Title: Transition from the Construction Project to PreOps and Operations


1
Transition from the Construction Project to
Pre-Ops and Operations
  • Howard Gordon

2
The ATLAS Experiment Very International!
ATLAS Collaboration(Status October
2002) Albany, Alberta, NIKHEF Amsterdam,
Ankara, Ann Arbor, LAPP Annecy, Argonne NL,
Arizona, Arlington UT, Athens, NTU Athens, Baku,
IFAE Barcelona, Bergen, Berkeley LBL and UC,
Bern, Birmingham, Bonn, Boston, Brandeis,
Bratislava/SAS Kosice, Brookhaven NL, Bucharest,
Cambridge, Carleton/CRPP, Casablanca/Rabat, CERN,
Chinese Cluster, Chicago, Clermont-Ferrand,
Columbia, NBI Copenhagen, Cosenza, INP Cracow,
FPNT Cracow, Dortmund, JINR Dubna, Duke,
Frascati, Freiburg, Geneva, Genoa, Glasgow, ISN
Grenoble, Technion Haifa, Hampton, Harvard,
Heidelberg, Helsinki, Hiroshima, Hiroshima IT,
Indiana, Innsbruck, Iowa SU, Irvine UC, Istanbul
Bogazici, KEK, Kobe, Kyoto, Kyoto UE, Lancaster,
Lecce, Lisbon LIP, Liverpool, Ljubljana, QMW
London, RHBNC London, UC London, Lund, UA Madrid,
Mainz, Manchester, Mannheim, CPPM Marseille,
MIT, Melbourne, Michigan SU, Milano, Minsk NAS,
Minsk NCPHEP, Montreal, FIAN Moscow, ITEP
Moscow, MEPhI Moscow, MSU Moscow, Munich LMU, MPI
Munich, Nagasaki IAS, Naples, Naruto UE, New
Mexico, Nijmegen, Northern Illinois, BINP
Novosibirsk, Ohio SU, Okayama, Oklahoma, LAL
Orsay, Oslo, Oxford, Paris VI and VII, Pavia,
Pennsylvania, Pisa, Pittsburgh, CAS Prague, CU
Prague, TU Prague, IHEP Protvino, Ritsumeikan,
UFRJ Rio de Janeiro, Rochester, Rome I, Rome II,
Rome III, Rutherford Appleton Laboratory, DAPNIA
Saclay, Santa Cruz UC, Sheffield, Shinshu,
Siegen, Southern Methodist, NPI Petersburg,
Stockholm, KTH Stockholm,Stony Brook, Sydney, AS
Taipei, Tbilisi, Tel Aviv, Thessaloniki, Tokyo
ICEPP, Tokyo MU, Tokyo UAT, Toronto, TRIUMF,
Tsukuba, Tufts, Udine, Uppsala, Urbana UI,
Valencia, UBC Vancouver, Victoria, Washington,
Weizmann Rehovot, Wisconsin, Wuppertal,
Yerevan (149 Institutions)
The scientific author list has been updated (as
of 30th September), as this will be done now
yearly for the purpose of the MO A
sharing Total Scientific Authors 1594 Scientific
Authors holding a PhD or equivalent 1305 (used
for MO A sharing)
3
U.S. ATLAS Institutions
BNL is the Host Laboratory
4
UX15 civil engineering
Status mid October 2002
5
Barrel Cryostat ready for insertion
  • Pressure test with final seals successful
  • First EM wheel ready
  • All 64 FTs produced, installation in
    cryostat finished, all tested
  • Ready for insertion

6
U.S. ATLAS Budget Authority
7
Definitions for the Research Program
  • U.S. ATLAS Research Program is needed to support
    the ATLAS Experiment and especially our
    deliverables. It includes
  • Maintenance and Operations (MO) which includes
  • Pre-operations all activities until operations
  • Operations Beams-on time 8 months/year
  • Maintenance Ongoing plus Beams-off time every
    1-2 years of 4 months
  • Upgrade RD
  • Upgrade RD is envisaged for the luminosity
    upgrade of the LHC 1035 cm-1 s-1
  • New more radiation hardened electronics Pixels,
    Silicon Strips, LAr Front End Boards (FEB), LAr
    ROD upgrade, etc.
  • Physics and Computing
  • Installation (defined as inserting the U.S. ATLAS
    deliverable into ATLAS) is part of the
    Construction Project

8
Research Program Needs
9
U.S. ATLAS Personnel
10
U.S. ATLAS Skill Mix
11
US ATLAS - Tier 1 Facility Staffing
12
Scientific Effort on ATLAS
US ATLAS effort will ramp up by a factor 2 by
FY07 in anticipation of first LHC beam
13
U.S. ATLAS Project Management Plan
14
Separate MOUs for the Construction Project and
Research Program
15
Needs from BNL
  • Understanding of the Research Contracts to
    universities
  • Needs for some transfers of funds to CERN
    Category A B MO
  • Plans to increase the DOE base funding for the
    ATLAS Physics Analysis Center