CONTENTS
  • Introducing RAL
  • Prov Management Framework
  • Road Network
  • Road Management Strategy
  • Priority Roads
  • Criteria for Tarring
  • Tarring Programme
  • Conclusion

3
Rationale Context
  • In 1994 over 5 000 personnel were responsible for
    roads.
  • Unskilled personnel were not proportionately
    distributed in regions/districts.
  • Excess staff in general.
  • Shortage of labourers in some regions.
  • Shortage of managers.
  • A larger portion of the budget went into salaries
    and wages.
  • Moratorium on appointment of personnel.

4
New Role
  • Road network to be repositioned to serve a new
    role.
  • Support the political agenda of democracy,
    integration and unity.
  • It must promote access to different geographic
    and cultural areas.
  • Support economic growth and development.
  • Prioritise unconnected communities.
  • Provide affordable access to areas of social and
    economic opportunities.

5
RAL Established
  • Roads Agency established to own and manage
    Provincial roads.
  • Only a small and key engineering staff was
    transferred.
  • It had to remain small and agile.
  • Rely on private sector for roads delivery.
  • No equipment, no workshops no labourers.
  • Fast procurement process and specialised staff.
  • Mandate BE DIFFERENT BE EFFICIENT

6
Shareholding
  • MEC a shareholder on behalf of government.
  • Responsible for
  • Setting strategic direction.
  • Providing the budget.
  • Approving annual business plan.
  • Shareholders Expectations
  • Maintenance of roads in acceptable condition
    relative to budget.
  • Spending the budget on time.
  • Compliance with laws, policies, and regulations.
  • Achieving business plan objectives.

7
Legal Framework
  • NPRA Provincial Roads Act 7 of 1998.
  • Gives it ownership and management of roads.
  • Planning, design, construction, maintenance,
    rehabilitation, and control.

8
Legal Framework
  • This means that
  • The provincial govt has full powers and
    responsibility over provincial roads.
  • Any legislation required has to be passed by the
    legislature.
  • The Agency has a legal responsibility as an
    owner.
  • The directors are legally answerable for its
    operations and conduct.

9
Prov Mangement Framework
  • Roads classified according to functional
    hierachy.
  • Ownership goes accordingly.
  • Each roads authority is backed by constitution
    and laws.
  • Roads have to be developed and maintained
    irrespective of ownership authority.
  • All Roads Authorities need to cooperate to
    preserve the integrity of the network.

10
Creating Prov Framework
  • Provincial roads have been classified accordingly
  • Gazzetted all as public roads.
  • Transferring some to national govt.
  • SANRAL taken about 1 500km.
  • Gazzetted the transfer of all municipal roads to
    districts.
  • Districts to agree on the classification with
    local municipalities.
  • All roads authorities have to plan together.

11
ROAD NETWORK
  • 22 062km, Only 6 638km tarred.
  • Former Transvaal better
  • Waterberg 1 995km
  • Vhembe 1 287km
  • Capricorn 867km
  • Mopani 1 181km
  • Sekhukhune 1 308km

12
ROAD MANAGEMENT STRATEGY
  • Priority is preventative maintenance to avoid
    deterioration.
  • Selective routine maintenance
  • Prioritise patching of potholes.
  • Installation and cleaning of drainage structures.
  • Selective/Spot improvements of gravel roads
  • Limited regravelling
  • Seasonal grass-cutting in some areas
  • Tarring new roads.

13
CRITERIA FOR TARRING
  • Tarring of priority roads
  • Connecting the Province.
  • Connecting North to South and East to West.
  • Creating a grid pattern.
  • 10km to a tarred road for everyone.
  • High traffic volumes (600 vehicles/day.
  • Linking settlements with areas of social and
    economic opportunities.
  • Prioritizing neglected/isolated areas.
  • Connecting mining, tourism and agricultural dev
    areas.

14
PRIORITY ROADS
  • Agricultural roads
  • 1 921km at R7.684b.
  • Overlaps with tourism roads.
  • Tourism
  • 2 771km at R11.084b.
  • Overlaps with agricultural roads.
  • Mining
  • 668km at R2 672b.
  • Hospital access roads.
  • 183.5km at R734m
  • Priority network
  • Total is 3 300km.
  • Costing R13.2b.

15
TOURISM ROADS
  • Vhembe
  • Makonde-Masisi
  • Tarring of 55km at R220m
  • 11km completed.
  • Mukula-Mhinga
  • Tarring of 33km completed.
  • N1-Vleifontein-Vuwani-Malamulele-Altein/Shangoni
    Kruger Gate.
  • Tarring 53km at R212m.
  • 28km completed
  • Tshisaulu-Donald Frazer
  • Tarring 17km at R68m.
  • 8km to be completed end March 2009.

16
TOURISM ROADS
  • Vhembe
  • Matavhela-Muswodi
  • Tarring of 27km completed.
  • Dumasi-Mavambe
  • Tarring 11km completed.
  • Vhurivhuri-Lambani-Mahagala-Mhinga-Maphophe-Bevhul
    a-Altein.
  • Tarring 65km at R260m.
  • Mutele-Sagole-Moswodi
  • Tarring 40km at R160m.

17
TOURISM ROADS
  • Vhembe
  • Tshandama-Tshixwadza-Siloam
  • Tarring 50km at R200m.
  • P135/1-Bale-Dambale-Sagole
  • Tarring 15km at R60m.
  • Total for Vhembe
  • 399km at R1 596m

18
TOURISM ROADS
  • Mopani
  • Giyani-Phalaborwa
  • Tarring 61km at R244m.
  • 34km completed.
  • Modjadji-Mokwakwaila-Bambeni-Nkomo.
  • Tarring of 56km at R224m.
  • 34km completed.
  • Giyani-Thomo-Altein
  • Tarring 15km at R60m
  • Burgersdorp-Gravellote.
  • Tarring 27km at R108m.

19
TOURISM ROADS
  • Mopani
  • Tzaneen-Letsitele.
  • Rehabilitation 64km at R256m.
  • Deerpak-Moruji
  • Tarring 19km at R76m.
  • Mooketsi-Houtbosdorp.
  • Tarring 30km at R120m.
  • Mushiyani-Dzumeri-GaMokgwathi-GaWale-Nwa-Mitwa-Mor
    utji.
  • Tarring 79km at R316m.
  • 22km to be completed end March 2009.

20
TOURISM ROADS
  • Mopani
  • Houtbosdorp-Magobaskloof.
  • Tarring of 9km at R36m.
  • Thomo-Mahlathi-Ndindani-Hlomela-Mbaula.
  • Tarring 51km at R204km.
  • Trichardtsdal-Metz.
  • Tarring 30km at R120m.
  • Timbavati Reserve
  • Tarring 11km at R44m.
  • Total for Mopani
  • 423km at R1 692m.

21
TOURISM ROADS
  • Waterberg
  • Marulaneng-Segole-GaRapadi-Marken.
  • Tarring 46km at 184m.
  • GaSeleka-Kauletsi-Abbotspoort-GaMonyeki-Mmatladi.
  • Tarring 30km at R120m.
  • Modimolle-Vaalwater-Lephalale.
  • Rehabilitating 120km at R240m.
  • Modimolle-Marble Hall.
  • Rehabilitating 83km at R166m.

22
TOURISM ROADS
  • Waterberg
  • Marble Hall-Mokopane-Groblersbrug (SANRAL).
  • Rehabilitating 189km at R378m.
  • Mokopane-Marken.
  • Rehabilitating 102km at R91.8m.
  • GaKgabudi-Bakenburg.
  • Tarring of 18km completed.
  • Dwaalboom to D1173 next to border.
  • Tarring 36km at R144m.

23
TOURISM ROADS
  • Waterberg
  • Dwaalboom to D1173 next to border.
  • Tarring 36km at R144m.
  • Swartklip Mine-Thabazimbi Rural.
  • Tarring 87km at R348m.
  • Thabazimbi-Buffelsdrift border gate
  • Tarring 77km at R308m.
  • Mookgopong-Alma-Thabazimbi.
  • Tarring 138km at R552m.

24
TOURISM ROADS
  • Waterberg
  • Mookgopong-Melkery-Marken.
  • Tarring 49km at R196m.
  • Tolwe to Road D887.
  • Tarring 31km at R124m.
  • Merekeli Natonal Park-Leeupoort.
  • Tarring 36km at R144m.
  • Road D2460-D112.
  • Tarring 23km at R92m.

25
TOURISM ROADS
  • Waterberg
  • Bela-Bela to Alma.
  • Tarring 47km at R188m.
  • GaMotlana-GaMalekwa-GaRapadi.
  • Tarring 26km at R104m.
  • Lephalle-Stockpoort border post.
  • Tarring 35km at R140m.
  • Total 1 172km at R3.664b.

26
TOURISM ROADS
  • Capricorn
  • Bochum-Blauwberg.
  • Tarring 73km at R292m.
  • Mafefe-Sekororo.
  • Tarring 68km at R272m.
  • Schiermonikoog-Kromhoek-Grootpan.
  • Tarring 68km at R272m.
  • 26km completed.
  • Polokwane-Mooketsi-Duiwelskloof.
  • Rehab of 101km at R404m.
  • Lebowakgomo-Mokopane.
  • Rehab of 70km at R63m.

27
TOURISM ROADS
  • Capricorn
  • Sekhung- My Darling.
  • Tarring 37km at R148m.
  • Bochum Vivo.
  • Tarring 24km at R96m.
  • Bochum-Mobotha-Dikgale-Mahlwareng-Manaka-Driekoppi
    es-Windhoek.
  • Tarring 78km at R312m.
  • Haenertsburg-GaMothapo.
  • Tarring 34km at R136m.
  • Total of 434km at R1.995b

28
TOURISM ROADS
  • Sekhukhune
  • Flag Boshielo Dam-Veeplats-Apel-Mmabulela.
  • Tarring 69km at R276km.
  • 47km completed.
  • Sekiti-Sehlaku-Mamphahlane.
  • Tarring 46km at R184m.
  • Penge-Mmamogolo-Motsane-Malemeko-Mafefe.
  • Tarring of 35km completed.
  • Total of 150km at R600m.
  • Total Tourism Roads 1 172km at R4.688 billion.

29
MINING ROADS
  • Dilokong Corridor (Sekhukhune)
  • Polokwane Bugerfort
  • Transferred to SANRAL
  • Needs widening
  • Flag Boshielo Dam to Apel (crossing Polokwane
    Bugersfort road.
  • Mafefe-Lekgalameetsi Nature Reserve to
    Trichardtsdal.
  • To Gravelotte, then Phalaborwa.
  • Needs tarring of 137km at R548m

30
MINING ROADS
  • Dilokong Corridor Cont
  • Atok mines to Driekop
  • 59km at R236m
  • Kromdraai-Nebo to Ga-Masha.
  • Needs taring of 35km at R140m.
  • Maololo-Mphanama-Dikobeleng to Matokomane to
    Penge.
  • Needs tarring for 69km at R276m
  • Ga-Marishane-Mathapisa kromdraai.
  • Needs tarring for 37km at R148m.

31
MINING ROADS
  • Dilokong Corridor Cont
  • Mafefe-GaMokgotho to Penge.
  • Needs tarring of 35km at R140m.
  • Sekiti-Sehlaku-GaMampuru to GaMasha.
  • Tarring 46km at R184m.

32
MINING ROADS
  • East West Sub-Corridor (Waterburg)
  • GaKgabudi-Bakenburg-Phaka to Marken
  • Tarring of 64km at R256m.
  • Lephalale to Stokpoort border post.
  • Tarring 35km at R280m.
  • GaSeleka to Shongwane.
  • Tarring 30km completed.
  • Polokwane to Gillead
  • Rehabilitating 25km at R100m

33
MINING ROADS
  • East West Cont
  • Swartklip mine to the border North-West of
    Thabazambi.
  • Tarring 87km at R348m.
  • Modimolle-Vaalwater to Lephalale.
  • Rehabilitating 120km at R240m.
  • Modimolle to Marble Hall
  • Rehabilitating 83km at R176m.
  • N11 Marble Hall-Mokopane to Groblersbrug
    (SANRAL).
  • Resealing Rehabilitating 189km at R124m.

34
MINING ROADS
  • Vhembe District
  • Makonde to Masisi (Tshikondeni Mine).
  • Tarring of 55km at R220m.
  • 11km completed.
  • Total Cost of Mining Roads
  • R2.752m for 688km

35
AGRICULTURAL ROADS
  • Vhembe
  • Dumasi-Mavambe
  • Tarring of 11km completed.
  • Tshakhuma-Phiphidi
  • Tarring 8km at R64m.
  • Mooketsi-Sekgosese-Mamaila-Magorho-Njhakanjhaka-Ma
    shau.
  • Tarring 30km completed.
  • N1-Vleifontein-Vuwani-Malamulele.
  • Tarring 53km at R212m.
  • 28km completed.

36
AGRICULTURAL ROADS
  • Mopani
  • Deerpak-Moruji (Kubjana-Madumana).
  • Tarring 19km at R76m.
  • Mooketsi-Houtbosdorp.
  • Tarring 30km at R120m.
  • Eiland-Letaba Ranch
  • Tarring 37km at R148m.
  • Burgersdorp-Gravelotte.
  • Tarring 27km at R108m.
  • Houtbosdorp-Magoebaskloof.
  • Tarring 8km at R48m.

37
AGRICULTURAL ROADS
  • Capricorn
  • Bochum-VivoTarring 24km at R96m.
  • Sekonye-Marowe-GaMantlhodi-Schaffhausen-GaMothapo-
    Sepobe-Segole.
  • Tarring 123km R492m.
  • Haenertsburg-Molepo-GaMothapo.
  • Tarring 34km at R136m.
  • Solomondale-Rita (N1) 12km at R48m.
  • Mafefe-Sekororo.
  • Tarring 68km at R272m.
  • 35km completed.
  • Moletlane.Mogoto-Elandskraal.
  • Tarring 21km to be completed end March 2009.

38
AGRICULTURAL ROADS
  • Waterberg
  • GaKgabudi-Bakenburg.
  • Tarring 18km completed.
  • Dwaalboom to D1173 next to border.
  • Tarring 36km at R144m.
  • Merekeli Natonal Park-Leeupoort.
  • Tarring 36km at R144m.
  • Bela-Bela to Alma.
  • Tarring 47km at R188m.

39
AGRICULTURAL ROADS
  • Waterberg
  • Dwaalboom to D1173 next to border.
  • Tarring 36km at R144m.
  • Swartklip Mine-Thabazimbi Rural.
  • Tarring 87km at R348m.
  • Thabazimbi-Buffelsdrift border gate
  • Tarring 77km at R308m.
  • Mookgopong-Alma-Thabazimbi.
  • Tarring 138m at R552m.

40
AGRICULTURAL ROADS
  • Sekhukhune
  • Flag Boshielo Dam-Veeplats-Apel-Mmabulela.
  • Tarring 69km at R276m.
  • 47km completed.
  • Maserumo/Nebo-Matwitwane-Ragaphela-GaMatlala-Gamme
    la-Tsimanyane-Kromdraai.
  • Tarring 35km completed.
  • Penge-Mmamogolo-Motsane-Malemeko-Mafefe.
  • Tarring 35km at R140m.
  • Maserumo-Patatswane-GaMasha.
  • Tarring 25km at R100m.
  • Total of 150km at R299m.

41
AGRICULTURAL ROADS
  • Rehabilitation
  • Modimolle-Vaalwater-Lephalale.
  • Rehabilitating 120km at R240m.
  • Modimolle-Marble Hall.
  • Rehabilitating 83km at R176m.
  • Marble Hall-Mokopane-Groblersbrug (SANRAL).
  • Rehabilitating 189km at R378m.
  • Mokopane-Marken.
  • Rehabilitating 102km at R91.8m.

42
AGRICULTURAL ROADS
  • Rehabilitation
  • Polokwane-Mooketsi-Duiwelskloof.
  • Rehabilitating 101km at R202m.
  • Lebowakgomo-Mokopane.
  • Rehabilitating 70km at R63m.
  • Tzaneen-Letsitele-Eiland.
  • Rehabilitating 64km at R58m.
  • Agric Roads 1 921km at R7.684b.

43
TARRING PROGRAMME
  • Drawn a ten-year tarring programme.
  • Total priority network is 3 300km at R13,2
    billion.
  • Developed a four-year plan.
  • Pledge to do 1 320km in 4 years.
  • Need to tar 330km pa at R1 320m.
  • Average annual budget of R500m.
  • Can only tar 125km pa.
  • Will take about 11 years to tar 1 320km.
  • Will take 26 years to tar 3 300km.
  • Backlog growing annually.

44
CONCLUSION
  • Funding not enough.
  • Increase funding to reduce backlog.
  • .End..