Title: Diapositiva 1
1 Overview of the CTB results
Maria Jose Costa, CERN
ATLAS week 18th February, 2005
2Contents
- Motivations for the combined test beam
- Setup at H8
- Data taken
- Simulation software
- Reconstruction software
- Preliminary results
- Inner Detector
- Calorimeters
- Muons
- Combined
- Conclusions
3Motivations
- Combined test beam ATLAS slice ? allowed us to
test - Integration of all detectors in a common readout
- Detectors with final electronics and RODs
- Full DAQ chain, DCS and configurations database
- Monitoring (ROD level EF)
- Trigger studies during the 25 ns period
- HLT infrastructure reconstruction algorithms
- Integration of people!
- Offline reconstruction
- Simulation
- Analysis
- Alignment and calibrations
- Verify detector standalone performance
- ATLAS combined performance
- Improve simulation
DONE during the data taken period GREAT SUCCESS!
IN PROGRESS A lot has been done a lot needs to
be done
4Setup at H8
Muon system
ID and calorimeters
5Data taken in combined mode
- Electrons/pions
- Energy scans 1-250 GeV
- Eta scans 0-1.2
- Phi scans
- Material studies
- Al plates in front of LAr (eta 0.4)
- Al plates between Inner Detector parts (E 1-180
GeV) - Magnetic field scans
- Pions/Muons
- Energy 320 GeV, 350 GeV
- Eta scans (phi0)
- 25 ns run
- Pions/protons at 350 GeV and Muons/pions at 180
GeV - Muons (100-350 GeV)
- Magnetic field scans
- Photons 180 electron beam (30 GeV photons)
Total 90 millions events 4.6 TB Done
with evolving CTB setup
6Simulation
M.Gallas et al.
7Simulation
- The package to run the CTB simulation (CTB_G4Sim)
aims for - Preparation of the software reconstruction
- Pre-production has been done since August 2004
- Analysis of the CTB data
- Need to deal with the final setup used (which is
not unique) - The fully combined setup (from October 12th on)
is ready - Coming up for Rome release
- Infrastructure to deal with all different
configurations - Combined mode
- Photon beams
- Material studies
- Calibrations
- Run conditions infrastructure
- Use of the realistic field map (instead of
constant)
8Reconstruction
- Full reconstruction is run in Athena using the
ATLAS software - Small adaptation to reconstruction algorithms
themselves but big effort to deal with CTB
geometry.
- A package called RecExTB has been
- setup to run the CTB reconstruction.
- The reconstruction chain works for
- the different detectors for both real
- and simulated data.
- For real data needs to
- Deal with alignment and
- calibrations
- Real detectors (imperfections)
- Use Conditions database
- All this infrastructure was tested for the first
time thanks to the CTB!
- The LVL2 ID algorithms do also run in
- RecExTB.
9Preliminary results
- Preliminary results for the different subsystems
have been obtained - A few remarks
- Work on calibrations and alignment corrections is
still on going (main effort during last months) - Conditions database integration major focus
- B field map still approximate
- The software infrastructure to allow for combined
results have just started - Track to calorimeters extrapolations
- Combined tracking ID-Muons
- ?? ? No combined results yet
- ? Preliminary studies at the level of
correlations
10Inner Detector
R.Petti et al.
- Activities in the last months have been
concentrated on - Data validation ? 22.1 millions of good events
with full ID - Detector description to deal with the different
detector setups - 5 different versions for the combined period
- Check that the amount of material is as expected
- Alignment and calibrations
- SiliconTRT alignment
- T0s and R-t relations for TRT
- Dead and noisy channels
- First MC/Data comparisons are being performed
11Inner Detector
Results obtained after Alignment and TRT
calibrations (t0,R-t)
Pixels ?14?m
SCT ?24?m
TRT residuals wrt Si track Rotation
40mrad Shift y -1mm
TRT ?150?m
12Inner Detector
Momentum reconstruction
Run 2102130 9 GeV pions B 1.4 T
Preliminary
TB fitter
13LAr Calorimeter
M.Aleksa,I.Wingerter et al.
- Detailed studies are being done to
- Improve calibrations (reconstruction of the
signal peak) - Pedestal/Ramps stability and temperature
dependence - Computation of OFCs by 2 different methods to
minimize noise (need to understand timing issues) - Understand HV dependence and material effects
- Compare the performance of the different
clustering algorithms for the different kind of
particles.
14LAr Calorimeter
HV studies
- HV corrections can be applied to
- the reconstructed energy.
Preliminary
15LAr Calorimeter
First results with the photon run
16Tile Calorimeter
T.Davidek,C.Santoni et al.
- Calibrations are in very good shape since August
- Channel stability within 0.5 except 1 channel
(1 off)
Energy resolution for pions
- A method for cluster noise suppression is under
study based on signal energy - and time
17Tile Calorimeter
Response to Muons
Very good signal to noise ratio for muons
18Muons
F.Cerutti, S.Rosati et al.
- A lot of work has been done to improve the
alignment and calibrations
MDT Calibrations
- All t0s and R-t relations
- have been computed
19Muons
Alignment
- The Muon alignment system was tested successfully
to align the chambers.
- Relative alignment is in very good shape
- First results on the absolute alignment have
been obtained
20Muons
momentum
Momentum reconstruction
- Nominal energy 120 GeV
- Energy loss 12 GeV
- corresponds to 6.5m iron
- (beam dumpTileLAr)
G4 simulated data ?(s)intrinsic 40.4 ? 2.8
?m x/X0 33.7 ? 2.8
Real data ?(s)intrinsic 47.5 ? 4.4 ?m x/X0
34.1 ? 4.3
21Muons
Trigger performance during the 25 ns run
- RPC running in self-triggering mode
- The Region-of-Interest trigger information
successfully transmitted to the LVL1. - Full integration with all subdetectors using
MuonCalo trigger sent by the CTP. - Preliminary Trigger efficiency
- RPC (phi,3/4) 99.4
- TGC 98
22Combined
Track to Calorimeters
C.Bourdarios et al.
- A new tool has been created to extrapolate from
a track reconstructed by - either the ID or the Muon system to the
Calorimeters. - First tests have been done with the ID.
Preliminary
The ID-LAr alignment work can now start
23Combined
Inner Detector - Muon matching
- After extrapolating Muon tracks
- to the perigee (taking material
- effects into account)
- Comparison of the p reconstructed
- with the MDT and TRT
z Muon sytem
S.Hassani
G.Avolio
24Conclusions
- The CTB has been a very successful exercise for
all communities - Detector, TDAQ, DCS goals were accomplished
- The ATLAS reconstruction and simulation software
has also been successfully tested - The standalone reconstruction of the individual
detectors is in a good shape to start real
combined analysis. - Data has been validated and all detectors made
already clear requirements for the MC production - A new production for simulation and
reconstruction is expected for March and a second
one for April to be ready for Rome (although more
refined analysis are expected to go on) - The CTB life will continue in the combined
performance group
25Backup slides
26Reconstruction