Title: Environmental Groups
1 San Francisco-Oakland Bay Bridge
East Span Seismic Safety
Project Contractor Outreach August 13 and 14, 2002
2SFOBB New East Span August 13 and 14, 2002
Outreach event
- Welcome - my name is Sarah Picker
- Purpose
- Agenda
- Networking
- What can we accomplish?
- Sign-In Please
- Survey - day or night meetings
3Agenda Aug 13 and 14, 2002
4Purpose - Aug 13, 14
- Present information on project
- SFOBB New East Span
- encourage participation, primes meeting potential
sub-contractors and suppliers
5Welcome
- Paul Hensley
- Caltrans Chief Deputy District Director
6Project Limits
San Francisco
Oakland
Project Limits
7Yerba Buena Island
YBI/SAS Contracts
8Welcome
- James Fields
- City and County of San Francisco Human
Rights Commission
9Welcome
- Deborah Barnes
- City of Oakland
10The project team proposes the following
contracts
- YBI Building Demolition(R/W)
- a contract to remove three USCG buildings and one
state building executed as a right-of-way service
contract
11The project team proposes the following
contracts
- SAS W2 Structures
- a contract to construct the Self-Anchored
Suspension bridge land-based foundation, pier W2
12The project team proposes the following
contracts
- YBI Substation Viaduct Retrofit
- a contract to construct a replacement electrical
substation on YBI near the westbound on-ramp and
complete relatively simple bridge retrofit work
near the YBI tunnel (this work is combined due to
the close proximity of the work)
13The project team proposes the following
contracts
- SAS E2/T1 Structures
- a contract to construct the Self-Anchored
Suspension bridge in-bay foundations, the main
tower (T1) and pier E2 just to the east of YBI
14The project team proposes the following
contracts
- SAS Superstructures
- a contract to construct the tower and
superstructure of the Self-Anchored Suspension
bridge
15The project team proposes the following
contracts
- YBI Structures
- a contract to construct the temporary detour and
permanent bridges on YBI
16SAS/YBI Discretization
- What in the heck does that mean?
- Did you go to the March 12 Contractor Outreach?
- At that time, we exhibited information related to
a certain project code 04-012064 SAS/YBI
17SAS/YBI Discretization
- June 11, 2002 letter from Brian Maroney, Project
Manager, announced that we were breaking up the
project - smaller contracts that focus specific types of
construction work create more opportunities for
DBE and small business participation
18Recap of SFOBB East Span Seismic Safety Project
- already awarded
- PIDP 04-012084
- Skyway 04-012024
- Geofill 04-012054
- Archeological Excavation and Midden Site
04-012074
19Recap of SFOBB East Span Seismic Safety Project
- YBI Building Demolition(R/W)
- SAS W2 Structures 04-0120C1
- YBI Substation Viaduct Retrofit
- SAS E2/T1 Structures
- SAS Superstructures
- YBI Structures
20Recap of SFOBB East Span Seismic Safety Project
- Oakland Touchdown
- Existing bridge demolition
21SFOBB East Span
- Tonights discussions relate to the W2
construction contracts we are planning to
advertise for bid this fall and the Division of
Right of Ways service contract
22That would be the following
- SAS W2 Structures
- YBI building demolition (R/W)
23What is the schedule?
- We plan to advertise the W2 contract 04-0120C4 in
September 2002 - Why do I keep repeating the contract number?
- The R/W contract may hit the streets in late
August/early September
24Other Introductions
- Will the Potential Prime Contractors in the room
volunteer to raise their hands? - Would the DBE certified businesses raise their
hands? - Would the potential DBE or small businesses raise
their hands?
25Suggest a resource
- How Caltrans Builds Projects
- www.dot.ca.gov/hq/oppd/Proj_book/overview.pdf
26Roadway Items
Steven Hulsebus Office Chief, Toll Bridge Program
27Project Limits
San Francisco
Oakland
Project Limits
28T1/E2 foundations (04-0120E1)
Transition structure (04-0120H1)
E2
Retrofit/Substation (04-0120G1)
T1
SAS superstructure (04-0120F1)
W2 foundation (04-0120C1)
Building demolition
Yerba Buena Island
YBI/SAS Contracts
29YBI Transition Structure
W2 foundation contract
30YBI Eastbound On-Ramp
W2 foundation contract
31Self-Anchored Suspension Span (SAS)
W2 foundation contract
32Yerba Buena Island
- Varied topography -- 60 meter elevation
change - Steep slopes
- Narrow winding roads
- USCG base for 24 hour Search and Rescue unit
- Lots of underground utilities
33Environmental Constraints at YBI
Historic Structures
W2 foundation contract
W2 foundation contract
USCG Facilities
34Special Aquatic Site - Yerba Buena Island
Yerba Buena Island
35(No Transcript)
36(No Transcript)
37(No Transcript)
38(No Transcript)
39(No Transcript)
40(No Transcript)
41San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project
DBE/SBE/DVBE Outreach Program
Fall 2002
42YBI Structures
- YBI Transition Structure
- EB On-Ramp
- Viaduct Modifications (Initial)
- Viaduct Modifications (Final)
- Temporary Detour Structures
43Contract Limits
OAKLAND APPROACH
YBI TRANSITION
SUSPENSION
SKYWAY
OAKLAND GEOFILL
SKYWAY
SUSPENSION
OAKLAND APPROACH
YBI TRANSITION
Existing Bridge
44YBI Structures Quantities
- Temp Detour Structure
- Towers and Floor Beams 5,700,000 kg
- HP360 Piles 6,200 meters
- Permanent Structure
- HP Piles 14,500 meters
- W Piles 10,000 meters
- Total Concrete
- Concrete 55,000 m3
- Bar Reinforcing Steel 10,000,000 kg
45Construct W2 Foundation and Column
657 m
385 m
80 m
180 m
12 m
Elev. 160m
Pier W2
Aprox. OG along PG Line
Pier 1 Tower
Pier E2
46Earthwork Piling at W2
- Structure Excavation (W2) 15,600 m3
- Structure Backfill (Bridge) 3,640 m3
47Geologic Cross-Section
48Excavation Backfill at W2
49Structural Concrete at W2
- Structural Concrete, Bridge Footing
(SAS) 7,220 m3 - Structural Concrete, Bridge (SAS) 400 m3
- Structural Concrete, Retaining Wall 770 m3
50Pier W2 Elevation
51Structural Concrete at W2
52Bar Reinforcing Steel at W2
- Bar Reinforcing Steel (Bridge) 2,146,000
kg - Bar Reinforcing Steel (Retaining
Wall) 145,000 kg
53Pier Reinforcement at W2
54Miscellaneous Metal at W2
- Miscellaneous Metal (Bridge) 176,000 kg
55Miscellaneous Metal at W2
56YBI Structures
- YBI Transition Structure
- EB On-Ramp
- Viaduct Modifications (Initial)
- Viaduct Modifications (Final)
- Temporary Detour Structures
57YBI Structures Quantities
- Temp Detour Structure
- Towers and Floor Beams 5,700,000 kg
- HP360 Piles 6,200 meters
- Permanent Structure
- HP Piles 14,500 meters
- W Piles 10,000 meters
- Total Concrete
- Concrete 55,000 m3
- Bar Reinforcing Steel 10,000,000 kg
58Construct W2 Foundation and Column
- PSE Fall of 2002
- Advertise Winter 2002
59Earthwork Piling at W2
- Structure Excavation (W2) 15,600 m3
- Structure Backfill (Bridge) 3,640 m3
60Geologic Cross-Section
61Excavation Backfill at W2
62Structural Concrete at W2
- Structural Concrete, Bridge Footing
(SAS) 7,220 m3 - Structural Concrete,
- Bridge (SAS) 400 m3
- Structural Concrete, Retaining Wall 770 m3
63Pier W2 Elevation
64Structural Concrete at W2
65Bar Reinforcing Steel at W2
- Bar Reinforcing Steel (Bridge) 2,146,000 kg
- Bar Reinforcing Steel (Retaining
Wall) 145,000 kg
66Pier Reinforcement at W2
67Miscellaneous Metal at W2
- Miscellaneous Metal (Bridge) 176,000 kg
68Miscellaneous Metal at W2
69San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project
DBE/SBE/DVBE Outreach Program
Fall 2002
70- Civil Rights
- for information about
- Doing Business with Caltrans
- Disadvantaged Business Enterprise (DBE) Program
- Small Business Services
- Business Enterprise Program
- call (916) 324-1700 or accesshttp//www.dot.ca.gov
/hq/bep - Small Business/Disabled Veteran Business
Enterprise Services - call (916) 324-8399 or access http//www/dot.ca.go
v/bep/smallbusiness.htm
71SFOBB East Span Replacement Contracts Advertising
Award Process Overview
- Presented by
- Kris Kuhl Jeff Reeds
- August 13 14, 2002
72Purpose of this Presentation
- Provide you with information about Caltrans
contract advertising and award process for the
Pier W2 Foundation Contract of the San
Francisco/Oakland Bay Bridge East Span
Replacement Projects - Answer your questions
73Caltrans Mission
- Our mission is to improve mobility across
California - The Office Engineer contributes to Caltrans
mission by providing construction contracts that
are - Complete, biddable and buildable
- Competitively bid
- Meeting legal requirements
- Open to all licensed contractors
74Project Goals
- This is a federally-funded project
- A Disadvantaged Business Enterprise (DBE) goal
will be set for this project
75W2 Foundation Project Advertising to Award
Timeframe
Advertised Release Date 9/30/02
Advance Advertising
4 Weeks Prior to Releasing Bid Documents
Distribute Bid Documents to Bidders (9weeks))
Award
Open Bids 12/3/02
Process Award (30-60 days)
76Public Bid Opening
- Bids for this project will be opened and read in
a public forum - On Tuesday, December 3rd at 2 PM in Sacramento in
Room 100 at 1120 N Street - Immediately Following Bid Opening
- Bid amounts will be verified
- Preliminary bid results posted at (916) 654-5500
and on the Internet (http//www.dot.ca.gov/hq/esc/
oe/bidsopened.html) - Bid summaries will be mailed to all bidders
77Award Process
- Due to project size, this project may take more
than 30 days to award - Before awarding a contract, we verify
- Bid is responsive and complete
- Bid security is provided and correct
- All forms are complete and correct
- Contractor is properly licensed
- Verify Compliance with DBE requirements
- All protests addressed
78Other Requirements
- Pre-Bid Meeting -TBA
- Escrow of Bid Documents
- See Special Provisions
79Contract Execution Approval
- After Contract Award
- Contractor has 8 days to sign and return contract
for Caltrans approval - Executed Documents (returned)
- Contract signature page signed
- Payment and Performance bonds included signed
- Signed/Approved by Caltrans
80Internet Services Provided
- http//www.dot.ca.gov/hq/esc/oe/
- Information on Projects Released for Bid
- Weekly Advertisements for Bids
- Electronic copies of project plans
specifications - Bidder Assistance
- Bid Opening and Award Information
81Conclusion
- We thank you for your time and interest.
- If you have any questions or suggestions, we
would like to hear them
We look forward to doing business with you
soon!
82San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project
DBE/SBE/DVBE Outreach Program
Fall 2002