Title: NPDES Permit Compliance Action Plan
1NPDES Permit Compliance Action Plan
- Final Summary for the
- Galt City Council
- May 16, 2006
2Presentation Outline
- Background Review of Implementation Options
- Summary of Previous Council Decisions
- Latest Information and Recommendation on Option C
- Chapter 8 of the Action Plan
- Implementation Recommended Actions and Schedule
- Recommended Council Actions
3Implementation Options Evaluated
- Option A Laguna Creek Seasonal Discharge with
Continued Reclamation - Option B Laguna Creek Year-Round Discharge
- Option C Sacramento River Discharge
- Option D Zero Discharge with Full Reclamation
4Option A Laguna Creek Seasonal Discharge
5Option B Laguna Creek Year-Round Discharge
6Option C Sacramento River Discharge
Requires construction of a 12-mile pipeline and
river outfall facilities.
7Option D Zero Discharge
8Previous Council Decisions
- Eliminate Option D from Further Consideration
- Meet with Regional Board to Discuss Long-Term
Implications of Sacramento River Discharge
(Option C)
9Summary of Meeting with Regional Board Regarding
Option C
- Participants Mayor Clare, Council Member Malson,
City Staff, RWCQB Principal Engineer Ken Landau,
RWQCB Staff - RWQCB Input
- Tertiary filtration is coming closer to the
standard for all discharges (via best
practicable control technology). - Assimilative capacity for metals in the
Sacramento River is expected to decrease. - Dilution credits for discharge to the Sacramento
River (if granted) are likely to decrease over
time.
10Cost Comparison Option C with Filters
- Option B for 3 mgd with Wetlands 49M
- Option C for 3 mgd with Filters 71M
- Option B for 6 mgd with Wetlands 92M
- Option C for 6 mgd with Filters 107M
11Option C Considerations Based onRegional Board
Input and Cost Analyses
- High likelihood that tertiary filtration will be
required. - Dilution that may be available for metals and
trace constituents may be reduced over time. - Adding filters now makes Option C the most costly
compliance alternative.
12Conclusions and Recommendation forOption C
- Emerging treatment and water quality requirements
jeopardize the benefits of a Sacramento River
discharge. - With these added risks, there is little reason to
continue pursuit of this option.
Recommendation Drop Option C from further
consideration.
13Chapter 8 of NPDES Permit Compliance Action Plan
- Three Main Sections
- Summary of Key Conclusions and Observations
- Evaluation and Comparison of Implementation
Options - Action Plan for NPDES Compliance
- Sections 1 and 2 Summarize Information Presented
Previously - Section 3 is New and Constitutes the Action Plan
- Specific Projects and Tasks are Identified
- An Implementation Schedule is Presented
14Recommended Action PlanImmediate Action Items
(20062008)
- Conduct Flow and Water Quality Analyses for
Laguna Creek to Support NPDES Permit Negotiations - Conduct Effluent Water Quality Studies
- Begin Pilot Tests of Filtration Systems
- Design Selected Treatment Improvements
(Filtration, UV Disinfection) - Design Solids Processing Improvements
15Recommended Action PlanImmediate Action Items
(20062008)(Continued)
- Design and construct grit removal improvements.
- Prepare a rate study based on updated cost
estimates. - Prepare a Financial Plan.
- Continue source control activities.
- Postpone construction of pilot-scale treatment
wetlands until filter and water quality tests are
complete.
16Recommended Action Plan Long-Term Action Items
(20082012)
- Pursue additional land for effluent reclamation
and expand program to provide capacity through
construction of improvements. - Construct filter and UV facilities.
- Construct solids processing improvements.
- Perform translator and water effects ratio
studies (if needed). - Design and construct secondary treatment
improvements. - Design and construct full-scale treatment
wetlands (if needed).
17Recommended Action Plan Schedule
18Task Orders Requiring Council Authorization to
Proceed with Highest Priority Tasks
- Effluent and Laguna Creek Special Studies
(173,500) - Biosolids Processing Improvements (71,700)
- Filtration and UV Disinfection Preliminary Design
(255,300) - Grit Removal Facilities (Under Negotiation)
19(No Transcript)
20Galt WWTP Schedule Analysis
21(No Transcript)
22TREATMENT WETLANDS
FILTERS
WWTP PROCESS SCHEMATIC FOR OPTION A (WINTER
OPERATION)
23TREATMENT WETLANDS
FILTERS
NEED FOR/ADEQUACY OF WETLANDS IS DEPENDENT UPON
OUTCOME OF WATER QUALITY STUDIES, DILUTION
CREDIT, PILOT TESTING
WWTP PROCESS SCHEMATIC FOR OPTION B
24Estimated Capital Costs and OM Costs for Each
Option at 3 mgd
These costs are based on existing information and
assumptions, and are subject to change.
25(No Transcript)