Title: LONGTERM RESOURCE ADEQUACY: DEMANDRESPONSE OPTIONS
1LONG-TERM RESOURCE ADEQUACYDEMAND-RESPONSE
OPTIONS
- ERIC HIRST
- Consultant in Electric-Industry Restructuring
- Oak Ridge, TN
- Eric_at_EHirst.com www.EHirst.com
- November 2002
2THREE PROBLEMS WITH THIS ASSIGNMENT
- Concept of long-term resource requirement is
antithetical to competitive markets - What other products are purchased so far ahead of
use with such ambiguous product definition? - For what other products does government mandate
purchase? - FERCs proposed long-term resource adequacy
(LTRA) requirements, in SMD NOPR, vague and at
odds with other parts of SMD - FERCs opposition to ISO ICAP programs unclear
3ASSIGNMENT IS SIMPLE IN ONE SENSE
- Demand-response resources/programs developed for
shorter term should qualify as long-term
resources - No need to develop new programs to ensure LTRA
- Challenge is to treat demand resources comparably
(not necessarily identically) to supply resources - ISO operating and market rules accommodate supply
idiosyncrasies, need to do same for demand
resources
4KEY RESOURCE COULD BE DEMAND CURVE FOR
CONTINGENCY RESERVES
5ISSUES TO CONSIDER ...
- Forecast horizon
- Certification requirements
- Qualifying resources
- Interruptible loads and direct-load control
- Dynamic pricing
- Load participation in contingency-reserve markets
- Energy efficiency
- Seasonal v annual requirements
- RTO role in markets
- End-use infrastructure requirements
- Metering and communications
6 ISSUES TO CONSIDER
- RTO resource rights
- Retail customer/LSE obligations
- Minimum resource size
- Customer baseline level
- Payments
- Capacity
- Energy
- Penalties
- Other ??
7UNCERTAINTY OVER RESOURCES INCREASES WITH
FORECAST TIME
Plans
??
Physical resources
8WHAT CONSTITUTES CERTIFICATION AND WHEN?
- Resource Plan (long-term)
- How does RTO review and approve plan?
- Return to the days of utility IRP?
- Physical Resource (short-term, e.g., month ahead)
- Demonstration of actual load reduction within
time limit (ramp rate), metering and
communications equipment - Annual or seasonal demonstration or delivery when
called upon
9WHICH DEMAND RESOURCES CAN QUALIFY?
- YES
- Interruptible loads and direct-load control
(participants in existing DR and ICAP programs) - Bids into contingency-reserve markets
- NO
- Dynamic pricing ? Probably not
- Energy efficiency, passive nature prohibits
system operator dispatch of resource - These resources show up in load forecast
10DEMAND RESPONSE MORE VALUABLE AS LOAD REDUCTION
- Consider LSE with 100 MW peak demand, 15 reserve
requirement, and 10 MW of contracted load
reduction - If the 10 MW qualify as LTRs, then LSE needs
another 105 MW of qualifying resources - If the 10 MW reduce peak demand, then LSE needs
only 103.5 MW of qualifying resources
11HOW TO TREAT SEASONAL LOADS?
- Some load reductions are weather or season
dependent - Some are coincident with system peaks
- How to value such time-dependent load reductions?
- Calculate annual value based on hourly values of
system LOLP and potential load reduction, similar
to traditional utility system planning
12METERING AND COMMUNICATIONS DEPENDS ON TYPE OF
RESOURCE
- Interruptible Load
- Meters hourly
- Communications Receive, confirm, and act upon
RTO instructions (pager, telephone, email, fax) - Does RTO need to know load response in real time?
- Contingency Reserves
- Meters 1-minute recording
- Communications Receive and act upon RTO dispatch
instructions - Does RTO need to know load response in real time?
Who pays for this equipment?
13RTO RIGHTS
- Number of times per year (or season)
- Maximum duration of each interruption
- Minimum advance notice
- These limits generally do not apply to generators
and reduce the value of demand resources - Point in emergency sequence (OP-4) that resource
is called
14LSE/CUSTOMER OBLIGATIONS
- Prompt reporting of availability status
- Maintenance of metering and communications
equipment - For participation in contingency-reserve markets,
submission of daily availability bids (/MW-hr)
15PAYMENTS AND PENALTIES
- LTRs (both supply and demand) receive monthly or
annual reservation/capacity payments, /MW-month - When dispatched, supply paid for energy at spot
energy price and load does not pay for unconsumed
energy at same price - (Ruff argument, no double payment)
- Noncompliance vs. underperformance penalties
- Stiff noncompliance penalty is quid pro quo for
capacity payments - Underperformance penalty should be cost based
16MANY OF THESE FACTORS APPLY TO OTHER
DEMAND-RESPONSE PROGRAMS
- Minimum resource size
- Aggregation
- Frequency, duration, advance notice of deployment
- Customer baseline level
- Easier to determine for contingency reserves
17COMPARISON AMONG DR TYPES ...
18 COMPARISON AMONG DR TYPES
19MY BOTTOM LINE
- LTRA is a political necessity because of aversion
to price spikes and deficiencies in current
market designs - LTRA not compatible with competitive wholesale
energy markets - Demand resources can and should qualify as LTRs
and participate in such markets - Build on experience with existing ISO and utility
programs - Ensure comparability with treatment of generation