Totem Gas Storage Project - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Totem Gas Storage Project

Description:

No Seasonal Restrictions on Injection or Withdrawal ... Traditional Seasonal Single-Cycle. Hybrid 2.5 Cycles Per Year. HDMC 4 Cycles Per Year ... – PowerPoint PPT presentation

Number of Views:138
Avg rating:3.0/5.0
Slides: 15
Provided by: jbcon
Category:

less

Transcript and Presenter's Notes

Title: Totem Gas Storage Project


1
Totem Gas StorageProject
  • Wyoming Pipeline Authority
  • March 23, 2004

2
Highlights
  • Located 36 Miles NE of Downtown Denver
  • 9 Bcf of Working Gas
  • 135 Mmcfd Injection Capacity
  • 250 Mmcfd Withdrawal Capacity
  • CIG Interconnect Signed
  • Additional Interconnects Anticipated
  • Public Service Company of Colorado (Xcel)
  • Cheyenne Plains Pipeline
  • Kinder Morgans Advantage Pipeline
  • Southern Stars Western Frontier Pipeline

3
Highlights (contd)
  • High Operating Flexibility
  • One Hour Injection and Withdrawal Turnaround
    Capability
  • No Seasonal Restrictions on Injection or
    Withdrawal
  • Inject or Withdraw, or Both, on Any Day of the
    Year

4
(No Transcript)
5
(No Transcript)
6
Permits and Leasing
  • All Approvals, Certificates and Permits in Place
  • Colorado Oil Gas Commission
  • Colorado Public Utilities Commission CPCN
  • Colorado DPHE Air Emission Permits
  • Adams County Conditional Use Permits
  • All Required Leases and ROWs Have Been Obtained

7
Reservoir Modeling
  • Extensive Modeling of the Reservoir Has Been
    Performed by John Wells of Wells Chappell and
    Company, Houston
  • History Matching Volumetric Balancing
  • Base and Expected Cases
  • Various Service Profiles
  • High Degree of Confidence in Reservoir Integrity
    and Performance

8
Design Performance Profile
9
Engineering Cost
  • Detailed Engineering Design and Cost Estimate
    Performed in Fall, 2001 and Updated in 2002
  • Estimated Facility Cost Inclusive of Base Gas is
    57.3 million
  • Base Gas Assumption 4.5 bcf _at_ 4.00
  • Any Base Gas Savings Will Be Passed Along to
    Customers

10
Timetable
  • All of the Pre-Development Leg Work is Complete
  • 6-8 Months of Additional Development Activities
    Followed by 12 Months of Construction
  • Begin Injecting Base Gas in Summer, 2005
  • Possible Base Gas Injection Still in 2004
  • Fully Operational For Winter 2005/2006

11
Services
  • Traditional Seasonal Single-Cycle
  • Hybrid 2.5 Cycles Per Year
  • HDMC 4 Cycles Per Year

12
Tentative Rates
  • Traditional Single Cycle
  • 0.97 per Dth per Year Totem Provides Base Gas
  • 0.75 per Dth per Year Shipper Provides Base
    Gas
  • Hybrid Multi Cycle
  • 1.15 per Dth per Year Totem Provides Base Gas
  • 0.83 per Dth per Year Shipper Provides Base
    Gas
  • HDMC
  • 1.85 per Dth per Year Totem Provides Base Gas
  • 1.33 per Dth per Year Shipper Provides Base
    Gas

13
Open Season
  • Binding Open Season Was Concluded in September,
    2003
  • Negotiations Continue With Successful Bidders for
    100 of Capacity

14
For Further Information
  • J. B. Condill
  • (303) 680-4725
  • jbcrog_at_aol.com