Title: Cleco Transmission Planning Summit
1- Cleco Transmission Planning Summit
- Attachment K
- November 15, 2007
- Terry Whitmore
-
2FERC Order 890 Attachment K OVERVIEW
- STRAWMAN
- Presented FERC Little Rock technical conference.
- White Paper
- DRAFT ATTACHMENT K
- Presented FERC Atlanta technical conference.
- Solicited additional feedback prior to summit.
3Cleco Power Annual Transmission Planning Process
4FERC Order 890 Attachment K Definitions
- Base Case Model
- Critical Energy Infrastructure Information (CEII)
- Confidential Information
- Planning Criteria
- Construction Plan
5FERC Order 890 Attachment K Definition Comments
- Comment - Confidential Information
- Definition too broad
- Cleco Response
- Cleco disagrees. Consistent with FERCs model of
Protective Order confidentiality provisions of
OATT. - Comment - Construction Plan
- What is construction plan limited to 5 years
- Cleco Response
- Five year time frame came from Clecos budgeting
dept. Cleco agrees that a plan should exist to
include proposed projects up to 10 years.
6FERC Order 890 Attachment K Definition Comments
- Comment -Base Case Model
- Specify time period
- Indicate changes discrepancies in SPP SERC
models - Stakeholders should have input into SPP SERC
- Cleco Response
- MMWG set model time frame
- Cleco submits data for Clecos CA
- Data same for Cleco in both SPP SERC
- Stakeholders need to participate through SPP
SERC process not Cleco.
7FERC Order 890 Attachment K Planning Process
- Model Development including input by
stakeholders. - 10 year plan (Construction Plan 1-5, Proposed
Plan 6 - 10). - Coordinated regional planning with adjacent
transmission owners.
8FERC Order 890 Attachment K Planning Process
Comments
- Comment - Input into planning criteria.
- Cleco response. Planning criteria is industry
accepted. - Comment - Coordinated regional planning with
adjacent transmission owners. - Cleco response. Agree. Only adjacent systems
are monitored. Change Attach K to transmission
owners.
9FERC Order 890 Attachment K Coordination
- Stakeholders may request formation of committee.
- Open welcome input from stakeholders.
- Post calendar of events on OASIS as well as email
exploder to keep stakeholders up to date on
planning process as well as allow comments and
input. - Affected systems
10FERC Order 890 Attachment K Coordination Comments
- Comment - Summit is to inform stakeholders rather
than solicit input no follow up. - Cleco Response - Section 5.1 clearly states
stakeholders may comment and provide input. Flow
chart shows posting pre post summit. - Comment Company affiliates cant hold more
than one seat on stakeholder committee - Cleco Response Cleco agrees and language will
be changed.
11FERC Order 890 Attachment K Coordination Comments
- Comment Stakeholder may request any issue
related to transmission planning be considered by
committee. - Cleco Response Cleco agrees and language will
be changed.
12FERC Order 890 Attachment K Openness
- Willing to share all information, but must
protect confidential information including CEII. - Require requester to sign confidentiality
agreement.
13FERC Order 890 Attachment K Openness Comments
- Comment Signing a confidentiality agreement is
too excessive. - Cleco Response consistent with OATT and we are
referring ONLY to confidential information. Non
confidential information does not apply.
14FERC Order 890 Attachment K Transparency
- Cleco will allow stakeholder to request base case
power flow models, planning criteria, as well as
assumptions for verification and validation of
studies provided appropriate confidentiality
agreements are in place. - Post construction plan on OASIS.
15FERC Order 890 Attachment K Transparency
Comments
- Comment - Stakeholder should be allowed to
download information directly rather than make a
request. - Cleco response White paper does not specify
downloading, only process to obtain information.
Cleco is evaluating technical options including
eRoom or FTP server
16FERC Order 890 Attachment K Information Exchange
- Firm PTP reservations will be modeled during
active timeframe of TSR, unless it qualifies for
rollover rights (5 years or more). - Network customers (native load non-native load)
submit a 10 year load forecast DNRs.
17FERC Order 890 Attachment K Comparability
- All stakeholders are treated comparably whether
network, Point to Point, or pre 888. - Models and supporting data are available for
replication duplication of results.
18FERC Order 890 Attachment K Dispute Resolution
- Any party may dispute planning process by
providing written notice of such dispute. - Representatives of each party shall negotiate to
resolve dispute within 10 business days - Executive management of each party (30 days)
- Hire an external mutually agreed upon mediator
- File section 206 complaint with commission
19FERC Order 890 Attachment K Dispute Resolution
Comments
- Comment Should not apply to pre 888 agreements.
- Cleco response Agree, it is an OATT attachment.
- Comment Who is independent regional planning
authority? - Cleco response SPP
20FERC Order 890 Attachment K Regional
Participation
- Cleco participates in SPP SERC (Entergy) model
development processes. - Coordinate with affected systems
- Joint planning meetings w/ Entergy (SERC) SPP.
- Voting member of SPP TWG.
21FERC Order 890 Attachment K Economic Planning
Studies
- Separate queue on OASIS for TSR generator
interconnection. - Study annually three (3) highest priorities as
established by stakeholders (previously 1)
22FERC Order 890 Attachment K Economic Planning
Studies Comments
- Comment May be impracticable to submit data at
time of economic study request. - Cleco response Disagree. Execute study, scope
details must be included. - Comment Confidentially of data.
- Cleco response Agree. Language will be added
for confidential information.
23FERC Order 890 Attachment K Economic Planning
Studies Comments
- Comment Cost of studies above 3 will be
assigned to requesting parties. - Cleco response Agree. Language will be
modified. - Comment Requesting parties be billed as study
cost are incurred rather than prepayment. - Cleco response Draft language to be consistent
with OATT for study cost payments.
24FERC Order 890 Attachment K Cost Allocation
- Reliability Upgrades LPSC rate base for
planning criteria violations. - Economic Upgrades
- Cost allocated to beneficiary.
25FERC Order 890 Attachment K Cost Allocation
Comments
- Comment Stakeholders should have input into
Planning criteria. - Cleco response Clecos planning criteria is in
accordance with NERC reliability standards SPP
criteria. - Comment Clarity is needed is defining an
economic study. - Cleco response Disagree. Clearly stated that
if Clecos planning criteria is not violated
which is reliability, then it is an economic
upgrade.
26FERC Order 890 Attachment K Recovery of
Planning Cost
- Cleco will recover cost for three economic
studies annually through existing rate structure. - Requestor will pay for any additional studies.
27FERC Order 890 Attachment K Recovery of
Planning Cost Comments
- Comment Parties should not be exposed to TPs
cost exceeding estimate. - Clecos response Disagree. OATT requires TCs
to pay for studies.
28Questions