Title: Increasing Pipeline Safety Through Shared Planning
1Increasing Pipeline Safety Through Shared
Planning
- Pipeline Safety Trust Conference
- New Orleans, Louisiana
- 930 a.m. Session, November 16, 2007
2Topic The need for policies affecting the
siting, width and other characteristics of new
pipeline rights-of-way (ROW)
3Presented by Joseph Rust Affected Landowner,
REX East Natural Gas Pipeline, Greensburg
(Decatur County), Indiana
4Background Most landowners affected by the REX
East natural gas pipeline received initial
notification of the project from REX in June 2006
via first class mail.
5- Summary of Project From www.rexpipeline.com
- Pipeline Route from REX website
6- REX Open Houses Were Ineffective, Even Harmful.
7(No Transcript)
8- Our Pipeline Path Apparently Changed
9(No Transcript)
10- Panhandle Eastern Pipeline Path In Indiana
11- Various Reasons For Southern Route Given By REX
At Different Times - The Real Reason May Well Have To Do With Waiver
REX Received From PHMSA. - Approximately 90 percent of the Rockies Express
pipeline will be located in Class 1 areas in a
common right-of-way with other pipelines.
12- REX Changed The Formula But Wasnt Challenged By
FERC - In their application of April 30, 2007, REX
stated A majority of the pipeline (over 50)
will parallel existing utility corridor
right-of-wayThe majority of the route83,
traverses Class 1 (rural and agricultural)
areas. (Pg. 16) - What happened and what are the consequences?
- Indiana Regulatory Agencies Were Not Aware of the
Project
13- Some Pipeline Path Changes Were Made Behind
Closed Doors - REX Refused to Negotiate a Satisfactory
Mitigation Agreement with Agricultural Interests
In A Timely Manner - REX Did Not Do Their Homework
- REX Assumed the Process That Worked West of the
Mississippi Would Work East of It
14- Poor Upfront Research Has Caused Numerous Changes
- Communications With Landowners in the Field Are
Poor
15What Can We Learn From This and Help Future
Pipelines Proceed More Efficiently?
- Any route following existing pipelines should
proceed as today, subject to investigation in 6
below. - Any new pipeline going into virgin territory
needs to follow a different pre-routing
procedure, including direct involvement of the
federal, state and local government agencies,
including agricultural interests, before a
pipeline route is pre-filed.
16- Having all hearings open to public in this
pre-route time would eliminate the mistrust.
Encourage Area Planning and Zoning Boards and
County Commissioners to participate. Cast a wide
net. - FERC should be in charge of the pre-routing
process and insure relevant agencies are engaged,
not just notify them. - D.O.T. (PHMSA) and FERC should work together, not
act like safety, routing and environmental
concerns are somehow separate concepts. Neither
the public, nor state and local authorities, see
them as separate, nor should PHMSA and FERC.
This is bureaucracy at its worst.
17- Before virgin routes are proposed, FERC should
determine whether existing pipelines are in need
of replacement with more modern, larger, and
safer lines. - Granting waivers should be a rare exception.
- Realistic pipeline and compressor station
setbacks need to be developed by D.O.T. in
conjunction with state pipeline safety agencies. - Educate First Responders and disaster
preparedness agencies what they must plan for in
case of a leak or rupture.
18Summary
- Better pre-planning groundwork will eliminate
most of the mistrust and misunderstandings that
exist today, and will allow natural gas to flow
in the best interests of the U.S., resulting in
lower costs and safer conditions for all.
19Thank YouI am available for questionsJoseph
Rust9597 E. Co. Rd. 550 NGreensburg, IN
47240joerust_at_dishmail.net