TRANSMISSION ACCESS - INTERCONNECTORS - PowerPoint PPT Presentation

1 / 7
About This Presentation
Title:

TRANSMISSION ACCESS - INTERCONNECTORS

Description:

TRANSMISSION ACCESS INTERCONNECTORS – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 8
Provided by: hand
Category:

less

Transcript and Presenter's Notes

Title: TRANSMISSION ACCESS - INTERCONNECTORS


1
TRANSMISSION ACCESS - INTERCONNECTORS
  • Current Arrangements
  • Addressing TRs Five Questions
  • Implications of TA Vision
  • Consideration of European Developments
  • Other Comments
  • What Interconnectors would want from any Access
    Regime

2
Current Arrangements
  • Not without issue, but in general
  • Treated as a generator and demand and charged the
    same as any other connectee
  • Capacity rights are for max capability and for
    duration of project
  • Rights are contracted through CUSC and bilaterals
    between Interconnector Owner and NGC and are
    considered firm
  • Connection and TNUoS charges made to IOs and
    recharged to Interconnector Users
  • BSUoS charges made to IUs directly
  • Have also been reasonably and successfully
    adapted under different contract structures since
    1990

3
Addressing TRs 5 Questionsunder Current
Arrangements
  • Rights are allocated to IO once security
    established, firm for duration of project
    although no absolute surety of price
  • IOs could trade those rights in theory and can
    contract on
  • Breaching contract terms could ultimately require
    disconnection and termination charges as
    appropriate
  • Initially the IO is the contracted party with NGC
    and has the prime contractual responsibility
  • NGCs transmission investment driven by needs of
    the customer building the interconnection and the
    need to meet the planning standards. No different
    from other users and prospective users.
  • Sufficient information currently available - CUSC
    processes Charge out rules, transparent
    tendering, 7yr Statement

4
Implications/Questions of TA Vision
  • Access rights will only be allocated for several
    years. Then? Auctions?
  • IOs obtain access rights? One-way or two-way
    rights?
  • IUs contract/auction for I/C and Trans. Capacity?
    Are they separable?
  • Who and how do you invest in new
    interconnections?
  • Possible incorporation of Interconnection assets
    into Transmission? Inter-system trades done at
    mid-point?
  • Existing contracts for use of the
    Interconnections? Some have 2 yrs to run, some
    have 30yrs. Explicit duration and rights.
    Compensation?
  • Should there be different rules for
    interconnections from rest of system or between
    existing and future ones?
  • Is the SO always going to be wanting to buy back
    the rights in the direction most likely to
    aggravate a transmission constraint? Or, will it
    always wait until short term when trades have
    been agreed? Will this be in the energy market or
    the access market?

5
Consideration of European Developments
  • Interconnections allow Cross Border trading, but
    are regarded as psuedo-generators at the border
  • CBT debate likely to lead to fixed or zero charge
    for use of transmission for cross border trades,
    therefore
  • Replacing Connection and TNUoS and/or any TA
    regime?
  • System to System trading? When? Who? Rights to
    use?
  • Use of interconnectors in Europe considered firm
    except when potential loss of demand results.
  • Increasing interest in ICRP model in Europe
  • Is Interconnection ownership an issue? Conflicts
    of interest?

6
Other Comments
  • Any present or future interconnection transfer
    could flow disadvantageously wrt the Transmission
    System.
  • Interconnection transfers can reverse and if seen
    to be a long term possibility then the system
    could be reinforced accordingly. The judgement
    will be one of constraints costs versus
    investment costs.
  • Hence it is important to consider this at the
    investment planning stage this will impact on
    system reinforcement requirements or in level of
    charges.
  • Ability should be retained to allow transfers to
    be curtailed to prevent (or in the event of)
    demand disconnection.

7
What Interconnectors Want From Any Access Regime
  • Entry and Exit Access rights to each system
    agreed to IO for the life of the Interconnection,
    min 25yrs and possibly 40yrs.
  • Proper recognition of Two-Way flow and
    Superposition.
  • Ability to act as a Trading Unit and a party
    acting as aggregator.
  • Equitable treatment of Interconnectors within the
    overall charging regime, reflective of their
    impact on the system.
  • Trading opportunities for IUs in all timescales
    are maximised, not frustrated, especially if
    charges are the same as other users.
  • Interconnection investment opportunities can be
    realised.
  • The ability and option to have firm and non-firm
    access rights.
  • The auctioning of Interconnection Capability
    automatically gives rights of access to the
    Transmission System.
  • Only pass-thru costs are BSUoS and CBT. Other
    costs are IOs.
  • Equitable treatment with rest of Europe.
Write a Comment
User Comments (0)
About PowerShow.com