Transcript and Presenter's Notes

Title: CrossGrid


1
CrossGrid in January 2004 Coordination matters
Michal Turala ACC Cyfronet/ INP Krakow

2
Main events of 2003
  • First Yearly CrossGrid conference
  • Santiago de Compostela, February 2003
  • first pieces of software ready
  • testbeds in good shape
  • exchange of information between applications and
    services and tools
  • good integration workshop
  • first demonstrations
  • First Across Grids conference
  • - a CrossGrid idea
  • - appreciated by the participants
  • - continuation expected

3
Main events of 2003
  • First Year review March 2003
  • Several deliverables not accepted
  • some to be corrected
  • some to be redone (QA plan, dissemination- exploi
    tation report)
  • Recommendations
  • better technical focus
  • improve managerial structures
  • reduce number of deliverables
  • consider moving to GT3
  • -gt additional review on 18 June 2003

4
Main events of 2003
  • Preparations for the June review
  • CG meeting in Cracow, 20-21 May 2003
  • Steering group Technical Board
  • CG response to comments and recommendations
  • review of technical activities
  • review of CG architecture preparing responses to
    Brussels
  • new QA plan (QE, quality indicators)
  • new dissemination-exploitation report
  • .
  • Documents for Brussels
  • CG response to comments and recommendation
  • CG managerial structures
  • CG technical focus

5
Main events of 2003
  • Additional CrossGrid review, 18 June 2003
  • Project on track
  • Quality of the deliverables improved
    deliverables of M1 M15 accepted
  • Recommendations
  • technology-application matrix to be completed
  • improve QA (implement QE and quality indicators)
  • only 10 deliverables per year
  • style of deliverables to be changed
  • clarify responsibilities of the managerial
    bodies
  • appoint an overall integration leader
  • prepare a cooperation agreement with Condor

6
Main events of 2003
  • CrossGrid integration workshop, Poznan, July 2003
  • Testbeds stable on EDG1.4
  • First real integration of CrossGrid applications
    and CrossGrid grid services and tools - feedback
    received
  • Comments
  • very useful meeting
  • good progress in several areas
  • catalyzing impact of the CrossGrid migrating
    desktop and portal on the integration
  • but
  • gridification demonstrated in few cases only
  • interactivity not much addressed yet
  • not enough time to make sufficient step forward

7
Main events of 2003
  • Towards the CrossGrid amendment
  • Motivation
  • - technical
  • merging of some technical tasks
  • managerial
  • reduced list of deliverables
  • augmenting of CG managerial structures
    (Technical Board, QA engineer)
  • contractual
  • changing the category of staff recruited
  • adjustment to travel budgets
  • Schedule
  • new Technical Annex and CPFs sent to Brussels in
    November
  • feedback from Brussels received in December 2003
  • finalisation with all documents in January 2004

8
Cyprus CrossGrid meeting
  • Integration meeting
  • direct contacts and interactions are very
    important, however 2-3 days meeting will not
    solve all the problems
  • we have to learn how to work on a distance (last
    months progress was not fully satisfactory)
  • Reviewing the status of the project and preparing
    for the second CrossGrid Review
  • prototype demos give us the best information on
    the progress of each task and their integration
  • it is necessary to make a critical assessment of
    our work, before publicising the results
  • it is important to prepare good agenda for the
    second review
  • the awareness of the tough schedule in the
    coming weeks is essential to meet the deadlines

9
Cyprus CrossGrid meeting
  • Preparation for the Second CrossGrid Review
  • Deliverables
  • - M23 - D5.3.13
  • - M24 - technical deliverables D1.4, D2.5,
    D3.5, D4.6, D5.2.6
  • - managerial deliverables D5.1.8 (QR),
    D5.1.14 (YR)
  • Schedule
  • - Review at FZK on 16 March 2004
  • CrossGrid meeting at FZK on 14-15 March
  • Documents to Brussels
  • end of February 2004
  • Internal review of the Deliverables
  • 10 24 February 2004
  • Technical deliverables ready 10 February 2004
    !!
  • Managerial deliverables ready 20 February 2004
    !

10
Cyprus CrossGrid meeting
  • Preparation for the Second CrossGrid Review
  • Agenda
  • CG internal meeting at FZK on 14-15 March 2004
  • agenda for 16 March 2004
  • overview of the managerial and dissemination
    matters
  • overview of the CrossGrid technical progress
  • demos
  • (flood predictions.)
  • CrossGrid team
  • WP leaders (overview talks and discussions)
  • A. Hoekstra, H. Kornmayer, N. Meyer, J. Marco,
    M. Bubak, M. Turala
  • technical team (demos)
  • FZK staff complemented by selected collegues
  • selection of demos at the tomorrows TB meeting

11
Cyprus CrossGrid meeting
  • Plans for integration meetings, a third
    CrossGrid conference and the final Review
  • Integration meetings in Dagstuhl and Lisbon
  • - .
  • Final CrossGrid conference and Review in
    Amstardam
  • -
  • to be discussed at the CB meeting

12
Across Grids Conference
  • Second Across Grids Conference
  • seed planted by CrossGrid
  • organised by Cyprus University, CrossGrid,
    GridStart and IST Brussels office
  • presentations on European grid activities
  • - but also overviews of grid directions
  • dissemination of grid activities
  • technical brochures, posters and demos
  • proceedings expected in summer
  • Second IST Grid Concertation meeting and
    GridStart Technical Working Groups
  • exchange of information
  • explore synergies between different EU grid
    projects
  • plan for the future (GGF, 6FP, etc.)