Title: BUILDING PROJECT UPDATE
1BUILDING PROJECT UPDATE
- Fountain Lake School District
- December 18, 2008
2HISTORY Steering Committee
- Kristi Campbell
- Tim Forrest
- Carol Freeland
- Howard Freeland
- Lowell Hightower
- Darla Hollansworth
- Chelsy Jackson
- Tommy James
- Gene Johnson
- John Lands
- Jessie Ledbetter
- Wendell Sharpton
- Phil Simon
- Lewis Stivitts
3HISTORY Highlights from Steering Committee
Report September 2007
- Recommendation to reorganize to grades Pre-K to 4
as elementary, 5 to 8 as middle school and 9 to12
as high school - Build new 27 room middle school facility
- Existing 5th-6th grade classrooms used for
elementary - Add 14 new high school rooms. Convert two story
building to administrative offices or raze. - Net 41 room addition for grades 5 to 12.
4CONCEPT DRAWING BASED ON STEERING COMMITTEE REPORT
HIGH SCHOOL
EXISTING TWO STORY
MIDDLE SCHOOL
5HISTORY Debt Restructuring and ad valorem Tax
September 2007
- Steering Committee report proposed 10,000,000
construction costs - 34.9 mill tax restructuring and bond issue for
12,210,000 to retire 2,210,000 existing bonds
and provide 10,000,000 for new construction - Voters passed the ballot measure and also settled
a long running legal battle over tax assessments
and Amendment 59.
THANKS!
6PROGRESS
- October 2007 Issued bonds
- November 2007 Interviewed Arnold Associates
to provide architectural services for new
building project. - November 2007 Interviewed Nabholz Construction
to provide construction management services for
project. - December 2007 Hired Arnold Associates and
Nabholz, established project team and began
working on preliminary design. - May 2008 Preliminary report from Nabholz
7PROGRESS Purchased Church Property and Cleared
Adjacent Lot
136,484
8PROGRESS Demolished Old Pre-School Building
Relocated Pre-K
14,168
9PROGRESS Relocated Tennis Courts
311,632
10PROGRESS Installed New Drainage
FLOODING
GUSTAV
FLOODING
IKE
891,326
11NEW MIDDLE SCHOOL AND HIGH SCHOOL RENOVATIONS
63,362 SF TOTAL
16,006 SF
47,356 SF
12SITE PLAN
GREEN SPACE
NEW 2-STORY MIDDLE SCHOOL
TURN LANE
PARKING EXPANSION FROM 68 TO 108 SPACES
13MIDDLE SCHOOL LOWER FLOOR
- 11 - 7th 8th GRADE CLASSROOMS
- SCIENCE LAB AND COMPUTER LAB
- 4 SPECIAL EDUCATION ROOMS
- RECEPTION, OFFICES, CONFERENCE ROOMS, STORAGE,
DETENTION
14MIDDLE SCHOOL UPPER FLOOR
- 11 - 5th 6th GRADE CLASSROOMS
- SCIENCE LAB AND COMPUTER LAB
- ART ROOM
- LIBRARY/MEDIA CENTER
15MIDDLE SCHOOL LIBRARY/MEDIA CENTER
EXPOSED WOODEN BEAMS AND DECKING
FABRIC DUCT
NATURAL LIGHTING
16MIDDLE SCHOOL CONDITIONED ATTIC MECHANICAL ROOM
17HIGH SCHOOL EXISTING
- 10 EXISTING CLASSROOMS
- ART ROOM
- SMALL BATHROOMS
- LIMITED STORAGE
- HISTORICAL PROBLEMS WITH ELECTRICAL AND
PLUMBING - HISTORICAL PROBLEMS WITH LEAKING FLAT ROOF
- FLOODING PROBLEMS BEFORE NEW DRAINAGE PROJECT
18HIGH SCHOOL RENOVATIONS
- 7 CLASSROOMS
- LARGE ART ROOM
- JOURNALISM ROOM
- LARGE MEDIA CENTER
- RENOVATED BATHROOMS
- EXPANDED STORAGE
- NEW PLUMBING AND ELECTRICAL
- NEW SLOPED ROOF STRUCTURE
19HIGH SCHOOL RENOVATIONS
EXISTING
NEW
20DESIGN FEATURES
- Slab Foundation
- Wood Frame With Sprinkler System (No fire
retardant treated wood) - Impact Resistant Gypsum Interior Walls
- Two Tone Brick Veneer Exterior
- Metal Roof Over Wood Deck
- Considerable Exterior Glass
- Metal Exterior Accent Panels
21NEW FACILITIESSPACE SUMMARY
- 22 New Middle School Classrooms
- 4 New Middle School Special Education Rooms
- 7 New High School Classrooms
- 2 New Science Labs
- 2 New Computer Labs
- 2 New Art Rooms
- 2 New Libraries/Media Centers
- 1 New Journalism Room
- 35 New offices, work, storage, conference rooms
- 18 New or Renovated Restrooms
- 10 Existing Classrooms to Elementary
- 1-3 Portable Buildings Removed
- 1-2 Portable Buildings Used for Other Purposes
42 ROOMS vs. 41 PLANNED
22ENERGY EFFICIENCY AND OTHER GREEN FEATURES
- Wood Frame Construction
- Cool Roof specification on the roof sheathing
- Foil backed wood roof underlayment
- Use of windows to take advantage of natural light
- GE Ecolux Low Mercury High Efficiency Fluorescent
Bulbs - Occupancy sensors in the rooms
- HVAC Energy Management System
- Split system HVAC units in each classroom for
zoned control - Energy Recovery Ventilation System
- Specification for high recycle content materials
including ceiling tile, carpet, and floor tile - Low E rated glass with thermal break frames for
all windows - Low VOC paint
- Mechanical room in conditioned attic space
- 6 wall framing for better thermal and acoustical
insulation - Renovating existing structure rather than
building new
23BUILDING FUND
Current Balance 8,674,404
Projected 2009 Interest Income 150,000
Projected Total Income 10,574,772
Projected Available Funds 8,824,404
24PROJECTED CONSTRUCTION COST Conceptual Budget
- Conceptual Budget by Nabholz In May 2008
projected total costs at 10,765,413 - Budget was 295,793 low on the drainage project,
118,488 high on the tennis courts, and did not
include an estimated 536,878 for A/E fees,
325,000 for furnishings, 340,000 for technology
and approximately 261,678 for the church
property, pre-school relocation, landscaping and
miscellaneous expenses. - Adjusted total project budget would have been
12,406,274 (1.83 million high)
25PROJECTED CONSTRUCTION COST Cost Saving Measures
- Removed 4,970 SF multi-purpose building from
scope at estimated savings of 769,722 - Changed building design from masonry walls and
metal roof structure to wood frame structure with
brick veneer and metal roofing. - Original budget for masonry and steel was
148.35/SF for the middle school and 92.78/SF
for the renovations (134/SF combined excluding
site work and A/E fees, 150/SF with site work
and A/E fees). - Bids came in at combined 107/SF with site work
and A/E fees for an additional cost savings of
approximately 2.7 million (3.5 million total).
26PROJECTED REMAINING CONSTRUCTION COST
KNOWN EXPENSES
ANTICIPATED REMAINING EXPENSES
27PROJECTED FUND BALANCE
28SCHEDULE
- Middle School Construction
- Begin December 2008
- Complete By January 2010
- Renovations
- Begin January 2010
- Complete By August 2010