Title: before picture not currently available. arac constructed 1
14 SR-260, PinetopGood Performing Project
- SR 260 MP 351-354
- F-044-1-509
- Built 1991
2Pinetop
SR 260 MP 351
3SR260 Lakeside-Pinetop 1991
Before picture not currently AVAILABLE ar-ac
constructed 1991
4SR260 Lakeside-pinetop 2000
5SR260 Lakeside-pinetop 2000
6SR260 Lakeside-Pinetop 2000
7Location Info., SR 260 Pinetop
- Traffic ADT, ESALs 190,000/Year
- Elevation
6,500 - July Avg. Monthly High Temp. 83 F
- Jan. Avg. Monthly Low Temp. 18 F
- Avg. Annual Rainfall 15
- Avg. Annual Snowfall 40
8Existing Pavement, Pinetop
- Surfacing Thickness 7 HMA
- Base 8 AB
- Subgrade Clay Basalt R-Value 20
- Percent of Grade Flat
- Deflection Data, FWD, Temp.
- D1, D2, D3, D4, D5, D6, D7
- 13.01, 8.22, 4.61, 2.78, 1.82, 1.36, 1.01 72 F
9Before Overlay Data, PinetopYear 1990
- Cracking 2
- Crack Lineal Ft./Ln-Mile 2,534
- Crack Lineal Ft./Sq. Ft. .04
- Ride Smoothness 96 IRI
- Rutting 0.25
- Skid Number 46
- Maintenance Cost 2,500/Ln-Mile-Yr
10After Overlay Data, Pinetop2000, Age 9 Years
- Overlay 1 Gap AR-AC, Built 1991
- Cracking 1
- Crack Lineal Ft./Ln-Mile 1267
- Crack Lineal Ft./Sq. Ft. .02
- Ride Smoothness 78 IRI
- Rutting 0.12
- Skid Number 55
- Maintenance Cost 650/Ln-Mile-Yr
11SR 260 Pinetop, Base Asphalt Binder Data AC-10
12SR 260 Pinetop, Asphalt Rubber Tests
13Mix Design, PinetopGap ARAC
- AR Binder 7.6, Grade of Asph. AC-10
- -1/2, -3/8, -8, -40, -200 Gradation
- 100, 84, 17, 6, 1.5
- Sand Eq. 91, VMA 20.6, Air Voids 5.1
- Water Absorption 1.18 Asphalt 0.36
- Combined Sp. Grav. 2.553, 1 Cement
- Marshall Stab. 1003, Flow 9, MTD 144.2