Title: LARP LHC PHASE II COLL RC1 TESTS S. Lundgren 16 May 2006 No 1 22
1LARP Phase II Secondary Collimator RC1
- Collimator Test Program
- Revised 5/15/06
2LARP Phase II Secondary Collimator
RC1Collimator Test Plan
- Near term
- Jaw/Cooling Tube Joint Development
- Single Jaw Thermal Tests
- Later this year
- Design and fab hardware for Mechanical Prototype
Tests
3Jaw/Cooling Tube Joint DevelopmentPurpose
determine appropriate joint configuration
fabrication methods
- May 18th
- Cooling Tube
- Jaw Center
Mandrel
- In process.. target completion date
-
- Square hollow magnet conductor for first test 9
mm x 9 mm - Copper jaw and mandrel
- Cu-Au braze
- After first braze, machine coil o.d. for correct
fit to jaw i.d. - After second braze, section assy to inspect
coverage - Round tubing with grooved (?) mandrel is next
70 mm dia
100 mm dia
100 mm
4Jaw/Cooling Tube Joint Development
- Cooling Tube cross-section Options
- Preferred method is round tubing in a D shaped
groove - Flattening of tube can be done by rolling with
alcohol lubricant in clean environment - May require several groove shape attempts to
obtain braze uniformity (will start with .5 mm
flattening of tube) - Material should be available in Copper Alloy 101
OFE Class 2 ASTMF- 68 - Square tubing in square groove requires a
machining step prior to second braze - This may be a difficult machining operation
without lubrication - Material availability may be a problem
- Only certain od/id combinations are available
- Chemical composition is a concern wrt (see above)
5Jaw/Cooling Tube Joint Development
- Determine Mandrel/Cooling Tube features and
develop the winding process - Select constant or varying pitch grooves (ANSYS)
(Eric) - Design dummy parts for round tube test (Steve)
- Design tightening feature for center u-bend
location - Determine if bend radius is adequate to prevent
crushing - Perform tight radius bends in tube with/without
cerrobend or other recommended material (to
prevent crushing) - Perform preliminary winding test(s)
- Develop best winding techniques for manufacturing
process - QA assembly prior to brazing with ball test of
completed Mandrel assembly (80 diameter
spherical bead)
6Jaw/Mandrel/Cooling Tube RD Plan Forward
Square Cooling Tube Braze Test
Today
Machine od of coil to clean up winding
deformation
Square Tube is currently brazed to mandrel
Machine id of Jaw to suit coil od
Document results with photos and writ-up
of complete process
Braze assembly together
Machine into sections to inspect braze joint
7Jaw/Cooling Tube Joint Development
8Jaw/Cooling Tube Joint Development
- Glidcop Test Jaw showing D groove, entrance and
exit ports for cooling tube
Copper plating (.05mm thick) is required on outer
surface prior to brazing on the OFE copper tubing
Plating, winding, rolling and brazing techniques
will be developed during this test
9Single Jaw Thermal Test Hardware
- Long lead items (2-6 weeks)
- 2x Heater controllers are on order due mid June
- Ready to buy 4x 5kW electric resistance heaters
(380 mm long) - Ready to buy Glidcop material for 1 Jaw (2
Halves) - Ready to buy Glidcop material for 1 Mandrel
- Ready to buy molybdenum matl for Shaft (2
Halves) (vendor stock) - Heater Mount
- Determine appropriate material
- Design Mount profile for reasonable heat flow
into facet - Mount sections are 25 mm long to minimize effect
on Jaw stiffness - Bore to be .05 mm dia oversize of actual heater
size (15.88 mm dia) - Attach to facet by brazing (hold in alignment
with dummy heater) - Thermocouple attachments in Jaw
- Locations, depth, size, electrical isolation
features in Glidcop Jaw
10Single Jaw Thermal Test Hardware contd
- Jaw Support( bearings and mount)
- RC1 Bearings
- Mount them on V blocks or?
- Rigid mounting for capacitance sensors
- Locate at ends and center of Jaw
11Single Jaw Thermal Test Hardware
12Single Jaw Thermal Test Hardware
- Cooling Coil/Mandrel/Shaft Assembly
13Cooling Coil/Mandrel/Shaft Assembly Section
When inlet and outlet cooling tubes exit the
shaft on the bearing axis each tube will twist on
its own axis when the collimator is rotated
14Single Jaw Thermal Test Hardware
- Cooling tube entrance and exit detail
15Single Jaw Thermal Test Hardware
- End View of Cooling Coil wound on to Mandrel
16Single Jaw Thermal Test Hardware
Inner bore is tapered to facilitate assembly
Glidcop cost is 7884 each
17Single Jaw Thermal Test Hardware
- Jaw / Heater / Sheath Assembly cross section
2x 5kW Heater
38x 25 mm long Heater Mount
Braze Mounts to Jaw facet
18Single Jaw Test Thermocouple Locations
- Thermocouples are recessed into Jaw slightly
below the surface - Spaced along Heater length and equally spaced
half way around Jaw circumference - Should yield the Jaw heating profile predicted by
the FE analysis
2 x 5kW Heaters 30 x Mount (brazed to Jaw)
19Single Jaw Thermal Test Hardware
DAC Control Block Diagram
Heater 1 Controller
PC with LabView Software
Jaw Heater 1
Over Temperature Control
Heater 2 Controller
Jaw Heater 2
Capacitec Signal Amplifier
Jaw deflection sensors
DAC Signal Processor
Jaw thermocouples
20RC1 Mechanical Prototype Test
- Purpose bench top testing of the jaw actuating
mechanism in CERN orientations - Vacuum tank with easy access
- CERN adjustment mechanism
- SLAC cooling water feed-throughs and flexible
connections - SLAC rotation mechanism
- Simplistic control system for jaw aperture
- Minimal instrumentation connections for position,
temperature, etc. - RC2 will incorporate LHC-compliant interfaces
- Heat loading may not be possible
- Use CERN Phase I components as appropriate
21RC1 Mechanical Prototype
FY07 RC1 consists of jaws, tank actuators -
evaluated for horizontal (shown), vertical (90o)
and skew (/- 45o) orientations.
FY08, RC2
Variant use CERN vac tank, dummy jaws of correct
weight
22Development/Test Lab