Ascend: Upgrading your Oracle Applications - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

Ascend: Upgrading your Oracle Applications

Description:

Unable to perform data upgrade on a timely basis ... Usually over weekend or extended weekend. Test User accessibility. 9/6/09. Page 20 ... – PowerPoint PPT presentation

Number of Views:66
Avg rating:3.0/5.0
Slides: 26
Provided by: nick73
Category:

less

Transcript and Presenter's Notes

Title: Ascend: Upgrading your Oracle Applications


1
(No Transcript)
2
Ascend Upgrading your Oracle Applications
  • Brian Kobylinski, Manager

3
Agenda
  • Common Upgrade Pitfalls
  • Ascend Overview
  • Benefits of Ascend
  • Questions and Answers

4
Common Upgrade Pitfalls
  • Insufficient Hardware Resources
  • Not all customizations are upgraded
  • New functionality not utilized
  • Unable to perform data upgrade on a timely basis
  • Incomplete project plan - vital tasks
    missed/overlooked

5
Ascend Overview
  • What is Ascend?
  • marchFIRSTs Oracle Applications Upgrade
    Methodology
  • Based on previous experience and best practices
  • Bottom-Up developed methodology
  • Reviews new functionality opportunities
  • Challenges current customizations
  • Review and enhancement of Architecture
  • Provides tools, procedures and templates
  • Tried and tested product

6
Ascend Overview
  • Four Key Phases
  • Assessment
  • Migration
  • Transition
  • Support

7
Assessment Phase
  • Technical
  • Functional
  • Project

8
Technical Assessment
  • Identify all existing customizations using
    pre-written utilities
  • Forms,Reports, PL/SQL
  • Interfaces
  • Database triggers, Tables, Views, etc.
  • Responsibilities, Menus
  • Examine the current hardware
  • Disk Space
  • Existing environments
  • New environments required
  • Operating System

9
Technical Assessment
  • Plan new Architecture requirements
  • 2 or 3 Tier ?
  • New Server sizing considerations
  • Existing Server sizing
  • Thin Client requirements

10
Functional Assessment
  • Oracle Applications New Features presentations
  • Review Existing Functionality used and new
    functionality opportunities
  • Workshops to identify redundant customizations

11
Project Assessment
  • Determine which customizations are to be migrated
  • Produce a detailed Project Plan with resource
    usage
  • Utilize Client Resources
  • Templated Upgrade Project Plan
  • Produce Project Charter that includes Project
    Governance, Change Control procedures and Issue
    Tracking procedures

12
Assessment Phase - Summary
  • Short Duration
  • Deliverables
  • Customizations Report
  • Environment Planning Report
  • New Features Presentations
  • Functional Assessment Report
  • Detailed Project Plan
  • Project Charter
  • Accurate estimate of costs for remainder of the
    project

13
Migration Phase
  • 3 Parallel Activities
  • DBA Trial Upgrade
  • Implementing New Functional features
  • Migrating required customizations

14
Migration - DBA Responsibilities
  • Perform Trial Upgrade(s)
  • Document all required pre post upgrade steps
  • Upgrade the RDBMS
  • Apply necessary patches
  • Identify any data problems and produce scripted
    solutions
  • Capture upgrade timing information

15
Migration - Technical Responsibilities
  • Produce design addendum's for required
    customizations
  • Modify and unit test custom modules in accordance
    with designs
  • Migrate custom set-up lost during upgrade
  • Menus, Responsibilities,Request Groups, etc.
  • System test the customization against the
    upgraded database

16
Migration - Functional Responsibilities
  • Produce Solution Designs for new functionality
  • Perform additional Application set-up against the
    upgraded database
  • System test new functionality set-up
  • System test old functionality

17
Migration - Testing
  • Repeat the Trial Upgrade
  • Check new data combinations
  • Insure upgrade process is tuned
  • Perform User Acceptance Testing
  • Test new Oracle Functionality
  • Test all Customizations
  • Test Interfaces
  • Test old Oracle Functionality

18
Migration Phase - Summary
  • Largest and longest phase of the upgrade project
  • Customizations are migrated
  • Trial Upgrade(s) performed
  • New Functionality set-up
  • Acceptance Tested system
  • All upgrade problems/patches identified
  • Required time for upgrade established

19
Migration Phase - Summary
  • Deliverables
  • Upgrade Steps Document
  • System Test Approach
  • System Test Scripts
  • Design Addendum
  • Module Control List

20
Transition Phase
  • Train the end-users
  • New functionality
  • GUI look and feel (post-10.7)
  • Prepare Production Environment
  • Ensure all code and scripts are in place
  • Necessary space available on servers
  • Perform Live Upgrade
  • Usually over weekend or extended weekend
  • Test User accessibility

21
Support Phase
  • Go-Live Support
  • Technical
  • Functional
  • DBA Performance Review
  • Database tuning, if required
  • Access to Consultants

22
Benefits of Using Ascend
  • Based on prior upgrade experience
  • Used as part of over 30 upgrade projects globally
  • Templated documents
  • Written to address clients needs
  • Pre-written and tested Utilities to aid technical
    assessment

23
Question and Answer Session
24
Ascend Upgrading your Oracle Applications
Contact Information Brian Kobylinski 312-361-666
8 brian.kobylinski_at_marchFIRST.com
25
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com