Title: 1 of 11


1
Characteristics of Financeable Wind Energy
Projects
  • Northwest Power and Conservation Council
  • Workshop on Wind Energy and Electric Power
    Systems
  • December 5, 2003

Kevin J. Smith, PE Global Energy Concepts,
LLC 5729 Lakeview Dr, Suite 100 Kirkland, WA
98033 425-822-9008 ksmith_at_globalenergyconcepts.com
2
Overview
  • Wind Resource and Energy Projections
  • Land Acquisition
  • Permits and Approvals
  • Transmission/Interconnect
  • Power Purchase Agreement/Purchaser
  • Turbine Equipment/Supplier
  • O M Approach

3
Wind Resource and Energy Projections
  • Reducing Uncertainty Increases Financeability
  • Long-term, high quality on-site data to
    characterize seasonal variations and terrain
    effects
  • 10-minute turbulence and shear data
  • Hub-height?
  • Good correlation to long term reference
  • Well documented anemometry
  • Detailed and well documented analysis

4
Uncertainty Analysis
Probability of Occurrence
Net Annual Energy Production
  • Lenders focus on energy production estimate
    associated with 90 or greater confidence level
    of being exceeded.
  • Less uncertainty increases the energy
    production estimate associated with 90
    confidence level.
  • Higher energy production level increases debt
    capacity

5
Land Acquisition
  • Long term access to the land must be secured
  • Lease agreements are most common
  • Agreements must be transferable in event of
    property sale.
  • Carefully research land ownership
  • Title due diligence
  • Consider wind easement on surrounding land?

6
Permit and Approvals
  • Ensure all required local, state, and federal
    permits are in place and project is in compliance
  • Complex review and approval process can adversely
    impact projects ability to obtain financing
  • Local project acceptance concerns
  • Zoning, building permit, set back requirements

7
Transmission/Interconnect
  • Completed utility interconnection study
  • Completed grid congestion study
  • Interconnect agreement that provides long term
    and reliable access to the market

8
Power Purchase Agreement
  • Products
  • Energy, capacity, attributes, ancillary services
  • Take All when available
  • Price
  • Fixed with annual escalation (inflation)
    preferred
  • Term
  • Longer term, more likely to obtain financing
  • 20 years (expected project life)
  • Delivery
  • Scheduling requirements must accommodate
    intermittent non-dispatchable generation.
  • Lender Step-in Rights
  • Allow lender ability to assume project control to
    corrected operating deficiencies before
    termination.

9
Power Purchaser
  • Purchaser must be credit worthy B rating or
    better.
  • Not on watch list for potential downgrade
  • Parent company guaranty
  • Letter of Credit or 12 months of payments in
    escrow
  • Reputation

10
Turbine Equipment/Supplier
  • Proven turbine models with multiple year
    operation history
  • Site suitability analysis
  • Turbine certified by IEC, DNV, or GL
  • Warranty terms
  • Financial health of supplier
  • Experience and reputation of supplier in the
    industry

11
O M Approach
  • Project Owner vs. O M contractor
  • Past O M experience
  • Financial health of O M contractor
  • Attainable performance goals with penalties
  • Long term