Title: OUTLINE
1Remedial MUDSTom Gries, Dept. of Ecology
- OUTLINE
- Summary of MUDS Feasibility-Related Activities
and Studies - Evaluation of Contaminated Sediment Treatment
Technologies - Barriers to Treatment and Potential Solutions
- Final Recommendations
- Lessons for Puget Sound and the Lower Duwamish
Waterway
2Summary of MUDS
- History (mid-80s origin)
- Reconnaissance Study, Feasibility Study/Cost
Sharing Agreement (1995-1997) - Programmatic EIS (1999)
- Siting Phase Studies (2000-2001)
- Final Recommendations and Corps Feasibility
Report (2002-2003)
3Summary of MUDSProgrammatic EIS Conclusions
- Large volume of CS to be removed from Puget Sound
for safe management - No action is not acceptable
- All confined disposal alternatives feasible and
many treatment technologies promising - MUDS cost/cubic yard ? existing mgt costs
- Environmental impacts/benefits significant
- Selecting any MUDS alternative tradeoffs
4(No Transcript)
5Summary of MUDSSiting Phase Investigations
- Management Options - Who should own and operate a
MUDS facility? - Siting Process - What kind of MUDS should be
built and where? - Public Participation - Which strategy and tools
will get interest groups and the public involved?
6Summary of MUDSSiting Phase Investigations
- Feasibility of Treatment/Beneficial Use Which
technologies and beneficial uses are most
promising? - Evaluated various treatment technologies
- Surveyed vendors and end product markets
- Assessed environmental impacts, product liability
- Listed likely barriers (e.g., lack dependable
supply of contaminated sediment) and incentives - Identified funding options
7Summary of MUDSInterim Recommendations
- Identify single public MUDS authority
- Form public/private partnership for
privately-owned/operated MUDS and continue siting
process for publicly-owned MUDS - Facilitate development of regional-scale sediment
treatment capacity - Begin RFP-like process to interest private sector
- Identify preferred assistance/incentives
- Identify preferred funding/legislation
8Evaluation of Contaminated Sediment Treatment
Technologies
- What did MUDS agencies do?
- Developed evaluation process
- Agreed to (consensus) treatment technology
evaluation criteria - Developed questionnaire, conducted survey
- Compiled information submitted and applied
criteria to select top four technologies - Investigated top four further
- Identified important barriers and potential ways
to overcome them
9Evaluation of Contaminated Sediment Treatment
Technologies
- Evaluation criteria categories
- (consensus weighting factor)
- Performance (8.2)
- Flexibility (7.0)
- Cost and marketability (6.3)
- Public acceptability/permittability (5.7)
- Facility process/characteristics (5.2)
- Relevant business information (4.4)
10Evaluation of Contaminated Sediment Treatment
Technologies
- Top four technologies/products
- Ultra-high temperature combustion/glass
- Chemical immobilization/construction fill
- High temperature combustion/cement
- Soil washing/manufactured top soil
11Evaluation of Contaminated Sediment Treatment
Technologies
- Technical Feasibility
- Most types of sediment treatment are technically
feasible, for example - Particle separation
- Neutralization (chemical, electrochemical,
encapsulation, washing) - Thermal destruction/treatment
12Barriers and Potential Solutions
- Economics Related
- Continuous minimum flow of sediment or other raw
materials needed for profitability - Annual volume needed too great?
- Public sector guarantees of minimum volume
unlikely? - End or bi- product markets needed for
profitability - How certain is regional demand for clean fill,
light weight aggregate, decorative tiles, etc.? - Land (10 ac urban/industrial) and capital costs
- Facility life span interest rate interest
payments - Other (utility costs, marketing, monitoring,
closure)
13Barriers and Potential Solutions
- Others
- Treatment/reuse criteria
- Environmental impacts, product liability
- Siting and permitting processes
14Barriers and Potential Solutions
- Public acceptance
- Technical feasibility
- Facility site/location (NIMBY)
- Environmental benefits/impacts for the region and
selected location - Public process and involvement
15Barriers and Potential Solutions
- Potential Solutions
- Economics - public land, land swap, tax
incentives, legislated tipping fee - Flow - separate dewatering/storage facility,
alternate feedstocks, scheduled cleanups,
Aquafund/PSI resources, requirement to use MUDS - Product markets - public sector survey of
markets, promotions, use of products - Permitting/public acceptability - public/private
partnership
16 Final Recommendations
- Feasibility Report (USACE, Dec 2003)
- DNR should act as lead agency
- Clarify certain regulations
- Develop Request for Proposal, evaluate proposals,
sign agreement(s) ensuring access to
cost-competitive landfill disposal - Integrate mgmt alternative with DMMP
- Conclude Feasibility Study
17 Final Recommendations
- Monitor effectiveness of long-term agreement(s)
on progress cleaning up contaminated sediment
sites - Build public awareness that contaminated sediment
poses substantial environmental risk and thus is
an important environmental issue - Track progress being made to develop treatment
technologies - Restart Feasibility Study if existing management
alternatives no longer cost-competitive with MUDS
18Lessons for Puget Sound and the Lower Duwamish
Waterway
- Treatment still muddy after all these years
- A regional MUDS owned and operated by a private
sector entity requires profitability, meaning - End product markets
- Steady flow
- Site with acceptable impacts and public buy-in
- A regional MUDS owned and operated by the public
sector would likely require the same
19Lessons for Puget Sound and the Lower Duwamish
Waterway
- Food for thought
- Are any smaller-scale, more periodic treatment
options economically viable? - Particle separation technologies to reduce
volume? - Chemical immobilization and beneficial use (e.g.,
use as clean fill if meets MTCA Method B or place
at open-water disposal sites if meets DMMP
guidelines)? - Soli washing?
- Subsidize smaller-scale treatment demo projects?