Let yesterday be a source of fond memories, - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

Let yesterday be a source of fond memories,

Description:

... files, crowbars, wrenches, screwdrivers, rags, drills, and hoists should be ... Backfill all low spots as soon as possible, especially on rainy days. ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 49
Provided by: toroagromi
Category:

less

Transcript and Presenter's Notes

Title: Let yesterday be a source of fond memories,


1
  • Let yesterday be a source of fond memories,
  • Let tomorrow be a time of new beginnings,
  • Let today be filled with everything that makes
    you happy.

2
Chapter IX INSTALLATION
  • Michael J. Boswell
  • lttoroagro.comgt

3
Chapter 9 InstallationINTRODUCTION
  • These guidelines clarify commonly accepted
    procedures for construction, installation, and
    testing of micro-irrigation systems.
  • These guidelines synchronize the various steps
    which are required for a proper and smoother
    installation, and result in fewer problems.

4
Chapter 9 Installation GENERAL INSTALLATION
  • System Planning
  • Accurate topographic maps of the area are
    obtained.
  • Water source and other pertinent features of the
    area, such as a power source, utility cables or
    pipelines, rock piles or rock outcroppings,
    roads, etc. are indicated on the topographic
    maps.

5
Chapter 9 Installation GENERAL INSTALLATION
  • System planning
  • Irrigation system is designed and drawings are
    prepared.
  • Materials take-off list is prepared from the
    design.

6
Chapter 9 Installation GENERAL INSTALLATION
  • System planning
  • List of materials is adjusted for wastage and
    breakage
  • Sheet for specification of materials is prepared.

7
Chapter 9 Installation GENERAL INSTALLATION
  • System planning
  • List of materials and specifications are
    distributed to hardware stores to request
    quotations on price and delivery dates.
  • Materials are ordered from suppliers.

8
Chapter 9 Installation TOOLS AND EQUIPMENT
  • A good stock of shovels, hand saws, hacksaws,
    files, crowbars, wrenches, screwdrivers, rags,
    drills, and hoists should be kept in a tool
    truck.
  • A pipe trailer, 22 feet long.

9
Chapter 9 Installation TOOLS AND EQUIPMENT
  • A vehicle to carry parts valves, fittings, glue,
    etc.
  • A dozer for backfilling trenches.

10
Chapter 9 Installation TOOLS AND EQUIPMENT
  • A forklift or boom truck for lifting heavy items,
    including filters, large valves, pumps, tanks,
    etc.
  • A wire spooler to string control wire or tubing.

11
Chapter 9 Installation TOOLS AND EQUIPMENT
  • Tractors as required by field installation
    operations.
  • A small portable sump pump to remove water from
    flooded areas for making repairs.

12
Chapter 9 Installation RECEIVING AND HANDLING
OF MATERIALS
  • Prepare the warehouse for materials, including a
    protected area for drip irrigation lines (reels),
    glue, etc .
  • Delivery of materials should be carefully checked
    against purchase orders.
  • Pipes should be delivered to a specified location
    near the job site on a planned delivery schedule.

13
Chapter 9 InstallationASSEMBLY OF FITTINGS AND
PARTS
  • Designate a location for the assembly of fittings
    and accessories.
  • Set up assembly equipment tables, jigs, tools,
    bins for ditches (trenches), parts, glue, Teflon
    tape, saws, wrenches, etc.

14
Chapter 9 InstallationSURVEYING, STAKING AND
MAKING DITCHES
  • The surveyor stakes out mainline and sub main
    routes, field boundaries, locations of
    underground utility cables or pipelines, roads,
    etc.
  • Trenches are dug along the routes where the mains
    and sub mains will be laid.

15
Chapter 9 InstallationASSEMBLY OF PIPELINES
  • Lower the principal and secondary pipe lines
    carefully to the trenches.
  • Make sure the correct glue is being used with PVC
    pipe. There are different types of glue available
    for different sizes of pipe. Make sure primer is
    used correctly.

16
Chapter 9 InstallationASSEMBLY OF PIPELINES
  • Procedure
  • Clean the pipes with a sanitary napkin and
    acetone.
  • Put glue at both ends of the pipe.
  • Join the parts immediately after applying the
    glue.
  • Use a rubber hammer to knock and force the
    entrance of one tube inside the other.

17
Chapter 9 Installation ASSEMBLY OF PIPELINES
  • In areas of high humidity, care should be taken
    to prevent PVC solvent cement from absorbing
    moisture.
  • Ppipes should be laid in the trench and covered.
  • PVC pipe should be cut properly, with a square
    clean-cut end.

18
Chapter 9 Installation ASSEMBLY OF PIPELINES
  • Smaller sizes of pipe may be snaked in the
    trench larger sizes should be laid in the trench
    and covered when cool.
  • Assembly the elbows, tees, raisers flushing
    valves, and check valves.
  • The major parts are assembled outside the
    trenches.

19
Chapter 9 InstallationINSTALLATION OF CONTROL
WIRE OR TUBING IN TRENCHES AND HYDRAULIC TUBES
  • Wire should be laid in the trench loosely.
  • Sufficient slack should be allowed at each sub
    main riser for making connections to field
    control valves, and also to allow for contraction
    .
  • Keep wire or tubing away from sharp edges of pipe
    line fittings and rocks.

20
Chapter 9 InstallationINSTALLATION OF CONTROL
WIRE OR TUBING IN TRENCHES AND HYDRAULIC TUBES
  • Wire or tubing should be tested before burial.
  • In hot weather, pipe should be laid into the
    trenches and covered with the soil in the early
    morning or late evening. If this is done when the
    pipe is hot, the buried pipe will tend to
    contract after buried.

21
Chapter 9 InstallationINSTALLATION OF FITTINGS,
VALVES, RISERS
  • All the remaining pipeline work should be
    completed at this time. Install all the
    fittings, valves and riser assemblies.
  • Connect the wire or control tubing to the control
    valves in the field.

22
Chapter 9 InstallationINSTALLATION OF FITTINGS,
VALVES, RISERS
  • Paint all the exposed PVC pipe and the fittings
    with a compatible PVC paint, to protect against
    sunlight and prevent algae growth.

23
Chapter 9 InstallationPARTIAL BACKFILLING
  • Partially backfilling should be done immediately
    after pipelines are laid in the trench.
  • Backfill all low spots as soon as possible,
    especially on rainy days.

24
Chapter 9 InstallationPARTIAL BACKFILLING
  • When backfilling, sub mains with flexible hose
    risers, hose kinking may be prevented by first
    slipping a short length of 1 PVC pipe over the
    hose riser.

25
Chapter 9 InstallationPARTIAL BACKFILLING
  • After backfilling, these short pipe lengths may
    then be removed and used again at the next sub
    main.

26
Chapter 9 InstallationINSTALLATION OF THRUST
BLOCKS
  • Construct support walls after filling partially
    the channels.
  • Install reinforcement steel and mounting brackets
    where required.

27
Chapter 9 InstallationINSTALLATION OF THRUST
BLOCKS
  • Pour concrete for thrust blocks.
  • Allow several days for concrete to cure properly.

28
Chapter 9 InstallationINSTALLATION OF LATERAL
LINES IN FIELD AND FLUSHING, PRESSURIZING AND
TESTING
  • Lateral lines are installed in the field, but not
    yet connected to sub mains.
  • Ends of lateral lines should be kept close to
    ensure that the lateral lines are not
    contaminated with soil, insects, etc.
  • Close all sub main control valves.

29
Chapter 9 InstallationINSTALLATION OF LATERAL
LINES IN FIELD AND FLUSHING, PRESSURIZING AND
TESTING
  • Fill mainlines with water open flushing valves to
    flush foreign materials out of mainlines.
  • The flush out valves should be closed, and the
    mainline pressure brought up to test pressure.

30
Chapter 9 InstallationINSTALLATION OF LATERAL
LINES IN FIELD AND FLUSHING, PRESSURIZING AND
TESTING
  • Maintain test pressure for 24 hours. If leaks
    develop in the mainline, immediately shut off the
    system. Repair leaks, flush the mainline, and
    repeat test.

31
Chapter 9 InstallationCONNECTING LATERAL LINES
TO SUBMAINS
  • With ends lateral of line open, connect lateral
    lines to sub mains.
  • The connection is more easily made if water is
    running in the sub mains.
  • Flush lateral lines thoroughly.

32
Chapter 9 InstallationCONNECTING LATERAL LINES
TO SUBMAINS
  • Close ends of lateral line.
  • Adjust all sub main pressures as required.
  • Check for leaks, mark them, shut system off. Fix
    any leaks in sub main and lateral lines.

33
Chapter 9 InstallationTESTING SYSTEM OPERATION
AND BACKFILLING TRENCHES
  • Check operation of controllers, sub main and
    control valves, filters and filter controllers,
    etc.
  • When it has been determined that all underground
    components, including pipes, fittings, control
    wires and tubing, are working properly, backfill
    all trenches.

34
Chapter 9 InstallationTESTING SYSTEM OPERATION
AND BACKFILLING TRENCHES
  • 3. Care must be taken during backfilling,
    particularly with large, thin-wall pipe, to
    prevent collapse or other damage to the pipe.
  • Once the system is running properly, take
    pressure and flow readings at strategic points in
    the system, i.e., before and after pumps,
    filters, main control valves.

35
Chapter 9 InstallationABOVE GROUND ASSEMBLY
  • Install the laterals with the orifices facing
    upwards.
  • An air/vacuum relief valve should always be
    installed at the sub main riser to prevent
    suction from occurring in the Bi-Wall tubes when
    the system is shut down.

36
Chapter 9 InstallationABOVE GROUND ASSEMBLY
  • Suction in buried Bi-Wall tubing will tend to
    draw muddy water back into the tubing through the
    orifices, causing contamination.
  • Close the ends of lateral lines.

37
Chapter 9 InstallationBELOW GROUND ASSEMBLY
  • Bi-Wall tubing may be laid on the surface or
    buried up to 18 inches deep.
  • Injection equipment used to install Bi-Wall
    tubing should be free of sharp edges, burrs, and
    areas where the tubing could be damaged.

38
Chapter 9 InstallationBELOW GROUND ASSEMBLY
  • Bends, rollers, and other points of contact with
    the tubing should be kept to a minimum to reduce
    the possibilities for damage and the tension on
    the tubing as it is injected.
  • It is strongly recommended that the Bi-Wall
    tubing be monitored as it is buried in the soil.

39
Chapter 9 InstallationBELOW GROUND ASSEMBLY
  • Someone should be watching to ensure that the
    tubing maintains its orifices inward orientation,
    to assist in case the tubing becomes tangled in
    the injector, and to signal the tractor driver
    when the Bi-Wall real is empty and must be
    replaced.

40
Chapter 9 Installation INSTALLATION EQUIPMENTS
lthttp//projects.andassoc.com/t
omscreek/alternative/images/drip/photo2.jpggt
41
Chapter 9 Installation INSTALLATION EQUIPMENTS
lthttp//www.accesskansas.org/kscc/images/SDIInstal
lation.jpggt
42
Chapter 9 Installation INSTALLATION EQUIPMENTS
lthttp//www.cati.csufresno.edu/cit/rese/95/950104/
img00002.jpggt
43
Chapter 9 Installation INSTALLATION EQUIPMENTS
lthttp//www.cati.csufresno.edu/cit/rese.95/950104/
img00003.jpggt
44
Chapter 9 Installation FIELD MANIFOLD
ltwww.irrigationtutorials.comgt
45
Chapter 9 Installation COMPONENT OF A DRIP
IRRIGATION SYSTEM
ltwww.fao.orggt
46
Chapter 9 Installation COMPONENT OF A TYPICAL
DRIP IRRIGATION SYSTEM
ltwww.automatedbuildings.comgt
47
Chapter 9 Installation COMPONENT OF A TYPICAL
DRIP IRRIGATION SYSTEM
ltwww.oznet.ksu.edugt
48
  • It is only with the heart that one can see
    rightly,
  • What is essential is invisible to the eye.
  • Antoine De Saint Exupery
  • The Little Prince
Write a Comment
User Comments (0)
About PowerShow.com