Title: COCOMO II


1
COCOMO II
Dr. Ray Madachy madachy_at_usc.edu CSCI 510
September 30, 2002October 2, 2002
2
Agenda
  • COCOMO introduction
  • Basic estimation formulas
  • Cost factors
  • Reuse model
  • Sizing
  • USC COCOMO tool demo
  • Data collection

3
Supplemental Handouts
  • Software Cost Estimation with COCOMO II
  • Estimation Form

4
Software Cost Estimation Methods
  • Cost estimation prediction of both the
    person-effort and elapsed time of a project
  • Methods
  • Algorithmic
  • Expert judgement
  • Estimation by analogy
  • Parkinsonian
  • Best approach is a combination of methods
  • compare and iterate estimates, reconcile
    differences
  • COCOMO is the most widely used, thoroughly
    documented and calibrated cost model
  • Price-to-win
  • Top-down
  • Bottom-up

5
COCOMO Background
  • COCOMO - the COnstructive COst MOdel
  • COCOMO II is the update to COCOMO 1981
  • ongoing research with annual calibrations made
    available
  • Originally developed by Dr. Barry Boehm and
    published in 1981 book Software Engineering
    Economics
  • COCOMO II described in new book Software Cost
    Estimation with COCOMO II
  • COCOMO can be used as a framework for cost
    estimation and related activities

6
Software Estimation Accuracy
4x
  • Effect of uncertaintiesover time

2x
Relative Size Range
x
0.5x
Initial Operating Capability
OperationalConcept
Life Cycle Objectives
Life Cycle Architecture
0.25x
Feasibility
Plans/Rqts.
Design
Develop and Test
Phases and Milestones
7
COCOMO Black Box Model
product size estimate
development, maintenance cost and schedule
estimates
product, process, platform, and personnel
attributes
COCOMO II
reuse, maintenance, and increment parameters
cost, schedule distribution by phase, activity,
increment
organizational project data
recalibration to organizational data
8
Major COCOMO II Features
  • Multi-model coverage of different development
    sectors
  • Variable-granularity cost model inputs
  • Flexibility in size inputs
  • SLOCS
  • function points
  • application points
  • other (use cases ...)
  • Range vs. point estimates per funnel chart

9
COCOMO Uses for Software Decision Making
  • Making investment decisions and business-case
    analyses
  • Setting project budgets and schedules
  • Performing tradeoff analyses
  • Cost risk management
  • Development vs. reuse decisions
  • Legacy software phaseout decisions
  • Software reuse and product line decisions
  • Process improvement decisions

10
Productivity Ranges
  • COCOMO provides natural framework to identify
    high leverage productivity improvement factors
    and estimate their payoffs.

11
COCOMO Submodels
  • Applications Composition involves rapid
    development or prototyping efforts to resolve
    potential high-risk issues such as user
    interfaces, software/system interaction,
    performance, or technology maturity. Its sized
    with application points (weighted screen
    elements, reports and 3GL modules).
  • The Early Design model involves exploration of
    alternative software/system architectures and
    concepts of operation using function points and a
    course-grained set of 7 cost drivers.
  • The Post-Architecture model involves the actual
    development and maintenance of a software product
    using source instructions and / or function
    points for sizing, with modifiers for reuse and
    software breakage a set of 17 multiplicative
    cost drivers and a set of 5 factors determining
    the project's scaling exponent.

12
Agenda
  • COCOMO introduction
  • Basic estimation formulas
  • Cost factors
  • Reuse model
  • Sizing
  • USC COCOMO tool demo
  • Data collection

13
COCOMO Effort Formulation
  • of cost drivers
  • Effort (person-months) A (Size)B P EMi
  • i1
  • Where
  • A is a constant derived from historical project
    data (currently A 2.94 in COCOMOII.2000)
  • Size is in KSLOC (thousand source lines of code),
    or converted from function points or object
    points
  • B is an exponent for the diseconomy of scale
    dependent on five additive scale drivers
    according to b .91 .01SSFi,where SFi is a
    weighting factor for ith scale driver
  • EMi is the effort multiplier for the ith cost
    driver. The geometric product results in an
    overall effort adjustment factor to the nominal
    effort.
  • Automated translation effects are not included

14
Diseconomy of Scale
  • Nonlinear relationship when exponent gt 1

15
COCOMO Schedule Formulation
  • Where
  • Schedule is the calendar time in months from the
    requirements baseline to acceptance
  • C is a constant derived from historical project
    data (currently C 3.67 in COCOMOII.2000)
  • Effort is the estimated person-months excluding
    the SCED effort multiplier
  • B is the sum of project scale factors
  • SCED is the compression / expansion percentage
    in the SCED cost driver
  • This is the COCOMOII.2000 calibration
  • Formula can vary to reflect process models for
    reusable and COTS software, and the effects of
    application composition capabilities.

Schedule (months) C (Effort)(.330.2(B-1.01))
x SCED/100
16
Coverage of Different Processes
  • COCOMO II provides a framework for tailoring the
    model to any desired process
  • Original COCOMO was predicated on the waterfall
    process
  • single-pass, sequential progression of
    requirements, design, code, test
  • Modern processes are concurrent, iterative,
    incremental, and cyclic
  • e.g. Rational Unified Process (RUP), the USC
    Model-Based Architecting and Software Engineering
    (MBASE) process
  • Effort and schedule are distributed among
    different phases and activities per work
    breakdown structure of chosen process

17
Common Process Anchor Points
  • Anchor points are common process milestones
    around which cost and schedule budgets are
    organized
  • COCOMO II submodels address different development
    stages anchored by these generic milestones
  • Life Cycle Objectives (LCO)
  • inception establishing a sound business case
  • Life Cycle Architecture (LCA)
  • elaboration commit to a single architecture and
    elaborate it to cover all major risk sources
  • Initial Operational Capability (IOC)
  • construction commit to transition and support
    operations

18
MBASE Phase Distributions
  • see COCOMO II book for complete phase/activity
    distributions

Schedule
Effort
Phase
12.5
6
Inception
37.5
24
Elaboration
62.5
76
Construction
12.5
12
Transition
100
100
COCOMO Total
125
118
Project Total
19
Waterfall Phase Distributions
Schedule
Effort
Phase
20
7
Plans rqts
26
17
Product Design
48
58
Programming
Integration Test
25
26
12.5
12
Transition
100
100
COCOMO Total
125
119
Project Total
20
COCOMO II Output Ranges
  • COCOMO II provides one standard deviation
    optimistic and pessimistic estimates.
  • Reflect sources of input uncertainties per funnel
    chart.
  • Apply to effort or schedule for all of the stage
    models.
  • Represent 80 confidence limits below optimistic
    or pessimistic estimates 10 of the time.

21
COCOMO Tailoring and Enhancements
  • Calibrate effort equations to organizational
    experience
  • USC COCOMO has a calibration capability
  • Consolidate or eliminate redundant cost driver
    attributes
  • Add cost drivers applicable to your organization
  • Account for systems engineering, hardware and
    software integration

22
Agenda
  • COCOMO introduction
  • Basic estimation formulas
  • Cost factors
  • Reuse model
  • Sizing
  • USC COCOMO tool demo
  • Data collection

23
Cost Factors
  • Significant factors of development cost
  • scale drivers are sources of exponential effort
    variation
  • cost drivers are sources of linear effort
    variation
  • product, platform, personnel and project
    attributes
  • effort multipliers associated with cost driver
    ratings
  • Defined to be as objective as possible
  • Each factor is rated between very low and very
    high per rating guidelines
  • relevant effort multipliers adjust the cost up or
    down

24
Scale Drivers
  • Precedentedness (PREC)
  • Degree to which system is new and past experience
    applies
  • Development Flexibility (FLEX)
  • Need to conform with specified requirements
  • Architecture/Risk Resolution (RESL)
  • Degree of design thoroughness and risk
    elimination
  • Team Cohesion (TEAM)
  • Need to synchronize stakeholders and minimize
    conflict
  • Process Maturity (PMAT)
  • SEI CMM process maturity rating

25
Cost Drivers
  • Product Factors
  • Reliability (RELY)
  • Data (DATA)
  • Complexity (CPLX)
  • Reusability (RUSE)
  • Documentation (DOCU)
  • Platform Factors
  • Time constraint (TIME)
  • Storage constraint (STOR)
  • Platform volatility (PVOL)
  • Personnel factors
  • Analyst capability (ACAP)
  • Program capability (PCAP)
  • Applications experience (APEX)
  • Platform experience (PLEX)
  • Language and tool experience (LTEX)
  • Personnel continuity (PCON)
  • Project Factors
  • Software tools (TOOL)
  • Multisite development (SITE)
  • Required schedule (SCED)

26
Example Cost Driver - Required Software
Reliability (RELY)
  • Measures the extent to which the software must
    perform its intended function over a period of
    time.
  • Ask what is the effect of a software failure?

27
Example Effort Multiplier Values for RELY
1.39
1.15
Very High
High
Very Low
Nominal
Low
1.0
Slight Inconvenience
Low, Easily Recoverable Losses
High Financial Loss
Moderate, Easily Recoverable Losses
Risk to Human Life
0.88
0.75
  • E.g. a highly reliable system costs 39 more than
    a nominally reliable system 1.39/1.01.39)
  • or a highly reliable system costs 85 more than a
    very low reliability system (1.39/.751.85)

28
Scale Factors
  • Sum scale factors Wi across all of the factors to
    determine a scale exponent, B, using B .91
    .01 S Wi

29
Precedentedness (PREC) and Development
Flexibility (FLEX)
  • Elaboration of the PREC and FLEX rating scales

30
Architecture / Risk Resolution (RESL)
  • Use a subjective weighted average of the
    characteristics

31
Team Cohesion (TEAM)
  • Use a subjective weighted average of the
    characteristics to account for project turbulence
    and entropy due to difficulties in synchronizing
    the project's stakeholders.
  • Stakeholders include users, customers,
    developers, maintainers, interfacers, and others

32
Process Maturity (PMAT)
  • Two methods based on the Software Engineering
    Institute's Capability Maturity Model (CMM)
  • Method 1 Overall Maturity Level (CMM Level 1
    through 5)
  • Method 2 Key Process Areas(see next slide)

33
Key Process Areas
  • Decide the percentage of compliance for each of
    the KPAs as determined by a judgement-based
    averaging across the goals for all 18 Key Process
    Areas.

34
Cost Drivers
  • Product Factors
  • Platform Factors
  • Personnel Factors
  • Project Factors

35
Product Factors
  • Required Software Reliability (RELY)
  • Measures the extent to which the software must
    perform its intended function over a period of
    time. Ask what is the effect of a software
    failure

36
Product Factors contd
  • Data Base Size (DATA)
  • Captures the effect large data requirements have
    on development to generate test data that will be
    used to exercise the program.
  • Calculate the data/program size ratio (D/P)

37
Product Factors contd
  • Product Complexity (CPLX)
  • Complexity is divided into five areas
  • control operations,
  • computational operations,
  • device-dependent operations,
  • data management operations, and
  • user interface management operations.
  • Select the area or combination of areas that
    characterize the product or a sub-system of the
    product.
  • See the module complexity table, next several
    slides

38
Product Factors contd
  • Module Complexity Ratings vs. Type of Module
  • Use a subjective weighted average of the
    attributes, weighted by their relative product
    importance.

39
Product Factors contd
  • Module Complexity Ratings vs. Type of Module
  • Use a subjective weighted average of the
    attributes, weighted by their relative product
    importance.

40
Product Factors contd
  • Required Reusability (RUSE)
  • Accounts for the additional effort needed to
    construct components intended for reuse.
  • Documentation match to life-cycle needs (DOCU)
  • What is the suitability of the project's
    documentation to its life-cycle needs.

41
Platform Factors
  • Platform
  • Refers to the target-machine complex of hardware
    and infrastructure software (previously called
    the virtual machine).
  • Execution Time Constraint (TIME)
  • Measures the constraint imposed upon a system in
    terms of the percentage of available execution
    time expected to be used by the system.

42
Platform Factors contd
  • Main Storage Constraint (STOR)
  • Measures the degree of main storage constraint
    imposed on a software system or subsystem.
  • Platform Volatility (PVOL)
  • Assesses the volatility of the platform (the
    complex of hardware and software the software
    product calls on to perform its tasks).

43
Personnel Factors
  • Analyst Capability (ACAP)
  • Analysts work on requirements, high level design
    and detailed design. Consider analysis and design
    ability, efficiency and thoroughness, and the
    ability to communicate and cooperate.
  • Programmer Capability (PCAP)
  • Evaluate the capability of the programmers as a
    team rather than as individuals. Consider
    ability, efficiency and thoroughness, and the
    ability to communicate and cooperate.

44
Personnel Factors contd
  • Applications Experience (AEXP)
  • Assess the project team's equivalent level of
    experience with this type of application.
  • Platform Experience (PEXP)
  • Assess the project team's equivalent level of
    experience with this platform including the OS,
    graphical user interface, database, networking,
    and distributed middleware.

45
Personnel Factors contd
  • Language and Tool Experience (LTEX)
  • Measures the level of programming language and
    software tool experience of the project team.
  • Personnel Continuity (PCON)
  • The scale for PCON is in terms of the project's
    annual personnel turnover.

46
Project Factors
  • Use of Software Tools (TOOL)
  • Assess the usage of software tools used to
    develop the product in terms of their
    capabilities and maturity.

47
Project Factors contd
  • Multisite Development (SITE)
  • Assess and average two factors site collocation
    and communication support.
  • Required Development Schedule (SCED)
  • Measure the imposed schedule constraint in terms
    of the percentage of schedule stretch-out or
    acceleration with respect to a nominal schedule
    for the project.

48
Cost Factor Rating
  • Whenever an assessment of a cost driver is
    between the rating levels
  • always round to the Nominal rating
  • e.g. if a cost driver rating is between High and
    Very High, then select High.

49
Cost Driver Rating Level Summary
50
Cost Driver Rating Level Summary contd
51
Agenda
  • COCOMO introduction
  • Basic estimation formulas
  • Cost factors
  • Reuse model
  • Sizing
  • USC COCOMO tool demo
  • Data collection

52
Reused and Modified Software
  • Effort for adapted software (reused or modified)
    is not the same as for new software.
  • Approach convert adapted software into
    equivalent size of new software.

53
Nonlinear Reuse Effects
  • The reuse cost function does not go through the
    origin due to a cost of about 5 for assessing,
    selecting, and assimilating the reusable
    component.
  • Small modifications generate disproportionately
    large costs primarily due the cost of
    understanding the software to be modified, and
    the relative cost of interface checking.

54
COCOMO Reuse Model
  • A nonlinear estimation model to convert adapted
    (reused or modified) software into equivalent
    size of new software

55
COCOMO Reuse Model contd
  • ASLOC - Adapted Source Lines of Code
  • ESLOC - Equivalent Source Lines of Code
  • AAF - Adaptation Adjustment Factor
  • DM - Percent Design Modified. The percentage of
    the adapted software's design which is modified
    in order to adapt it to the new objectives and
    environment.
  • CM - Percent Code Modified. The percentage of the
    adapted software's code which is modified in
    order to adapt it to the new objectives and
    environment.
  • IM - Percent of Integration Required for Modified
    Software. The percentage of effort required to
    integrate the adapted software into an overall
    product and to test the resulting product as
    compared to the normal amount of integration and
    test effort for software of comparable size.
  • AA - Assessment and Assimilation effort needed to
    determine whether a fully-reused software module
    is appropriate to the application, and to
    integrate its description into the overall
    product description. See table.
  • SU - Software Understanding. Effort increment as
    a percentage. Only used when code is modified
    (zero when DM0 and CM0). See table.
  • UNFM - Unfamiliarity. The programmer's relative
    unfamiliarity with the software which is applied
    multiplicatively to the software understanding
    effort increment (0-1).

56
Assessment and Assimilation Increment (AA)
57
Software Understanding Increment (SU)
  • Take the subjective average of the three
    categories.
  • Do not use SU if the component is being used
    unmodified (DM0 and CM 0).

58
Programmer Unfamiliarity (UNFM)
  • Only applies to modified software

59
Commercial Off-the-Shelf (COTS) Software
  • Current best approach is to treat as reuse
  • A COTS cost model is under development
  • Calculate effective size from external interface
    files and breakage
  • Have identified candidate COTS cost drivers

60
Reuse Parameter Guidelines
61
Agenda
  • COCOMO introduction
  • Basic estimation formulas
  • Cost factors
  • Reuse model
  • Sizing
  • USC COCOMO tool demo
  • Data collection

62
Lines of Code
  • Source Lines of Code (SLOCs) logical source
    statements
  • Logical source statements data declarations
    executable statements
  • Executable statements cause runtime actions
  • Declaration statements are nonexecutable
    statements that affect an assembler's or
    compiler's interpretation of other program
    elements
  • Codecount tool available on USC web site

63
Lines of Code Counting Rules
  • Standard definition for counting lines
  • Based on SEI definition checklist from
    CMU/SEI-92-TR-20
  • Modified for COCOMO II
  • When a line or statement contains more than one
    type, classify it as the type with the highest
    precedence. Order of precedence is in ascending
    order

64
Lines of Code Counting Rules contd
  • (See COCOMO II book for remaining details)

65
Counting with Function Points
  • Used in both the Early Design and the
    Post-Architecture models.
  • Based on the amount of functionality in a
    software product and project factors using
    information available early in the project life
    cycle.
  • Quantify the information processing functionality
    with the following user function types

66
Counting with Function Points contd
  • External Input (Inputs)
  • Count each unique user data or user control input
    type that both
  • Enters the external boundary of the software
    system being measured
  • Adds or changes data in a logical internal file.
  • External Output (Outputs)
  • Count each unique user data or control output
    type that leaves the external boundary of the
    software system being measured.

67
Counting with Function Points contd
  • Internal Logical File (Files)
  • Count each major logical group of user data or
    control information in the software system as a
    logical internal file type. Include each logical
    file (e.g., each logical group of data) that is
    generated, used, or maintained by the software
    system.
  • External Interface Files (Interfaces)
  • Files passed or shared between software systems
    should be counted as external interface file
    types within each system.

68
Counting with Function Points contd
  • External Inquiry (Queries)
  • Count each unique input-output combination, where
    an input causes and generates an immediate
    output, as an external inquiry type.
  • Each instance of the user function types is then
    classified by complexity level. The complexity
    levels determine a set of weights, which are
    applied to their corresponding function counts to
    determine the Unadjusted Function Points
    quantity.

69
Counting with Function Points contd
  • The usual Function Point procedure involves
    assessing the degree of influence of fourteen
    application characteristics on the software
    project.
  • The contributions of these characteristics are
    inconsistent with COCOMO experience, so COCOMO II
    uses Unadjusted Function Points for sizing.

70
Unadjusted Function Points Counting Procedure
  • Step 1 - Determine function counts by type.
  • The unadjusted function counts should be counted
    by a lead technical person based on information
    in the software requirements and design
    documents.
  • The number of each of the five user function
    types should be counted
  • Internal Logical File (ILF)
  • Note The word file refers to a logically related
    group of data and not the physical implementation
    of those groups of data.
  • External Interface File (EIF)
  • External Input (EI)
  • External Output (EO)
  • External Inquiry (EQ))

71
Unadjusted Function Points Counting Procedure
contd
  • Step 2 - Determine complexity-level function
    counts.
  • Classify each function count into Low, Average
    and High complexity levels depending on the
    number of data element types contained and the
    number of file types referenced. Use the
    following scheme

72
Unadjusted Function Points Counting Procedure
contd
  • Step 3 - Apply complexity weights.
  • Weight the number in each cell using the
    following scheme. The weights reflect the
    relative value of the function to the user.
  • Step 4 - Compute Unadjusted Function Points.
  • Add all the weighted functions counts to get one
    number, the Unadjusted Function Points.

73
Agenda
  • COCOMO introduction
  • Basic estimation formulas
  • Cost factors
  • Reuse model
  • Sizing
  • USC COCOMO tool demo
  • Data collection

74
USC COCOMO Demo
75
Agenda
  • COCOMO introduction
  • Basic estimation formulas
  • Cost factors
  • Reuse model
  • Sizing
  • USC COCOMO tool demo
  • Data collection

76
Cost Driver Ratings Profile
  • Need to rate cost drivers in a consistent and
    objective fashion within an organization.
  • Cost driver ratings profile
  • Graphical depiction of historical ratings to be
    used as a reference baseline to assist in rating
    new projects
  • Used in conjunction with estimating tools to
    gauge new projects against past ones objectively

77
Example Cost Driver Ratings Profile
78
Techniques to Generate Cost Driver Ratings Profile
  • Single person
  • Time efficient, but may impose bias and person
    may be unfamiliar with all projects
  • Group
  • Converge ratings in a single meeting (dominant
    individual problem)
  • Wideband Delphi technique (longer calendar time,
    but minimizes biases). See Software Engineering
    Economics, p. 335

79
COCOMO Dataset Cost Metrics
  • Size (SLOCS, function points)
  • Effort (Person-hours)
  • Schedule (Months)
  • Cost drivers
  • Scale drivers
  • Reuse parameters

80
Recommended Project Cost Data
  • For each project, report the following at the end
    of each month and for each release
  • SIZE
  • Provide total system size developed to date, and
    report new code size and reused / modified code
    size separately. This can be at a project level
    or lower level as the data supports and is
    reasonable. For languages not supported by tools
    such as assembly code, report the number of
    physical lines separately for each language.
  • EFFORT
  • Provide cumulative staff-hours spent on software
    development per project at the same granularity
    as the size components.

81
Recommended Project Cost Data contd
  • COST DRIVERS AND SCALE DRIVERS
  • For each reported size component, supply the cost
    driver ratings for product, platform, personnel
    and project attributes. For each reported size
    component, supply scale driver ratings.
  • REUSE PARAMETERS
  • For each component of reused/modified code,
    supply reuse parameters AA, SU, UNFM, DM, CM and
    IM.
  • See Appendix C in COCOMO II book for additional
    data items
  • Post-mortem reports are highly recommended

82
Effort Staff-Hours Definition
  • Standard definition
  • Based on SEI definition checklist form
    CMU/SEI-92-TR-21
  • Modified for COCOMO II
  • Does not include unpaid overtime, production and
    deployment activities, customer training
    activities
  • Includes all personnel except level 3 or higher
    software management (i.e. directors or above who
    timeshare among projects)
  • Person-month is defined as 152 hours

83
Further Information
  • B. Boehm, C. Abts, W. Brown, S. Chulani, B.
    Clark, E. Horowitz, R. Madachy, D. Reifer, B.
    Steece, Software Cost Estimation with COCOMO II,
    Prentice-Hall, 2000
  • B. Boehm, Software Engineering Economics.
    Englewood Cliffs, NJ, Prentice-Hall, 1981
  • Main COCOMO website at USC http//sunset.usc.edu/
    research/COCOMOII
  • COCOMO information at USC (213) 740-6470
  • COCOMO email cocomo-info_at_sunset.usc.edu