Title: INSURV PREPARATION


1
INSURV PREPARATION
  • HOW TO PREPARE FOR INSURV (Submarine)

03/22/07
2
RESOURCES
  • INSURV WEB SITE
  • http//www.spawar.navy.mil/fleet/insurv/
  • Submarines who have recently completed INSURV
  • Squadron OPS or INSURV POC can provide local
    assistance
  • INSURVINST 4730.2 Series
  • Posted on Web Site

3
WHAT TO EXPECT
  • Letter 60-90 days prior to the scheduled
    inspection
  • INSURV Recorder (your primary POC on the INSURV
    Board) identified
  • Messages 45-60 days prior to the inspection
  • Assist Request
  • INSURV Board Clearance Information
  • Services Request

4
Ships INSURV Coordinator
  • Develop inspection schedule of events (SOE) based
    on INSURVINST 4730.2, App. A, forward to INSURV
    recorder (minimum 1 week prior to inspection)
  • Track accomplishment of items in services request
    message
  • Gather information required by Chapter 1 of
    INSURVINST 4730.2
  • Address ships concerns to INSURV board through
    INSURV recorder

5
Evolutions/Procedures
  • S/F operates ships equipment.
  • INSURV does not provide procedures S/F will use
    only approved procedures during the conduct of
    any inspection. (e.g. - SUBMEPP Maintenance
    Standards, PMS, SSMs, Technical Manuals,
    Operating Manuals, and SPAWAR Test Procedures)
  • Prepare to conduct as many evolutions as possible
    in parallel and early.
  • May not desire to see the entire procedure
    performed.

6
Auxiliaries Preparations(Refer of INSURVINST
4730.2E, Chapter 2)
  • Assemble information package IAW 2-1, indicating
    location of documents not in package.
  • Evaluate Inspection Guide
  • Download Auxiliary Equipment Inspection Guide
    from web site
  • Review PMS MRCs called out for S/F performance
    and prepare necessary tag outs
  • Coordinate evolution schedule with Ships INSURV
    Coordinator
  • AX Inspector will request to meet with DCA, ALPO
    following Inbrief on first day of inspection.

7
Electrical Preparations (Refer to INSURVINST
4730.2E, Chapter 3)
  • Assemble information package IAW 3-1, indicating
    location of documents not in package.
  • Contact the EL Inspector as early as practical to
    discuss preparations for the inspection. Key to
    thermal imaging is permission to conduct
    inspections in the vicinity of energized gear
    (not-to-break-the-plane).
  • EL Inspector will provide you with a separate
    detailed equipment listing for inspection/thermal
    imaging (contact electrical inspector to get
    advanced copy).
  • EL Inspector will request to meet with EA and
    ELPO following Inbrief first day of inspection.

8
Electrical Preparations Sample List
9
Main Propulsion/Reactors Preparations (Refer to
INSURVINST 4730.2E, Chapter 4)
  • Due to security concerns, ENG contact the MP/RX
    Inspector as early as practical to discuss
    preparations for the inspection.
  • Assemble info package IAW 4-1, indicating
    location of documents if not included in package.
  • Coordinate and arrange to conduct demonstrations
    and evolutions discussed in 4-5 and following.
  • IG provides additional details on demos.
  • MP/RX Inspector will request to meet with ENG,
    EDMC and MLPO following Inbrief on first day of
    inspection.

10
NAV/OPS
  • Contact the NV/OP Inspector as early as practical
    to discuss preparations for the inspection.
  • Some PMS is required to be completed ahead of the
    inspection and results provided on arrival. Plan
    early to get it done. Examples include
  • RF Gain Test, Shroud Test, EMI Surveys, Sail
    Inspections.
  • NV/OP Inspector will request to meet with ANAV,
    NODEA, Comm LPO following Inbrief on first day of
    inspection.

11
Operations Preparations (Overview of INSURVINST
4730.2E, Chapter 5)
  • Assemble information package IAW 5-1, indicating
    location of documents if not included in package.
  • Evaluate Inspection Guide
  • Download Navigation/Operations Inspection Guide
    from website.
  • Review procedures for the items listed to be
    inspected.
  • Coordinate evolution schedule with Ships INSURV
    Coordinator.

12
Navigation/IC Preparations (Overview of
INSURVINST 4730.2E, Chapter 6)
  • Assemble information package IAW 6-1, indicating
    location of documents if not included in package.
  • Evaluate Inspection Guide
  • Download Navigation/Operations Inspection Guide
    from website.
  • Review procedures for the items listed to be
    inspected.
  • Coordinate evolution schedule with Ships INSURV
    Coordinator.
  • Ensure safety tags and WAF for Sail Inspection
    are prepared prior to RTP.

13
Weapons/Deck Preparations (Overview of INSURVINST
4730.2E, Chapter 7)
  • Assemble information package IAW 7-1, indicating
    location of documents if not included in package
    (i.e. Diver AEL in Dive Binder).
  • Identify any demos for which approved procedures
    do not exist to INSURV POC.
  • Evaluate Inspection Guide
  • Download applicable Weapons and Deck Inspection
    Guides from website
  • Review PMS MRCs called out for SF performance
    and prepare necessary tag outs
  • Coordinate evolution schedule with Ships INSURV
    Coordinator
  • WP/DK/IS Inspector will request to meet with WEPS
    or AWEPS, Div Os, WDEA, STLPO, FTLPO, TMLPO, 1st
    LT, Deck LPO, and LAN Administrator following
    Inbrief on first day of inspection.

14
Damage Control Preparations(Overview of
INSURVINST 4730.2E, Chapter 8)
  • Assemble information package IAW 8-1.
  • Ensure materials listed in 8-2 are available.
  • Download DC Inspection Guide from the website and
    evaluate.
  • Ensure DCPO is off the watchbill for duration of
    the inspection.
  • Senior Member will request to meet with DCPO
    following Inbrief on first day of inspection.

15
Habitability Preparations (Overview of INSURVINST
4730.2E, Chapter 9)
  • Assemble information package IAW 9-1.
  • Download Habitability Inspection Guide from the
    website and evaluate.
  • Senior Member will request to meet with COB,
    Ships Diving Officer as soon as practical
    following Inbrief on first day of inspection.

16
Supply Preparations (Overview of INSURVINST
4730.2E, Chapter 10)
  • Download Supply Inspection Guide from the website
    and evaluate.
  • Conduct PMS on Galley APC system and Grease
    Interceptor Hood and related equipment.
  • Conduct PMS testing dual High-limit safety
    thermostat operation on Galley Deep Fat Fryer.
  • Ensure that the temperature controls on the
    Ovens, Griddles, Deep Fat Fryers, Electric Water
    Heater, Dishwaters and Chill Boxes are
    calibrated.
  • Have discrepancies corrected and be prepared to
    be inspected beginning of day 1.

17
Medical Preparations (Overview of INSURVINST
4730.2E, Chapter 11)
  • Download Medical Inspection Guide from the
    website and evaluate.
  • Test Bio-refeer high low temp and loss of power
    alarm (SSBN/SSGN).
  • Ensure all equipment on AMAL is inspection ready.
  • Document completion of Ship Pesticide Control
    Management course, and maintain Deratization
    Certification.

18
Occupational Safety and Health Preparations
(Overview of INSURVINST 4730.2E, Chapter 12)
  • Download OH Inspection Guide from the website and
    evaluate.
  • Ensure required personnel training and NAVOSH
    program evaluations are documented. For training
    materials go to www.safetycenter.navy.mil.
  • Medical and Safety should review ships
    Industrial Hygiene Surveys.
  • Inspect general work shop equipment for proper
    machine guarding.

19
Environmental Protection Preparations (Overview
of INSURVINST 4730.2E, Chapter 13)
  • Download EP Inspection Guide from the website and
    evaluate.
  • Ships Afloat Environmental Protection
    Coordinator must have completed the AEPC course
    and should be very knowledgeable of the INSURV
    environmental checklist.
  • All hands are required to have completed
    environmental awareness training.
  • Controllers and overboard discharge valves for
    the oily waste/water pumps should be labeled
    Discharge of oil prohibited.

20
NAVOSH/ENVIRONMENTAL PROTECTION INSPECTOR
  • The NEP Inspector will request to meet with the
    MDR, Safety Officer, Supply Officer, SKLPO and
    CSLPO following the Inbrief on the first day of
    the inspection.

21
3M Coordinator
  • Provide a CSMP download to INSURV board upon
    arrival (coordinate with INSURV recorder for
    proper format)
  • Upon conclusion of the inspection, a disk with
    the inspection results will be provided to upload
    into the ships 3M system

22
Finally
  • Early liaison with the submarine board through
    the INSURV Recorder has proven invaluable.

23
INSURV POC InformationSubmarine Board