seal
designed and tested in the plant design - Flexible polyurethane foam was used instead of
spray polyurethane foam, increasing the risk of
fire - Seal did not have the fire retardant coating that
was specified in the plant design
16BTP APCSB 9.5-1
- NRC issued in May 1976
- Applied only to licensees filing for construction
permits after July 1, 1976 - Incorporated recommendations from Browns Ferry
fire special review team and NUREG-0500 - Added Defense in Depth methodology to current
fire safety procedures. - Divided plants into multiple distinct and
independent fire containment areas - Equipment redundancy must be demonstrated between
each fire area to maintain shutdown margin and
ensure safety - Vital equipment must be adequately protected from
fire
1710 CFR 50.48 Fire Protection
- Applies to all nuclear plants licensed after
January 1, 1979 - Requires
- Automatic and manually operated fire detection
and suppression systems in fire-sensitive areas - Limit fire damage to structures, systems and
components important to shutdown margin and
safety - All cables covered in flame retardant coverings
1810 CFR 50 Appendix R
- Fire protection for nuclear facilities operating
before January 1, 1979 - Hot Shutdown Criteria
- One train of equipment necessary to achieve hot
shutdown from either the control room or
emergency control station(s) must be maintained
free of fire damage by a single fire, including
an exposure fire.
10 CFR 50 Appendix R requires that a single fire
not prevent the shutdown of the reactor from
either the control room or emergency control
stations as a result of the near meltdown at
Browns Ferry.
1910 CFR 50 Appendix R (Cont.)
- Each nuclear power plant must establish a fire
protection program to create and implement a fire
protection policy - Must conduct Fire Hazards Analysis (FHA)
- Considers both in situ and transient fire hazards
- Transient fire analysis must be conducted for
- Normal operation
- Maintenance
- Repair
- Modification
- Requires compliance with BTP APCSB 9.5-1
20NUREG/CR 2258
- Provides conditional probabilities, used in most
PRAs, for hot shorts caused by fire damage - Empirical data taken from Browns Ferry fire was
used to determine the probability and duration of
a hot short during a fire - Hot shorts are conductor to conductor shorts that
induce spurious actuation - Browns Ferry is one of the only majors fires
whose report focused on the details of cable
failures and resulting circuit faults
21IAEA Safety Guidelines No. 98
- On-Site Habitability in the Event of an Accident
at a Nuclear Facility - Recommendations from Browns Ferry Fire
- Open penetrations between cable spreading room
and control room should be avoided and if found
should not be filled with flammable foam - Firefighting equipment (CO2, Halides) should be
considered a potential hazard for personal
The IAEA recommended changes be made in safety
and risk analysis including considering
firefighting equipment failures.
22Defense in Depth
- Objectives
- Prevent fires from starting
- Promptly detect control and extinguish fires that
occur - Protect structures, systems, and components
important to safety so that a fire that is not
promptly extinguished will not prevent the safe
shutdown of the plant
23Seal Inspections
- BFNP Units 2 and 3 underwent 100 penetration
seal inspection in 1975 and 1977 respectively
following the accident - Penetration seals are one element of fire
protection defense in depth - Confines the fire to the area of origin
- Protects plant systems and components within an
area from fire outside the area - NRC does not consider penetration seal
deficiencies to be a lack of adequate fire
protection
24Fire Protection Programs
- Consider Potential Fire Hazards (PFH)
- Determine the effects of fires in the plant on
the ability to safely shutdown the reactor or on
the ability to minimize and control the release
of radioactivity to the environment - Specified measures for
- Fire prevention
- Fire detection
- Fire containment
- Automatic and manual fire suppression
- Post-fire safe-shutdown capability