Title: A NEW SYSTEM
1 A NEW SYSTEM FOR RAPID PRECAST DECK
CONSTRUCTION
FHWA International Technology Exchange Program
Prefabricated Bridge Elements and Systems in
Japan and Europe Accelerated Construction
GET IN, GET OUT, AND STAY OUT
- Total Precast Concrete Systems
- Piles Pile Caps
- Columns Bent Caps
- Girders
- Deck
2Total Precast
- Every major component of the bridge is precast
piles, pile caps, columns, pier caps, girders and
deck (or segmental box). - Currently, use of precast is common for
everything but deck construction. - However, about 50 of the cost of bridge
construction is tied up in the deck, regardless
of superstructure type.
3Piles
- Standard Precast Piles
- Square Precast Piles 12 to 36
- Cylinder Piles
- 36 to 66 Outside Diameter
- 6 Wall Thickness
- 16 Spun Cast Sections Post-Tensioned Together
4Pile To Cap Connections
5St George Island Bridge, Franklin County, Florida
Pile to Pier Cap Connection (Low Level)
6 Substructure
- Precast Forms
- Precast Forms for Pile Caps
- Precast Tubs for Pile Caps
- Precast Pile Caps
- Precast Piers and Columns
- Design Considerations
- Connections
- High Strength Threadbar
- Grout Sleeve Splices
- Rebar Cages
- Pipe, I-Girder, or Other Structural Steel Section
- Post Tensioning Tendons
7Pile Cap Forms
St. George Island Bridge, Florida
8BAY ST. LOUIS PRECAST FORM SLAB
9(No Transcript)
10(No Transcript)
11Sanibel Causeway Bridges Precast Tub
12Sanibel Causeway Bridges Precast Tub
13Columns
I-287 Cross Westchester Expressway, NY
14Columns
Linn Cove Viaduct, NC
Sunshine Skyway, Tampa, FL
Baldorioty de Castro Ave., Puerto Rico
15Columns
Louetta Road, TX
16Precast Solution
17(No Transcript)
18(No Transcript)
19Stem Element
Footing/Stem Joint
Splice Sleeve
20Pile Caps are 36-0 by 21-0 by 6-0 weigh
in excess of 300 tons
Voids are formed for piles, which extend four
feet into the cap for fixity.
Mass Concrete is monitored using Intellirock
temperature/maturity loggers, insulated using
thermal blankets
Precast Caps are formed on Barges, lifted from
one barge to another for transport
Sanibel Causeway, Lee County, Florida
21(No Transcript)
22(No Transcript)
23(No Transcript)
24Precast Piers are cast on their side, then moved
to barges for storage and transport. NMB Grout
Sleeve Splices are used to Connect piers to pile
caps. Pad-eyes are cast into the caps for
handling, they are later buried in CIP pedestals
. Piers are considered Mass Concrete pours,
monitored and insulated.
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)
29(No Transcript)
30Superstructure
- Girder Systems
- AASHTO Girders
- Bulb Tees
- Deck Bulb Tees
- Boxes, Slabs,
- Spliced Girders
- Simple Span
- Continuous
- Curved
31Deck Bulb Tees
- Bulb tee girders cast integrally with deck
- Longitudinal joints between units
- Typically no field-cast deck concrete
- May have a wearing surface
32Grouting Keyways
33BPA Bridge
34BPA Bridge
35Day 5 6
36Day 7 - Wednesday, August 25th
37Day 8 Membrane Pavement
38(No Transcript)
39(No Transcript)
40CONSTANT BULB HAUNCH
SECTION A-A
HAUNCH VARIATION DETAILS
41CONSTANT WEB DEPTH
SECTION A-A
HAUNCH VARIATION DETAILS
42(No Transcript)
43(No Transcript)
44(No Transcript)
45Decking Systems
- Conventional Forms
- Precast SIP Forms
- Deck Panels
46(No Transcript)
47(No Transcript)
48SIP Deck Form Panels
49Full-Depth Deck Panels
- Previous Woodrow Wilson Bridge
- Deck replaced in 1983 with full depth panels
50Full-Depth Deck Panels
U.S. Highway 6, Near Golden Colorado
51Full-Depth Deck Panels
52Full-Depth Deck Panels
Bid as Cost Time 30 Days Max Two, 12-Hour
Shifts Finished in 12 Days with 2 days weather
delay
53Skyline Bridge NU Deck
54Skyline Bridge NU Deck
55Skyline Bridge NU Deck
56Why Precast Deck Construction?
- Construction in Remote Areas, over Water,
Wetlands or Otherwise Inaccessible Sites. - Minimal Field Labor, Rapid Erection, Resulting
Schedule Compression. - Adverse or Uncooperative Climate/Weather.
- High Degree of Quality Control in both the
Casting Yard and at the Site. - Total Precast System Piles, Bent Caps, Girders
and Deck.
57Why Precast Deck Construction?
- Construction in Remote Areas, over Water,
Wetlands or Otherwise Inaccessible Sites. - Minimal Field Labor, Rapid Erection, Resulting
Schedule Compression. - High Degree of Quality Control in both the
Casting Yard and at the Site. - Total Precast System Piles, Bent Caps, Girders
and Deck.
58Why Precast Deck Construction?
- Construction in Remote Areas, over Water,
Wetlands or Otherwise Inaccessible Sites. - Rapid Erection with Minimal Field Labor.
- High Degree of Quality Control in both the
Casting Yard and at the Site. - Piles, Pile Caps, Bent Caps, Girders and Precast
Deck Panels.
59Rapid Precast Construction Systems
- A Patented Forming System and a New Approach to
Deck Construction - Low-Profile Bogies Designed to run on Bottom
Flanges of AASHTO B-T Girders. - A Leveling System Comprised of Leveling Bolts or
Automated Screw Jacks - Full or Partial Depth Precast Panels.
60RPCS
- A Patented Forming System and a New Approach to
Deck Construction - Low Profile Bogies Designed to Run on Bottom
Flanges of AASHTO B-T Girders - A Leveling System comprised of Leveling Bolts or
Automated Screw Jacks. - Full or Partial Depth Precast Panels.
61RPCS
- A Patented Forming System and a New Approach to
Precast Construction - Low Profile Bogies Designed to run on the Bottom
Flanges of AASHTO or B-T Girders - A Leveling System consisting of Leveling Bolts or
Automated Screw Jacks. - Full or Partial Depth Precast Deck Panels.
62How it Works.
- Bogies are Adjustable Variables include Girder
Type, Spacing, Camber Superelevation - Deck Panel Width, Jacking Frame Height, Screw
Jack Stroke, etc. - Girders are Placed and Braced.
- Panels are Wheeled into Place on Bogies, and Deck
Elevations Shot over each Jack. - Panels are lifted/lowered into Alignment, O-Rings
Installed, and Panel Joints Buttered. - Panels are Post-Tensioned together while
Suspended on Bogies.
63How it Works.
- Bogies are Adjustable Variables include Girder
Type, Spacing, Camber Superelevation - Deck Panel Width, Jacking Frame Height, Screw
Jack Stroke, etc. - Girders are Placed and Braced.
- Panels are Wheeled into Place on Bogies, and Deck
Elevations Shot over each Jack. - Panels are lifted/lowered into Alignment, O-Rings
Installed, and Panel Joints Buttered. - Panels are Post-Tensioned together while
Suspended on Bogies.
64How it Works.
- Bogies are Adjustable Variables include Girder
Type, Spacing, Camber Superelevation - Deck Panel Width, Jacking Frame Height, Screw
Jack Stroke, etc. - Girders are Placed and Braced.
- Panels are Wheeled into Place on Bogies, and Deck
Elevations Shot over each Jack. - Panels are lifted/lowered into Alignment and
Panel Joints Buttered. - Panels are Post-Tensioned together while
Suspended on Bogies.
65How it Works (Continued)
- Shear Studs are Shot onto Girders to Provide
Horizontal Shear Strength - Before Panel Placement if Full Depth Panels are
used. - Rigid Foam Form Stops are placed to Channel
Grout for Build-Up.. - Grout is Injected through Ports in the Deck
Panels to Provide Build-Up and - Composite Bond.
- End Diaphragms and Closure Pours are CIP over the
Pier/Bent Caps. - Bogies Proceed, One by One, from One Span to the
Next. - Intermediate Diaphragms, if required, can be
precast, and set after the deck - is in place delivered on Bogies.
66How it Works (Continued)
- Shear Studs are Shot onto Girders to Provide
Horizontal Shear Strength - Rigid Foam Form Stops are Placed to Channel
Grout for Build-Up. - Grout is Injected through Ports in the Deck
Panels to Provide Build-Up and - Composite Bond.
- End Diaphragms and Closure Pours are CIP over the
Pier/Bent Caps. - Bogies Proceed, One by One, from One Span to the
Next. - Intermediate Diaphragms, if required, can be
precast, and set after the deck - is in place delivered on Bogies.
67How it Works (Continued)
- Rigid Foam Backer Rod is Placed and Panels
lowered to Finished Grade - Shear Studs are Shot onto Girders to Provide
Horizontal Shear Strength - Grout is Injected through Ports in the Deck
Panels to Provide Build-Up and - Composite Bond.
- End Diaphragms and Closure Pours are CIP over the
Pier/Bent Caps. - Bogies Proceed, One by One, from One Span to the
Next. - Intermediate Diaphragms, if required, can be
precast, and set after the deck - is in place delivered on Bogies.
68How it Works (Continued)
- Rigid Foam Backer Rod is Placed and Panels
lowered to Finished Grade - Shear Studs are Shot onto Girders to Provide
Horizontal Shear Strength - Grout is Injected through Ports in the Deck
Panels to Provide Build-Up and - Composite Bond.
- End Diaphragms and Closure Pours are CIP over the
Pier/Bent Caps. - Bogies Proceed, One by One, from One Span to the
Next. - Intermediate Diaphragms, if required, can be
precast, and set after the deck - is in place delivered on Bogies.
69Field Services
- Supply and Maintenance of Bogies and Jacks over
the life of the Project. - Supply and Maintenance of Battery Molds for
Casting Panels. - Field Measurements of Girder Camber,
Determination of Dead Load Deflections, - and Calculation of Required Build-Up.
- Field Crews to Set, Level, Post-Tension and
Grout the Deck Panels. - Load Ratings, if Required by the Owner.
70Design and Construction Considerations
- Transverse Prestress By varying strand size, a
full range of girder spacing - can be accommodated using the same strand
pattern.
71Design and Construction Considerations
- Longitudinal Post-Tensioning Finite Element
Analysis can be used to - size tendons based on tension across panel
joints. Residual Compression ensures - adequate shear transfer across panel joints.
72Design and Construction Considerations
- Composite/Horizontal Shear Transfer The current
AASHTO Equations - recognize that cohesion as well as shear
friction contributes to composite - shear transfer. On Wide Flange Bulb-Tees,
cohesive forces are adequate to resist - virtually all horizontal interface shear
forces. At girder ends, headed studs - can be used to supplement cohesive forces. Two
foot stud spacing can - be provided, though analysis shows strength is
adequate at greater stud spacing.
73Design and Construction Considerations
- Bracing Bracing is needed to stabilize girders.
A simple system for bracing - the girders over piers has been developed that
allows bogies to roll freely - from one span to another. A stiffened plate
or wheel bridge spans the gap - between girders.
- Between piers, thrust due to wheel loads is
resisted by friction between - polyurethane treads on the concrete, but
supplemented using a system - of brackets clamped to the bottom flanges
(brackets can be placed from above).
74A Flexible Approach Rapid Precast Construction
Systems Can Provide
- Bogies (precast deck panels or traditional form
stripping) and/or Battery Moulds. - Full or Partial Depth Precast Slabs.
- Engineering Field Support from Conceptual
Design thru Project Completion. - Total Precast Solutions.
75(No Transcript)
76(No Transcript)
77(No Transcript)
78Automated System Operation
Bogies are winched forward incrementally (winches
are located on the lead bogie) Screw jacks are
pre-leveled, and a panel is set. The train is
pulled forward, and the next panel is set. At
the end of each step, screw jacks are adjusted to
maintain uniform panel support. Jacks adjustment
is made from a touch screen panel, either
individually, or uniformly as a group. Once
the entire span is filled, elevations are shot
over each jack, and each jack is adjusted to
level all panels into the same plane. Panels are
then post-tensioned. After post-tensioning, the
deck is lowered uniformly - to final grade,
and the build-up is placed between girders and
deck.
79(No Transcript)
80(No Transcript)
81QUESTIONS?