Booking - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

Booking

Description:

Table 2.6 Performing LS Adjustment of Leveling Network on a Spreadsheet ... Fig. 2.16: plan & section of an island. contour line of 0 meter value: 'tidemark ... – PowerPoint PPT presentation

Number of Views:132
Avg rating:3.0/5.0
Slides: 32
Provided by: thom6
Category:
Tags: booking | island | ls

less

Transcript and Presenter's Notes

Title: Booking


1
Booking Calculations Rise Fall Method
  • Staff readings usually recorded in level book /
    booking form printed for that purpose
  • Readings have to be processed to find RLs
    (usually carried out in the same book)

2
  • Recommended hand-held calculator / notebook
    computer with spreadsheet avoid hand
    calculations potential mistakes
  • Rise fall method one of most common booking
    methods
  • all rise/falls computed recorded on sheet
  • RL of any new station add rise to (or subtract
    fall from) previous stations RL, starting from
    known BM.

3
Example 1. Rise fall method (staff readings in
Fig. 2.12) Table 2.2
3.729
2.518
0.556
4.153
4.212
0.718
B
CP2
Fig. 2.12
CP1
Table 2.2
BM
4
From (2.3), (2.4) (2.5),
Total rise total fall Last RL first RL
  • Equalities checked in last row of Table 2.2.
  • Any discrepancy ? existence of arithmetic
    mistake(s), but has nothing to do with accuracy
    of measurements.

5
Example 2. BS, FS ( IS) readings in Fig. 2.13
are booked as shown in Table
2.3
0.595
1.522
2.234
3.132
2.587
1.334
1.985
TBM
2.002
58.331m above MSL
B
A
C
D
Fig. 2.13 BS FS Observed at Stations A - D
Table 2.3
Using rise fall method, a spreadsheet can be
written to deduce RLs of points A through D as
shown in Table 2.4. (use IF MAX in Excel) you
are encouraged to reproduce Table 2.4 on Excel.
6
Table 2.4
Last row of Table 2.4
Total rise total fall Last RL first RL
no mistake with arithmetic.
7
Closure Error
  • Definition of misclosure allowable values
  • Whenever possible close on either starting
    benchmark or another benchmark to check accuracy
    detect blunders. Misclosure (evaluated at
    closing BM)
  • ? measured RL of BM ?? correct RL of BM
    (2.9)
  • If ? acceptable corrected for so that closing BM
    has correct known RL

8
  • Max. acceptable misclosure (in mm)
  • E ? C
  • where K total distance of leveling route (in
    number of kilometers)
  • C a constant typically between 2 mm (precise
    leveling work of highest standards) 12 mm
    (ordinary engineering leveling)

9
  • Somewhat empirical values can be justified by
    statistical theory Bannister et al. (1998).
  • Construction leveling often involves relatively
    short distances yet a large number (n) of
    instrument stations. In this case, an alternative
    criterion for E can be used
  • E ? D (2.10)
  • 5 mm 8 mm commonly adopted values for D.

10
LS Adjustment of Leveling Networks Using
Spreadsheets
Surveyors often include redundancy Fig. 2.15
leveling network associated data Arrowheads
direction of leveling e.g. Along line 1 rise
of 5.102 m from BM A to station X, i.e. RLX RLA
5.102, Along line 3 fall of 1.253 m from B
to Z, i.e. RLZ RLB 1.253. (unknown)
RLs of stations X, Y, Z lower-case letters x, y,
z.
Fig. 2.15
11
  • Common practice in leveling adjustments
    observations assigned weights inversely
    proportional to (plan) sight distances L
  • wi
    (2.11)
  • i 1, 2, , 7.
  • Objective determine x, y, z.
  • Many different solutions
  • (e.g. by loop A-X-Y-Z-A, or B-Z-Y-X-B),
  • probably all differ slightly ? random errors
    in data.

12
  • Utilize all available data weights least
    squares analysis.
  • Note
  • 7 observed elevation differences vector
  • x 200.000, 207.500 x, z 207.500,
    200.000 z, y x, y 207.500, z yT

13
This vector can be decomposed into a matrix
product as follows
(2.12)

14
  • Separate unknowns from constants ? re-write
    leveling information
  • Ax k1
    k2
  • where
  • A coefficient matrix of 0s 1s on RHS of
    (2.12),
  • k1 last vector in (2.12) containing benchmark
    values,
  • k2 5.102, 2.345, -1.253, -6.132, -0.683,
    -3.002, 1.703T.
  • Problem now in Ax k form,
  • where k k2 k1,
  • weight matrix W Diag 1/40,1/30,1/30,1/30,1/20,1
    /20,1/20

15
  • Problem treated in Ch.1
  • Solution (1.5) ?numerical matrix computations
  • Spreadsheet method
  • fast, easy to learn, highly portable
  • instant, automatic recalc. if s in problem
    changed (common situation in surveying updating
    of control coordinates, discovery of mistakes,
    etc.).

16
  • Spreadsheet shown in Table 2.6. Note
  • computed s in Table 2.6 do not necessarily show
    all d.p. ? paper space limitations (all
    computations full accuracy).
  • Format Cells Number Decimal places to
    display only desired number of d.p. (computations
    always carry full accuracy).
  • Select any cell in matrix ? ctrl - ? whole
    matrix selected (matrix must be completely
    surrounded by blank border)
  • See Table 2.6 steps to be carried out on
    spreadsheet

17
(No Transcript)
18
Table 2.6 Performing LS Adjustment of Leveling
Network on a Spreadsheet
Most probable RLs for stations X, Y, Z 205.148
m, 204.482 m, 206.188 m, respectively.
19
Contours
  • Contour lines best method to show height
    variations on a plan
  • Contour line drawn on a plan
  • a line joining equal altitudes
  • Elevations indicated on plan
  • tidemarks left by a flood that fell at a
    discrete contour interval.

20
  • Fig. 2.16 plan section of an island
  • contour line of 0 meter value tidemark left by
    the sea
  • Ascending at 10 m contour intervals a series of
    imaginary horizontal planes passing through
    island ? contours with values of 10 m, 20 m, 30
    m, 40 m, at their points of contact with
    island.

21
Fig. 2.16
22
  • Fig. 2.16 gradient of the ground between A C
  • Gradient along AC
    1 in 6
  • Similarly,
  • Gradient along DE
    1 in 3
  • regions where contours are more closely packed
    have steeper slopes
  • a contour line is continuous closed on itself,
    although the plan may not have sufficient room to
    show.
  • Height of any point unique ? two contour lines
    of different values cannot cross or meet, except
    for a cliff / overhang.

23
  • Contouring laborious. One direct method
  • BM (30.500 m above HKPD) sighted, back sight
    0.500 m ? height of instrument (HI) 31.000m.
  • Staff reading 1.000 m ? staffs bottom at 30-m
    contour level
  • Staff then taken throughout site, and at every
    1.000 m reading, point is pegged for subsequent
    determination of its E, N coordinates by another
    appropriate survey technique ? 30-m contour
    located.
  • Similarly, a staff reading 2.000 m ? a point on
    9-m contour so on.
  • Tedious uneconomical for large area
  • Suitable in construction projects requiring
    excavation to a specific single contour line.

24
Trigonometric Leveling
Discussion so far differential leveling may not
be practical for large
elevations (e.g. tall buildings height)
trigonometric leveling ( heighting) basic
procedure
25
  • rough estimate of h, e.g. residential buildings
    h ? (number of stories ? 3 m).
  • Useful for checking result later, also a good
    separation (if possible) between instrument
    building (why?).
  • If taping horizontal distance AB from instrument
    to building obtained directly. Alternatively EDM
    at A reflector at some point B directly above
    / below B slope distance AB zenith angle ? AB
    BB computed. Also, vertical distance BG (or
    prism height BG) to base of building by a staff
    / tape.

26
  • Raise telescope to sight building top, measure ?v
    precisely.
  • Note most theodolites give zenith angle ?z,
    vertical angle ?v 90? ?z.
  • Height of building PG AB tan ?v BG (where BG
    BG BB if EDM was used).

27
Modern Instruments
  • Many total stations built-in Remote Elevation
    Measurement (REM) mode expedites trigonometric
    leveling
  • Sight point B (Fig. 2.17) once distance
    zenith angle measured stored.
  • As one raises / lowers telescope ? corresponding
    height of new sighted point calculated
    displayed automatically.
  • Reflector to be placed at B (usually
    prism on top of a held pole)

28
  • Difficulties
  • People walking outside base of building may block
    prism
  • Reflectorless total station EDM laser beam can
    be reflected back from suitable building surfaces
    (e.g. white walls) w/o prism. Fig. 2.18(b) ? can
    sight any convenient point B along PG (see Fig.
    2.17) w/o prism,
  • Only limitations lasers maximum range
    (typically 100 m) type of buildings surface
    (certain absorbing/ dark surfaces may not work).

29
  • Sighting top of tall building ? steep vertical
    angles ? telescope points almost straight up ?
    reading eyepiece becomes difficult to view
  • Diagonal eyepiece provides extension of eyepiece
    allows comfortable viewing from the side Fig.
    2.18(a).

(a) A Diagonal Eyepiece (b) Nikon NPL-820
Reflectorless Total Station
Fig. 2.18
Leveling fieldwork time-consuming error-prone,
especially for staff reading by eye.
30
  • Digital levels (DL)
  • capable of electronic image processing.
  • Require specially made staffs with bar codes on
    one side conventional graduations on the other.
  • Observer directs telescope onto staffs bar-coded
    side focuses on it, as done in conventional
    leveling.
  • By pressing a key DL reads bar codes
    determines corresponding staff reading,
    displaying result on a panel.
  • Eliminate booking errors expedite leveling work
  • Can be used in conventional way also.

31
Standard error for DL typically sighting distance 100 m Observation
range typical upper limit 100 m, lower limit
2 m.

(a) Topcon DL-103 Digital Level (b)
Bar-coded side of a staff
Fig. 2.19
Write a Comment
User Comments (0)
About PowerShow.com