Title: Extreme Makeover Part II


1
Extreme Makeover Part II
  • The Nitty Gritty

2
Renovation Project Phases
  • Conceptual Design
  • Schematic Design
  • Design Development
  • Construction Documents
  • Construction
  • Occupancy

Plan temporary location
Plan move to temporary location
Plan move back to library
3
Conceptual Design
 
  • Review space allocated
  • Review adjacencies
  • Review security and sightlines

  Technology Center
 Reference Stacks
Reference Desk
Teen Zone
4
Schematic Design
  • Rooms begin to take shape
  • Furniture and equipment tested on plan
  • Cost estimate
  • Exiting and security
  • Circulation
  • Acoustics
  • Construction documents for temporary facility?

5
Design Development
  • Lighting and light control
  • HVAC
  • Power, data, and wireless
  • Mechanical system
  • Disabled access
  • Furniture and equipment reviewed
  • Cost estimate
  • Select finish materials

6
Construction Documents
  • Architect engineer coordination
  • Bidding documents
  • Furniture and equipment specifications
  • Final cost estimate
  • Specifications
  • Locate storage for library materials during
    renovation

7
The Big Decision To Move or Not to Move
  • Living in a renovation
  • Cost implications
  • Furniture and Equipment issues
  • Staff issues
  • Alternate locations

8
Delivering Service During Your Renovation
  • Close your doors
  • refer to neighboring library
  • Lease space
  • Live with it
  • open with limited service
  • Bookmobile service
  • Temporary facility

9
http//www.resuncorp.com/resun/temporary-shelter.h
tm http//www.comarkbuilding.com/modulargovernme
ntbuilding.html www.vanguardmodular.com www.mobile
modularrents.com
10
The Temp
  • Schematic, design development and construction
    documents
  • ADA compliance
  • Lighting
  • Fire and life safety
  • sprinklers
  • emergency exits and lighting
  • Signage
  • Rest rooms
  • Telephone, electrical power, network
  • Security system

11
Renovating the Temp
  • Double joists
  • Ramping for ADA
  • Interior partitions
  • Rest rooms drinking fountains
  • Carpet
  • Lighting
  • Shelving installation
  • Sprinklers

12
Scheduling the Temp
  • Order the modular units
  • Renovate the units for library use
  • Mobilize for move (www.ala.org/library/fact14.htm
    l)
  • Collections moved
  • Furniture and equipment installed
  • Signage
  • Network and systems

13
Back to Your Renovation
  • Be available
  • job walks
  • job meetings
  • requests for information (RFI)
  • submittals
  • Furniture ordered
  • Technology ordered
  • Community public relations
  • http//www.flossmoorlibrary.org/libraryupdate.htm
    (Flossmoor Library)
  • http//www.geocities.com/ncpl_2005/. (National
    City)
  • Los Angeles Public Library (fill in website)

14
Moving In Taking Occupancy
  • Professional movers
  • cost to move books
  • Approximately .25 to .50 per book with movers
  • furniture and equipment moving
  • Use of volunteers
  • use book truck
  • purchase cartons 2.00 and up
  • 20 inch cubes, 30 inch cubes

15
Furniture and Equipment Delivery
  • Include in bid documents
  • Deliver and install
  • Unpack or uncrate
  • Set in place
  • Level and gang together
  • Wipe off
  • Touch up
  • Test
  • Wire lamps and shorten cords
  • Remove debris

16
Occupancy.continued
  • Signage, graphics art work
  • Floor plans, maps publications
  • Staff orientation
  • Training in use of new equipment
  • Installation testing of technology
  • Punch list
  • Cleaning (!)