Title: Hazard Scenario


1
Hazard Scenario 1
  • USS OH NO (FFG) just returned from a three-week
    pre-deployment exercise and most of the equipment
    is on fire-main back-up due to divers working
    over the side. Meanwhile 1 (of 4) fire pumps is
    OOC because of bad pump bearings. They just
    received a message from the type commander that
    the deployment has been moved up and they have to
    get underway in one week for a six-month
    deployment. Repairs must be made before getting
    underway without losing fire-main or fire
    fighting capabilities.

2
Step 1 Identify Hazards
  • Flooding
  • Loss of fire -main
  • No correct parts on hand
  • Effect on watch-bill
  • No rigging equipment
  • Lack of tools
  • QA package or drawings out of date
  • Work area not secured
  • EDO unavailable to sign tags

3
Step 2 Assess Hazards
  • RAC
  • Flooding
  • Loss of fire-main
  • No correct parts on hand
  • Effect on watch-bill
  • No rigging equipment
  • Lack of tools QA package or drawings out of date
  • Work area not secured
  • EDO unavailable to sign tags

4
Step 2 Assess Hazards
  • RAC
  • Flooding 2
  • Loss of fire-main 3
  • No correct parts on hand 4
  • Effect on watch-bill 4
  • No rigging equipment 2
  • Lack of tools 3
  • QA package or drawings out of date 3
  • Work area not secured 4
  • EDO unavailable to sign tags 4

5
Step 3 Make Risk Decisions
  • Flooding-2
  • No rigging equipment-2
  • Loss of fire-main-3
  • Lack of tools-3
  • QA package or drawings out of date-3
  • No correct parts on hand-4
  • Effect on watch-bill-4
  • Work area not secured-4
  • EDO unavailable to sign tags-4

6
Step 3 Implement Controls
  • Ensure tag out and blank flanges are in place.
  • Pre-stage before start of job, do op-test.
  • Ensure other pumps are operating and loop
    aligned.
  • Verify regular and special tools on hand before
    starting.
  • Be sure lead work center has it routed and its
    all inclusive.
  • Pull parts from supply. Check against Tech.
    Manual and inspect for damage.
  • Work with the SWO so you can work till complete.
  • Rope area off. Have Eng. watch keep an eye on it.
  • Get phone number where they are going to be.
  • Flooding-2
  • No rigging equipment (weight tested-2
  • Loss of fire-main-3
  • Lack of tools-3
  • QA package or drawings out of date-3
  • No correct parts on hand-4
  • Effect on watch-bill-4
  • Work area not secured-4
  • EDO unavailable to sign tags-4

7
Step 4 Implement Controls
  • Formal Work Package.
  • Tagout procedures
  • Heat stress program.
  • Safety brief.
  • NSTMs for rigging, PMS on rigging equip.

8
Step 5 Supervise
  • Enforce controls.
  • Monitor effectiveness of controls.
  • Evaluate and adjust controls as the situation
    changes.
  • Ensure the all personnel are familiar with
    stations.
  • Change will present new RISK.
  • If there is a change, a time critical process may
    have to be done on the spot.