Title: 20082009 FINANCE AND PERFORMANCE REPORT Month 1
12008/2009FINANCE AND PERFORMANCE REPORT
Month 1
Jonathan Wise, Director of Finance Performance
2Contents
- Part 1 Finance report (slides 2-13)
- Part 2 Performance report (slides 14 26)
- Part 3 PBC and Acute commissioning report
- ( slide 27)
- Finance Appendices (slides 28 - 35)
- Summary Operating Cost Statement and variances by
budget heading - 2. Balance sheet
- 3. Cash flow
3PART 1 FINANCE REPORTFinancial position -
Summary
- Statutory duties
- Forecast underspend against revenue resource
limit - Achievement of capital resource limit
- Forecast underspend against cash limit
- Achievement of Operating plan surplus
- Improvement in ALE assessment
- Budget holder responsibilities / training
4Overview of budget position
- Total budgets agreed by Board at March meeting
- 000
- Issued budgets 418,054
- Contingency 4,200
- Investment programme 9,500
-
- TOTAL 431,754
-
- Surplus for investment 12,446
-
-
- TOTAL 444,200
- All issued budgets have been signed off by
budget holders - All budget changes (virements, access to
contingency and new investment programme) being
tracked for agreement at appropriate level
5Approval of budget changes
- In year contingency all to be agreed by CE,
as agreed at March Board meeting - New investment programme all to be agreed
Board, on advice of Investment - group (Chaired by CE) as agreed at March Board
meeting. The following - investments are put forward for Board
approval - 000
- PBC Executive group - 100 (non-recurrent)
- (payments to attendees)
- Primary care strategy - (Project Mgr)
65 (non-recurrent) - Health visitors x 4 WTE 92 (recurrent, full
year 157k) - Health visitors (agency cover
- for sick leave) 54 (non-recurrent)
- - Project Management 216 (non-recurrent)
6The investment process has 2 phases
- Project selection (portfolio formulation)
- Ensure strategic fit
- Establish priorities
- Project delivery (programme execution)
- Detailed planning(ensure project offers good
value for money and is deliverable) - Deliver plans
- Review
7Portfolio Formulation
Programme Execution
Decision
1 Agree to invest
0 Commission analysis
3 Project complete
4 Benefits evaluation
2 Go live
1 Start-up
2 Delivery
3 Closure
4 Review
Stage
Project Brief
Business case project plan
Go/no go report
End project lessons learnt report
Post-implemen-tation review
Document
8Successful schemes at Stage 0
- Have clear outcomes, that make a major
contribution to our strategic objectives - Give the Panel confidence that the scheme is
realistic - Cost
- Benefit
- Risks
- Next steps
9Successful schemes at Stage 1
- Have the best value for money (cost v benefits)
- Give the Panel confidence that the scheme is
deliverable - Stakeholders
- Delivery plans
- Resources
- Risks
10Successful schemes at Stage 2
- Monitor progress to ensure the business case is
still strong - Costs
- Benefits
- Risks
- Stakeholders and interfaces
- Milestones
- Re-plan as circumstances change
11Overview of month 1 position
- Aggregate surplus of 1041k largely reflecting
planned surplus for investment in 09/10 - Variances on issued budgets net to overall
balance - Commissioning April activity data not yet
available so position largely reflects
contractual agreements - Primary Care the YTD underspend of 40k is
likely to increase with slippage on GMS enhanced
services and additional Dental allocation - Provider services risks in respect of income
reflected in YTD overspend of 34k - HQ net overspend of 31k being investigated
further - General a significant element of the Phase 1
investment programme is profiled later in the
year and potential slippage (underspend) is
currently being assessed
12Achievement of Operating Plan surplus
- A full assessment of the overall plan is underway
and will be presented (with proposed actions) to
the July Board, building on the risk assessment
presented to the March Board
Risk Assessment of Overall Financial Position
2008/9
13Other Corporate objectives
- ALE assessment
- Action plan to deliver the Corporate objective of
achieving adequate or better across all
dimensions being considered by EMT / Audit
Committee - Update on high risk areas will be considered at
June EMT/Audit Committee - Budget holder responsibilities / training
- Budget sign-off letter plus Finance guide clearly
set out responsibilities - Provider arm training commenced 12/5 (14
attended) - Further Provider arm plus Commissioner training
planned for June
14Part 2 2008-09 Performance Report
- 4 main target areas as set out in the 2008-09
Operating Plan - National Requirements (NR) refers to national
commitments where the requirements are very
specific at a national level and must be cascaded
to PCT level. - National Priorities (NP) - refers to national
commitments, but where trajectories are set by
the PCT. - London Priorities (Lon P) as per national
commitments but for the London SHA area. - Local Priorities (LP)- Priorities and any
corresponding targets agreed locally. - Existing Commitments (EC)- PCT required to
continue to achieve targets from prior
commitments. - Indicators marked with an asterix () under
internal monitoring frequency column will be
subject to local monitoring on a more frequent
basis than that proposed by the SHA and DoH. This
will ensure appropriate monitoring of high risk
target areas where investment has been focused
for 2008-09. Discussions will take place with
individual Directors to agree in year reporting
and timetables for these indicators.
152008-09 Performance Report(2)
- Actuals against Plan will be available within 6
weeks of the current reporting month and reported
to the following EMT and Board meetings. - Performance against targets will be measured
using the Red, Amber and Green (RAG) rating as in
previous years and in accordance with the SHA
thresholds for each target. - The targets have been grouped by Directorate and
the monitoring frequency as shown on the
following pages.
16Clinical Leadership and Integrated Governance
17Organisational Development Human Resources
18Primary and Community Commissioning Services
19Primary and Community Commissioning Services (2)
20Provider Development and Estates
21Public Health
22Public Health (2)
23Strategic Commissioning
24Strategic Commissioning (2)
25Strategic Commissioning (3)
26Strategic Commissioning (4)
27Part 3 PBC and Acute Commissioning Report
- PBC budgets (PbR services) were issued on 24
April at the PBC launch event - Practices are due to confirm acceptance of the
budget and the Governance and Accountabilities
arrangements on 27 May - The PCT is now working on
- PBC reporting arrangements
- In-year acute contract data validation / contract
management arrangements - Month 1 reports are expected to be available to
Practices in June
28(No Transcript)
29(No Transcript)
30(No Transcript)
31(No Transcript)
32(No Transcript)
33(No Transcript)
34(No Transcript)
35Appendix 3 Cash Flow Report to 30/04/08
Cash drawings in April were consistent with plan.
Receipts including Sure Start were higher than
expected and contributed to the cash balance at
month end.