Title: PRESENTATION TO NCOP BY THE MEC LIMPOPO PROVINCIAL TREASURY
1PRESENTATION TO NCOPBY THE MEC LIMPOPO
PROVINCIAL TREASURY
__________________________________________________
__________
2INTRODUCTION
- Honourable Chairperson, I would like to thank you
for the opportunity to participate in this Public
Hearing. As I present the report on our
provincial departments spending of Conditional
Grants, I intend to do so honestly so as to
afford Members an opportunity to get an accurate
understanding of the situation as it obtains in
Limpopo. - I shall not attempt to conceal the truth
regardless of the image it may portray. To me,
this hearing is not only a platform to account on
behalf of my department and province, I also
regard this as an opportunity to benefit from the
advice that Honourable Members of the NCOP may
offer to improve our situation. I intend to
listen in on the sessions that you will have with
my counterparts from sister provinces, so as to
draw learnings from their inputs and to adopt
best practices.
3INTRODUCTION Cont
- We present this report at a time when our EXCO,
led by Premier Sello Moloto, resolved to be
impatient with officials who continue to deprive
our people of quality services despite the fact
that we avail resources to deliver on the mandate
we get from the people. The Conditional Grants is
a good example of this problem. Such behaviour is
highly unacceptable, regardless of the good and
valid sounding excuses we always get in the
glossy reports that they produce and present to
us. - I fully understand the obligation that rests on
me and my department to permanently uproot such
tendencies from within the public service. As a
Provincial Treasury, we have to ensure that the
planning and implementation of programmes in all
departments are linked and improved.
4INTRODUCTION Cont
- Honourable Members may be aware that ours is a
new department which is less than one year old.
However, we have just finalised and approved our
departments structure on the 14th September 2005
and will be filling some of the critical
vacancies as a matter of extreme urgency. These
vacancies include those for Programme Analysts
who will be experts in their fields and dedicated
to the various departments with the aim to
improve expenditure and the general management of
their budgets. - Further, we are also, through EXCO, exerting
pressure on spending agencies to ensure that they
close their capacity gaps in order to negate the
poor delivery of service and the inherent
under-spending it brings.
5INTRODUCTION Cont
- To this end, the MEC for Education for example,
agreed to review his departments structure in
order to establish a fully-fledged unit to deal
with infra-structure since it is such a critical
deliverable for that department and, as this
report will show, they always encounter
difficulty in meeting their targets. - We are convinced that this intervention together
with the appointment of Programme Analysts within
Provincial Treasury and National Treasurys
Infra-Structure Development Improvement Programme
IDIP will certainly go a long way in reversing
the current challenge of under-spending. - Honourable Chairperson, I now present the report
6Conditional Grants as at 30 June 2005
7Reasons for under spending-C Grants
- Health
- HIV/AIDS
- The underspending is as a result of the journal
for pharmaceuticals which is not yet finalised
i.e. the department appointed a service provider
to distribute medicines for the province. These
are distributed in bulk, and thereafter the
department pass journals to identify spending
specifically for HIV/AIDS drugs. - Hospital Revitalisation
- The underspending is as a result of payments that
are dependent on stages of construction and will
pick up in the second quarter - Integrated Nutrition Programme
- The underspending is as a result of agreements
not yet signed with NGOs. The department
assisted NGOs to develop business plans in the
first quarter and the plans have now been
approved.
8Reasons for under spending-C Grants
- Social Development
- HIV/AIDS
- The underspending is as a result of business
plans not approved by the National Department as
they were referred back to the provincial
department for correction in the first quarter.
The plans have been approved and spending will
pick up in the second quarter. - Social Assistance Admin Grant
- The underspending is as a result of the delay in
filling of posts identified as critical, and also
on goods and services as a result of shared
items, e.g. Stationery, telephone, water and
electricity. South African Social Security Agency
is currently housed within the Department of
Health and Social Development.
9Reasons for under spending-C Grants
- Education
- HIV/AIDS
- The underspending is as a result of HIV/AIDS
related activities that take place only during
school holidays to avoid disruption on learning
and teaching at schools. - Primary School Nutrition Programme
- The underspending is due to the delay in
submission of invoices by service providers
10Education CAPEX spending 30 June 2005
11Health CAPEX spending 30 June 2005
12Social Dev spending 30 June 2005
13Reasons for under spending-CAPEX
- Education
- Projects started later than anticipated and this
is reflected in the low expenditure patterns over
the first quarter. - The business plan was reworked and changed to
reflect change in new political priorities, e.g.
shift away from 4X4 classrooms to more
comprehensive schools, etc.
14Reasons for under spending-CAPEX
- Health
- For some of the projects, contractors were
appointed late. - For 15 of the main contracts, contractors went on
site from the 15th of July, which negatively
affected spending.
15Reasons for under spending-CAPEX
- Health
- Delays on supply of medical equipment for the
hospital projects, orders were issued in April
2005 but to due to delays in delivery, no
payments were made for these projects in the 1st
Quarter of 2005/06. - Spending on clinics (both new construction and
upgrades), health centres and mortuaries was also
hampered by delays in the documentation phase of
project implementation (e.g. tender evaluations,
etc in line with the Construction Industry
Development Board (CIDB) guidelines
16Reasons for under spending-CAPEX
- which require contractors to be registered and
categorised per amount of project that they can
undertake). - Social Development
- Disbursements for projects are made on a
percentage of completion method, i.e. payments
made per stage of construction, in the first
quarter, most projects had just started,
resulting in low expenditure
17Intervention strategies-CAPEX
- Education
- The Department of Education engages the
Department of Public Works constantly to finalise
the business plans for Education (to ensure that
by early December, PW has a finalised business
plan for implementation). - The Department of Education is undertaking
project to do a complete school register of needs
which will highlight individual school conditions
and needs, it will facilitate better planning
and channeling of resources with the greatest
need. - The Department of Education is participating in
the Infrastructure Delivery Improvement Programme
(IDIP).
18Intervention strategies-CAPEX
- IDIP is aimed at improving infrastructure
delivery within provincial departments (run by
National and Provincial Treasury, DBSA and CIDB). - It has raised awareness regarding weaknesses
around human resource issues and infrastructure
delivery systems at Education. - A capacitation plan for the Department of
Education has been prepared to address these.
19Intervention strategies-CAPEX
- Interdepartmental training workshops have also
been run on DoRA reporting requirements, project
management, etc. - Departments are also engaged monthly prior to
reporting to ensure that problems are ironed out
timeously. - Through these intervention measures, there has
been an improvement in the quality and timeliness
of reporting, there is also increasing emphasis
on the analysis of the reported information on
the part of departments (which ensures that
Treasury receives better reports).
20Intervention strategies-CAPEX
- Health Social Development
- To improve the Cash Flow for the rest of 2005/06
financial year, the Department of Health brought
forward the appointment of consultants for some
of the major projects which were scheduled to
start later in order to preempt possible delays,
e.g. for Letaba and Maphuta Malatjie Hospitals
infrastructure projects.
21Intervention strategies-CAPEX
- This will ensure that contractors are on site and
projects undertaken before the end of the
financial year. - The Department of Health Social Development
also participated in the pilot phase of IDIP
which produced a capacitation plan to address the
shortcomings around capacity which were
identified in the department, e.g. setting up a
dedicated unit for infrastructure maintenance to
look after the provincial health assets to
prevent a deterioration in their condition.
22Monitoring capacity by the department
- The Provincial Treasury receives monthly
conditional grant and capital expenditure reports
from departments - The reports are presented to the Provincial
Technical Committee on Finance, Heads of
Department and Executive Council to assess the
levels of spending - The department has plans to fill critical posts
by 1st December 2005 to enhance monitoring
capacity e.g. the appointment of programme
analysts who will deal specifically with
allocated sectors