Title: Booking
1Booking Calculations Rise Fall Method
- Staff readings usually recorded in level book /
booking form printed for that purpose - Readings have to be processed to find RLs
(usually carried out in the same book)
2- Recommended hand-held calculator / notebook
computer with spreadsheet avoid hand
calculations potential mistakes - Rise fall method one of most common booking
methods - all rise/falls computed recorded on sheet
- RL of any new station add rise to (or subtract
fall from) previous stations RL, starting from
known BM.
3Example 1. Rise fall method (staff readings in
Fig. 2.12) Table 2.2
3.729
2.518
0.556
4.153
4.212
0.718
B
CP2
Fig. 2.12
CP1
Table 2.2
BM
4From (2.3), (2.4) (2.5),
Total rise total fall Last RL first RL
- Equalities checked in last row of Table 2.2.
- Any discrepancy ? existence of arithmetic
mistake(s), but has nothing to do with accuracy
of measurements.
5Example 2. BS, FS ( IS) readings in Fig. 2.13
are booked as shown in Table
2.3
0.595
1.522
2.234
3.132
2.587
1.334
1.985
TBM
2.002
58.331m above MSL
B
A
C
D
Fig. 2.13 BS FS Observed at Stations A - D
Table 2.3
Using rise fall method, a spreadsheet can be
written to deduce RLs of points A through D as
shown in Table 2.4. (use IF MAX in Excel) you
are encouraged to reproduce Table 2.4 on Excel.
6Table 2.4
Last row of Table 2.4
Total rise total fall Last RL first RL
no mistake with arithmetic.
7Closure Error
- Definition of misclosure allowable values
- Whenever possible close on either starting
benchmark or another benchmark to check accuracy
detect blunders. Misclosure (evaluated at
closing BM) - ? measured RL of BM ?? correct RL of BM
(2.9) - If ? acceptable corrected for so that closing BM
has correct known RL
8- Max. acceptable misclosure (in mm)
- E ? C
- where K total distance of leveling route (in
number of kilometers) - C a constant typically between 2 mm (precise
leveling work of highest standards) 12 mm
(ordinary engineering leveling)
9- Somewhat empirical values can be justified by
statistical theory Bannister et al. (1998). - Construction leveling often involves relatively
short distances yet a large number (n) of
instrument stations. In this case, an alternative
criterion for E can be used - E ? D (2.10)
- 5 mm 8 mm commonly adopted values for D.
10LS Adjustment of Leveling Networks Using
Spreadsheets
Surveyors often include redundancy Fig. 2.15
leveling network associated data Arrowheads
direction of leveling e.g. Along line 1 rise
of 5.102 m from BM A to station X, i.e. RLX RLA
5.102, Along line 3 fall of 1.253 m from B
to Z, i.e. RLZ RLB 1.253. (unknown)
RLs of stations X, Y, Z lower-case letters x, y,
z.
Fig. 2.15
11- Common practice in leveling adjustments
observations assigned weights inversely
proportional to (plan) sight distances L - wi
(2.11) - i 1, 2, , 7.
- Objective determine x, y, z.
- Many different solutions
- (e.g. by loop A-X-Y-Z-A, or B-Z-Y-X-B),
- probably all differ slightly ? random errors
in data.
12- Utilize all available data weights least
squares analysis. - Note
- 7 observed elevation differences vector
- x 200.000, 207.500 x, z 207.500,
200.000 z, y x, y 207.500, z yT
13This vector can be decomposed into a matrix
product as follows
(2.12)
14- Separate unknowns from constants ? re-write
leveling information - Ax k1
k2 - where
- A coefficient matrix of 0s 1s on RHS of
(2.12), - k1 last vector in (2.12) containing benchmark
values, - k2 5.102, 2.345, -1.253, -6.132, -0.683,
-3.002, 1.703T. - Problem now in Ax k form,
- where k k2 k1,
- weight matrix W Diag 1/40,1/30,1/30,1/30,1/20,1
/20,1/20
15- Problem treated in Ch.1
- Solution (1.5) ?numerical matrix computations
- Spreadsheet method
- fast, easy to learn, highly portable
- instant, automatic recalc. if s in problem
changed (common situation in surveying updating
of control coordinates, discovery of mistakes,
etc.).
16- Spreadsheet shown in Table 2.6. Note
- computed s in Table 2.6 do not necessarily show
all d.p. ? paper space limitations (all
computations full accuracy). - Format Cells Number Decimal places to
display only desired number of d.p. (computations
always carry full accuracy). - Select any cell in matrix ? ctrl - ? whole
matrix selected (matrix must be completely
surrounded by blank border) - See Table 2.6 steps to be carried out on
spreadsheet
17(No Transcript)
18Table 2.6 Performing LS Adjustment of Leveling
Network on a Spreadsheet
Most probable RLs for stations X, Y, Z 205.148
m, 204.482 m, 206.188 m, respectively.
19Contours
- Contour lines best method to show height
variations on a plan - Contour line drawn on a plan
- a line joining equal altitudes
- Elevations indicated on plan
- tidemarks left by a flood that fell at a
discrete contour interval.
20- Fig. 2.16 plan section of an island
- contour line of 0 meter value tidemark left by
the sea - Ascending at 10 m contour intervals a series of
imaginary horizontal planes passing through
island ? contours with values of 10 m, 20 m, 30
m, 40 m, at their points of contact with
island.
21Fig. 2.16
22- Fig. 2.16 gradient of the ground between A C
- Gradient along AC
1 in 6 - Similarly,
- Gradient along DE
1 in 3 - regions where contours are more closely packed
have steeper slopes - a contour line is continuous closed on itself,
although the plan may not have sufficient room to
show. - Height of any point unique ? two contour lines
of different values cannot cross or meet, except
for a cliff / overhang.
23- Contouring laborious. One direct method
- BM (30.500 m above HKPD) sighted, back sight
0.500 m ? height of instrument (HI) 31.000m. - Staff reading 1.000 m ? staffs bottom at 30-m
contour level - Staff then taken throughout site, and at every
1.000 m reading, point is pegged for subsequent
determination of its E, N coordinates by another
appropriate survey technique ? 30-m contour
located. - Similarly, a staff reading 2.000 m ? a point on
9-m contour so on. - Tedious uneconomical for large area
- Suitable in construction projects requiring
excavation to a specific single contour line.
24Trigonometric Leveling
Discussion so far differential leveling may not
be practical for large
elevations (e.g. tall buildings height)
trigonometric leveling ( heighting) basic
procedure
25- rough estimate of h, e.g. residential buildings
h ? (number of stories ? 3 m). - Useful for checking result later, also a good
separation (if possible) between instrument
building (why?). - If taping horizontal distance AB from instrument
to building obtained directly. Alternatively EDM
at A reflector at some point B directly above
/ below B slope distance AB zenith angle ? AB
BB computed. Also, vertical distance BG (or
prism height BG) to base of building by a staff
/ tape.
26- Raise telescope to sight building top, measure ?v
precisely. - Note most theodolites give zenith angle ?z,
vertical angle ?v 90? ?z. - Height of building PG AB tan ?v BG (where BG
BG BB if EDM was used).
27Modern Instruments
- Many total stations built-in Remote Elevation
Measurement (REM) mode expedites trigonometric
leveling - Sight point B (Fig. 2.17) once distance
zenith angle measured stored. - As one raises / lowers telescope ? corresponding
height of new sighted point calculated
displayed automatically. - Reflector to be placed at B (usually
prism on top of a held pole)
28- Difficulties
- People walking outside base of building may block
prism - Reflectorless total station EDM laser beam can
be reflected back from suitable building surfaces
(e.g. white walls) w/o prism. Fig. 2.18(b) ? can
sight any convenient point B along PG (see Fig.
2.17) w/o prism, - Only limitations lasers maximum range
(typically 100 m) type of buildings surface
(certain absorbing/ dark surfaces may not work).
29- Sighting top of tall building ? steep vertical
angles ? telescope points almost straight up ?
reading eyepiece becomes difficult to view - Diagonal eyepiece provides extension of eyepiece
allows comfortable viewing from the side Fig.
2.18(a).
(a) A Diagonal Eyepiece (b) Nikon NPL-820
Reflectorless Total Station
Fig. 2.18
Leveling fieldwork time-consuming error-prone,
especially for staff reading by eye.
30- Digital levels (DL)
- capable of electronic image processing.
- Require specially made staffs with bar codes on
one side conventional graduations on the other.
- Observer directs telescope onto staffs bar-coded
side focuses on it, as done in conventional
leveling. - By pressing a key DL reads bar codes
determines corresponding staff reading,
displaying result on a panel. - Eliminate booking errors expedite leveling work
- Can be used in conventional way also.
31Standard error for DL typically sighting distance 100 m Observation
range typical upper limit 100 m, lower limit
2 m.
(a) Topcon DL-103 Digital Level (b)
Bar-coded side of a staff
Fig. 2.19