Title: Kappa Delta Phi
1Kappa Delta Phi National Affiliated
Sorority Student Calendar Project 2007- 2008
2Background Analysis
- ??F NAS was incorporated in Fort Kent, Maine in
1976. Since that historical year, ??F NAS has
molded itself into a constantly growing
scholastic - group of women whos
- number one goal is to give
- back to the community.
3Philanthropy
- Is great for our organization, but is not very
profitable, and often times drains our bank
account. - Therefore, our objective is
- to create a profitable fundraiser
- and raise at least 1,000 profit.
4The Kappa Calendar
- Will be Placed for sale on our National Website,
in a market of 3,000 others in ??F N.A.S. - The Kappa Sisters will sell calendars. They will
also be sold at the bookstore, local stores, and
gas stations.
- It will be released for the next Academic Year,
and will outfit the years of 2007- 2008. - It will include scenic pictures of the Fort Kent
Area, the University, and the Kappa Sisters. - It will have monthly coupons available for
students from businesses around town. - The calendar will also be in the form of
a personal planner. -
5Objectives
- Raise a minimum of 3,000 using Coupon sales
approach. - Raise a minimum of 1,500 using Advertisement
sales approach. - Get at least half of our materials donated.
6Objectives
- 585.00 total budgeted for Paper
- Goal 292.50
- 1800.50 total budgeted for Bindings
- Goal 900.25
- 49.98 total budgeted for Ink
- Goal 50.00
7Objectives
- Cover all estimated cost before production date
- Total Estimated Cost 2,435.48 Budget
- Amount desired before production
2,600.00 - Raise at least 2,000 from the sale of our
Calendars after covering any other costs.
8Other measures taken
- General Approach
- Constraint identification
- Personnel Needs
- Responsibility Assignment Matrix (pg. 9)
- Risk Analysis (pg 10)
9Qualitative and Quantitative Risk Assessment
- Located on page 11 and 12
- Both show that this project has a medium risk
10Risk
- High Risk
- 1. Inability to maintain scheduled time
constraints - Moderate Risk
- 2. Inability to stay within our budget
constraints - 3. Inability to fulfill talent capability
- 4. Inability to meet sales goal
- Low Risk
- 5.Editorial Constraint
- 6. Data Collection Constraint
11Mitigation Strategy
- 1. Implement strategies finding slack time, and
critical paths in order to follow the tightest
constraints possible. - 2. Do multiple budget breakdowns in order to find
the best possible options. Work on donations
also. - 3. Take a personality test that can help me place
you where you will be the most effective. - 4. Implement strategy in order to meet sales
goal. - 5. Communicate early in order to fit this
constraint into slack time or add a project
buffer. - 6. Have to generate other ways of finding
information. Via internet, library.
12Cost EstimatesTime phases Budget
13Material Budget
- Located on page 14
- Total for Paper, Bindings, and Ink
- 2,435.48
14Other important means
- Activity Duration tables page 15
- Microsoft project schedule update
15In Conclusion
- This is a project that will ultimately benefit
the sorority. - It is very low cost, even without the help of
business and material donation. - This project has medium risk, and a feasible
project schedule and fits within all of our
constraints.
16Lets check it out